← All cases

[2024] NSWSC 1555

Claire Rewais and Osama Rewais t/as McVitty Grove v BPB Earthmoving Pty Ltd (No 2)

(1) Order (2) made on 10 October 2024 in these proceedings is varied to take the following form: The plaintiffs are to pay the first defendant’s costs of the proceedings. (2) Order that the first defendant pay the plaintiffs’ costs of the application. (3) The first defendant’s application for indemnity costs is dismissed.

Catchwords

COSTS — where successful party seeks indemnity costs — purported Calderbank offer — whether unreasonable for unsuccessful party to reject offer — HELD — offer not take effect as a Calderbank offer — not unreasonable for unsuccessful party to reject offer — variation to costs order to correct naming of first defendant COSTS — unsuccessful application for indemnity costs — costs follow the event — HELD — first defendant to pay the plaintiffs’ costs of application

Cases cited

  • Abdi v Abdi (No 2)[2022] NSWSC 582
  • A-Civil Aust Pty Ltd v Ceerose Pty Ltd[2023] NSWCA 144
  • Brodyn Pty Ltd t/as Time Cost and Quality v Davenport (2004) 61 NSWLR 421;[2004] NSWCA 394
  • Calderbank v Calderbank [1975] 3 All ER 333
  • Claire Rewais and Osama Rewais t/as McVitty Grove v BPB Earthmoving Pty Ltd[2024] NSWSC 1271
  • Commonwealth of Australia v Gretton[2008] NSWCA 117
  • Oshlack v Richmond River Council (1998) 193 CLR 72;[1998] HCA 11
  • SMEC Testing Services Pty Ltd v Campbelltown City Council[2000] NSWCA 323
  • Treloar Constructions Pty Ltd v McMillan (No 2)[2017] NSWCA 146
  • Vale v Eggins (No 2)[2007] NSWCA 12
  • Whitney v Dream Developments (2013) 84 NSWLR 311;[2013] NSWCA 188

Legislation cited

  • Building and Construction Industry Security of Payment Act 1999 (NSW) § 25(4)(b)
  • Civil Procedure Act 2005 (NSW) § 98
  • Home Building Act 1989 (NSW)
  • Uniform Civil Procedure Rules 2005 (NSW) § 36.16, 42.1, 42.2, 42.4

Judgment

INTRODUCTION

  1. [1]

    This judgment concerns the issue of costs arising from the judgment I delivered on 10 October 2024 in Claire Rewais and Osama Rewais t/as McVitty Grove v BPB Earthmoving Pty Ltd [2024] NSWSC 1271 (Principal Judgment). This judgment assumes familiarity with, and adopts the shorthand expressions and defined terms used in, the Principal Judgment.

  2. [2]

    In the Principal Judgment I determined the application made by the plaintiffs, Mrs Claire Rewais and Dr Osama Rewais trading as McVitty Grove (the Rewaises), in relation to the adjudication determination made under the Building and Construction Industry Security of Payment Act 1999 (NSW) on 7 July 2024 (Determination) by the second defendant, Mr Christopher Larcos, as adjudicator (Adjudicator). In the Determination, the Adjudicator held that the Rewaises owed the first defendant, BPB Earthmoving Pty Ltd, $277,007.16 in respect of building works and earthworks carried out by BPB at the Rewaises’ property in Woodlands, New South Wales (Property).

  3. [3]

    In the Rewaises’ application, they sought a declaration that the Determination was void, an order quashing it and an order permanently restraining BPB from enforcing it.

  4. [4]

    For the reasons set out in the Principal Judgment, in summary I concluded that:

    1. (1)

      The payment claim was not served by email in accordance with s 31(1)(d) of the Security of Payment Act and the Adjudicator was incorrect to conclude that the payment claim was served on 24 April 2024, but the payment claim was served on 11 June 2024 when the Rewaises were first made aware of it (Principal Judgment at [140]–[145]).

    2. (2)

      The s 17(2) notice was not served by email in accordance with s 31(1)(d) of the Security of Payment Act, the 17(2) notice was also not served in accordance with the requirements of s 31(1)(c) of the Security of Payment Act because it was sent by post addressed to the Rewaises’ residence and not the Rewaises’ ordinary place of business and it is to be regarded as having been received on 11 June 2024 (Principal Judgment at [146]–[150]).

    3. (3)

      Although BPB’s adjudication application was filed prematurely, the Determination is not void and will not be quashed on this basis (Principal Judgment at [164]–[170]).

    4. (4)

      The entire Property is a dwelling and the Contract is a contract for residential building work to which the Home Building Act 1989 (NSW) (HBA) applied (Principal Judgment at [205]–[214]).

    5. (5)

      As BPB did not have the required licence or insurance policy under the HBA, it has breached ss 4 and 92 of the HBA (Principal Judgment at [215]).

    6. (6)

      BPB is not barred by either ss 10 or 94 of the HBA from enforcing the Determination, by reason of their failure to comply with the licensing and insurance requirements of the HBA (Principal Judgment at [216]–[219] and [222]).

  5. [5]

    On 10 October 2024, I made orders in the Principal Judgment dismissing the summons filed 15 July 2024 by the plaintiffs and for the plaintiffs to pay the defendant’s costs of the proceedings.

  6. [6]

    On 21 October 2024, BPB filed a notice of motion seeking to vary the costs order I made in the Principal Judgment pursuant to rr 36.16(1) and (3A) of the Uniform Civil Procedure Rules 2005 (NSW) (UCPR).

  7. [7]

    In summary, the orders sought by BPB with respect to costs on the application which was the subject of the Principal Judgment and this application are as follows:

    1. (1)

      The Rewaises are to pay BPB’s costs of the proceedings on an ordinary basis up to 13 August 2024 and on an indemnity basis from 14 August 2024.

    2. (2)

      The Rewaises are to pay BPB’s costs of this application on an indemnity basis.

  8. [8]

    The Rewaises oppose these orders.

  9. [9]

    For the reasons set out below, I have concluded that BPB’s application for indemnity costs should be dismissed and there should be no change to the costs order I made on 10 October 2024 other than to correct the reference from “defendant” to “first defendant” to make clear that it is only BPB which is the subject of that costs order.

RELEVANT FACTS

  1. [10]

    The relevant facts underlying the Rewaises’ application are set out in full in the Principal Judgment at [7]–[108]. Set out below are additional facts that are not mentioned in the Principal Judgment but are relevant for the purposes of determining the issue of costs.

  2. [11]

    On 14 August 2024 at 6:15pm, BPB’s solicitors, Stacks, sent a letter to the Rewaises’ solicitors, Agility Legal, (14 August letter) headed “WITHOUT PREJUDICE, SAVE AS TO COSTS” setting out the factual bases upon which BPB had formed the view that the Contract was not for residential building work, asserting that the starting premise of the Rewaises’ whole argument (namely that the Contract was entered into in breach of the HBA) was wrong. In addition, the 14 August letter also stated that Brodyn Pty Ltd t/as Time Cost and Quality v Davenport (2004) 61 NSWLR 421; [2004] NSWCA 394 at [82]–[83] is authority for the proposition that BPB’s:

  3. [12]

    The 14 August letter then expressed an offer in the following terms:

  4. [13]

    The 14 August letter stipulated that BPB’s offer had been structured with the following matters in mind:

  5. [14]

    The 14 August letter concluded by noting that the offer was open for written acceptance by the Rewaises until 4:00pm on Friday 16 August 2024, after which it would lapse, and further stating:

  6. [15]

    The Rewaises did not accept BPB’s offer contained in the 14 August letter.

  7. [16]

    In accordance with the directions made by Ball J on 19 July 2024, BPB had until 16 August 2024 to serve any evidence on which it intended to rely at the hearing. BPB’s evidence was then provided in the form of one affidavit of 15 August 2024, two affidavits of 16 August 2024, four affidavits of 17 August 2024, one affidavit of 20 August 2024 and one affidavit of 22 August 2024.

LEGAL PRINCIPLES

  1. [17]

    Rule 36.16 of the UCPR relevantly provides that the court has power to set aside a judgment or order in the following circumstances:

  2. [18]

    The principal statutory provision containing the court’s powers as to costs is s 98 of the Civil Procedure Act 2005 (NSW) (CPA), which relevantly states:

  3. [19]

    The discretion to award costs under s 98 of the CPA is broad and the section itself is to be construed liberally: Oshlack v Richmond River Council (1998) 193 CLR 72; [1998] HCA 11, Gaudron and Gummow JJ at [21]. The discretion is, however, subject to the rules of court, including the UCPR.

  4. [20]

    Rules 42.1, 42.2 and 42.4 of the UCPR relevantly provide:

  5. [21]

    A number of observations regarding the exercise of the discretion to award costs made by McHugh J in Oshlack at [67]–[68] should be kept in mind, as summarised below:

    1. (1)

      An award of costs rests on fairness between the parties, with the unsuccessful party bearing the liability for the costs of the proceedings.

    2. (2)

      The primary purpose of an award of costs is to indemnify the successful party, not to punish an unsuccessful party because, had the proceedings not been brought, the successful party would not have incurred the expense of them.

    3. (3)

      As a matter of policy, one beneficial by-product of the compensatory purpose may well be to instil in a party contemplating commencing the proceedings a sober realisation of the potential financial expense involved.

  6. [22]

    The principles relating to the awarding of indemnity costs based on the failure of a party to accept an offer of compromise contained in a Calderbank letter were set out in SMEC Testing Services Pty Ltd v Campbelltown City Council [2000] NSWCA 323, Giles JA at [37] saying:

  7. [23]

    In Commonwealth of Australia v Gretton [2008] NSWCA 117, Beazley JA (Mason P agreeing and Hodgson JA substantially agreeing) at [44]–[45] indicated that there are two general requirements to justify making an order for costs on an indemnity basis following a Calderbank offer, stating:

  8. [24]

    In Whitney v Dream Developments (2013) 84 NSWLR 311; [2013] NSWCA 188, Barrett JA (Beazley P and McColl JA agreeing) at [57]–[60], in making additional remarks to the reasons of Bathurst CJ, considered several matters relevant to the determination of whether an offer took effect as a Calderbank offer, noting that it is crucial to determine the manifested objective intention of the offeror, stating:

  9. [25]

    In Dream Developments, Bathurst CJ (Beazley P and McColl JA agreeing) at [42] concluded that the essence of a Calderbank offer is an intention that the offer (or the circumstances in which it was conveyed) indicated that it would be relied on in relation to costs, should a verdict more favourable than the offer be achieved, saying:

  10. [26]

    In Abdi v Abdi (No 2) [2022] NSWSC 582, Ward P at [27]–[30] provided a statement of the principles relating to an award of indemnity costs following the rejection of a Calderbank offer as follows:

SUBMISSIONS

  1. [27]

    The submissions of BPB can be summarised as follows:

    1. (1)

      The reference in the order that the plaintiffs are to pay the defendant’s costs of the proceedings (Principal Judgment at [223]) is probably a reference to the first defendant’s costs because the second defendant filed a submitting appearance.

    2. (2)

      Within the time contemplated by r 36.16(3A) of the UCPR, BPB filed the notice of motion seeking to vary the costs order in the Principal Judgment. Although the motion refers to “the defendants’ costs”, the motion is only intended to be directed towards the costs of BPB as the first defendant.

    3. (3)

      The 14 August letter is a Calderbank letter containing a sophisticated offer to settle the present litigation and bears reading in full. The substance of the proposal includes:

    4. (4)

      By way of further explanation, BPB’s offer provided a solution to the “interim” dispute, being the question of validity of the Determination, on the basis of an “interim” monetary concession by BPB of $67,000 on the adjudication amount (from $277,000 to $210,000). The reference to the concession as being “interim” is made on the basis of sub-paragraph (d) of the offer in the 14 August letter. Additionally, the Rewaises would have the option to decide whether to accept BPB’s monetary concession as finally determining the dispute between them, or alternatively bringing proceedings to finally determine the parties’ respective rights. Meanwhile, the Rewaises would not be out of pocket (on the ordinary basis at least) in respect of the costs of the “interim” dispute.

    5. (5)

      The proposed “interim” concession is less than the amount the Rewaises would have been required to pay into court had the Rewaises applied to set aside the judgment, referring to s 25(4)(b) of the Security of Payment Act; or, as a matter of “established practice” to stay enforcement of the adjudication determination, citing A-Civil Aust Pty Ltd v Ceerose Pty Ltd [2023] NSWCA 144 at [15].

    6. (6)

      As indicated in the 14 August letter, the offer was a sensible attempt to resolve the “interim” dispute while leaving the Rewaises with the option to further agitate their “final” rights if they chose. The rejection by the Rewaises of the offer has done little other than prolong the substantive dispute between the parties and increase costs. The apparent likelihood is that one party or the other will be commencing proceedings to determine their separate rights, which could already be on foot if the Rewaises had accepted BPB’s Calderbank offer. In this context, the Rewaises’ rejection of the offer was unreasonable and they bear the responsibility for the costs incurred in these proceedings, citing Gretton at [121].

    7. (7)

      The result of the proceedings is more favourable to BPB than the proposed settlement, as it is open to BPB to enforce the full amount of the judgment debt, less any amounts which may have already been recovered.

    8. (8)

      If the court accepts that the Rewaises’ rejection of BPB’s offer was unreasonable and the result of the proceedings is more favourable to BPB than the proposed settlement, then the court should exercise its costs discretion to make an order for BPB’s costs on an indemnity basis rather than the ordinary basis.

  2. [28]

    The submissions of the Rewaises can be summarised as follows:

    1. (1)

      The offer made by BPB listed two different sums of $220,822 at sub-paragraph (c) and $220,000 at sub-paragraph (d) of the 14 August letter and so the actual terms and sum of the settlement offer are unclear.

    2. (2)

      BPB’s offer was not strictly a Calderbank offer and should not be considered as one for the following reasons:

    3. (3)

      The court has discretion as to costs, citing s 98 of the CPA. The discretion to award costs under a Calderbank letter falls within this jurisdiction. Unlike the process in relation to an offer of compromise as outlined in the UCPR, there is no presumptive entitlement to costs resulting from a Calderbank letter, citing Abdi at [26].

    4. (4)

      The making and rejection of a Calderbank offer is one factor which may, but will not necessarily, cause the court in its discretion to order costs on the indemnity basis. The rejection of a Calderbank offer may cause the court to make such an order if it is satisfied that the offer was a genuine offer of compromise and that the rejection of the offer was unreasonable, citing Treloar Constructions Pty Ltd v McMillan (No 2) [2017] NSWCA 146 at [8]–[9].

    5. (5)

      The onus of demonstrating that the Rewaises’ rejection of BPB’s offer was unreasonable in all the circumstances rests on BPB, citing Abdi at [27].

    6. (6)

      In relation to the factors to which a court will have regard when considering whether the rejection of the offer was unreasonable, citing Abdi at [29], the following points are noted:

    7. (7)

      It was reasonable to reject BPB’s offer, made on the premise that the Rewaises were wrong in stating that the Contract was entered into in breach of the HBA, a position which was correct and ultimately established at the trial. Although the Rewaises were ultimately unsuccessful at trial, they were successful in establishing that BPB was in fact in breach of ss 4 and 92 of the HBA. Contrary to the 14 August letter, the Rewaises were correct to assert that “the Contract was entered into in breach of the HBA” and it was reasonable for the Rewaises to consider that BPB’s view was incorrect when assessing the offer.

CONSIDERATION

  1. [29]

    In my opinion, for many of the reasons put forward by the Rewaises, the 14 August letter does not give cause for me to vary the costs order that I made on 10 October 2024. Importantly, those reasons which I regard as having the greatest weight in arriving at this decision are as follows:

    1. (1)

      While BPB indicated in the 14 August letter that it was written “without prejudice, save as to costs”, that it was made pursuant to the principles of Calderbank v Calderbank and that, in the event the offer was not accepted and the matter proceeded to hearing, BPB would tender a copy of the 14 August letter in support of any application for indemnity costs, it was missing the essence of a Calderbank offer. As made plain in SMEC Testing at [37] and Dream Developments at [60], that essence of a Calderbank offer is that it “would be relied on in relation to the question of costs should a verdict more favourable than the offer be achieved”. There is no such statement in the 14 August letter.

    2. (2)

      The 14 August letter refers to two inconsistent sums in the offer — $220,822 in sub-paragraph (c) and $220,000 in sub-paragraph (d). A Calderbank letter should be certain as to the sum that is required to be paid by the recipient as part of the offer. The 14 August letter did not contain such certainty.

    3. (3)

      Applying Abdi at [30], the explanation for the offer that is contained in the 14 August letter did not deal with the complexity of the issues in the proceedings. The assertion contained in the 14 August letter is, in essence, that the Contract was not one with to which the HBA applied. That is contrary to the finding I made in the Principal Judgment. Whilst the reference to the application in Brodyn was in accordance with my finding in the Principal Judgment, there was no attempt to explain what BPB’s position was in relation to any of the other issues that were live in the dispute on which I had to make determinations in the Principal Judgment.

    4. (4)

      Applying Abdi at [29], the extent of the compromise on offer in the 14 August letter as an “interim” measure was capable of producing a confusing outcome between the parties because it professed not to deal with the “underlying substantive position regarding the amount, if any, payable by [the Rewaises] to [BPB] in respect of the works”, stating that the offer was without prejudice to that position with both parties having reserved rights to deal with it. Yet by the Rewaises continuing to pursue the application, they were able to achieve an outcome favourable to them in the “underlying substantive position”, which is that the Contract was entered into in breach of the HBA. This was a potential outcome which made it reasonable for the Rewaises to refuse the offer.

    5. (5)

      Applying Abdi at [30], I do not think that a period of less than 48 hours for the Rewaises to consider the offer contained in the 14 August letter and either accept or reject it was a reasonable period of time in all the circumstances. This is particularly so when the Rewaises had prepared their evidence for the trial and BPB had not served any of its evidence in chief at the time the offer was made in the 14 August letter and did not complete doing so until 22 August 2024. This put the Rewaises in a position where they were not able to assess the strength of BPB’s evidence and therefore they were not able to make a proper assessment of the reasonableness of the offer contained in the 14 August letter.

  2. [30]

    For these reasons, applying Gretton at [44]–[45] and Abdi at [27], BPB has failed to discharge its onus to demonstrate that it was unreasonable for the Rewaises not to accept the offer contained in the 14 August letter.

ORDERS

  1. [31]

    For the reasons set out above, I have determined that I will not award any part of BPB’s costs on an indemnity basis in relation to these proceedings. I will, however, make a small variation to the order that I made on 10 October 2024 to make it clear that the reference in the order should be to the “first defendant”.

  2. [32]

    BPB has failed in the notice of motion filed 21 October 2024 seeking an award of indemnity costs. As costs of that application should follow the event, the Rewaises should have their costs of it.

  3. [33]

    Accordingly, I make the following orders:

    1. (1)

      Order that order (2) made on 10 October 2024 in these proceedings be varied to the following form:

    2. (2)

      The notice of motion filed 21 October 2024 by the first defendant (Motion) is dismissed.

    3. (3)

      The first defendant is to pay the plaintiff’s costs of the Motion.

Unofficial copy. Source: NSW Caselaw. Refer to the official version for authoritative text.