← All cases

[2022] NSWCA 63

The Owners – Strata Plan 87265 v Saaib; Alexandrova v The Owners – Strata Plan 87265

The Owners Corporation’s appeal (2021/83984) (1) Allow the appeal. (2) Set aside the orders made in the Equity Division on 1 March 2021 as varied on 21 April 2021. (3) In place thereof, (a) give judgment for the Owners Corporation against Mr Saaib in the sum of $3,425,583.54, such judgment to take effect from 1 March 2021; (b) order that Mr Saaib pay the Owners Corporation’s costs of the trial. (4) Order that Mr Saaib pay the appellant’s costs in this Court. Ms Alexandrova’s appeal (2021/140048) (1) Allow the appeal and set aside the orders made in the Equity Division on 1 March 2021. (2) In place thereof, (a) Dismiss the amended summons filed on 11 March 2020; (b) Order that the Owners Corporation pay Ms Alexandrova’s costs of the trial as an unrepresented party.

Catchwords

APPEALS – from findings of fact – primary judge assessed credibility and reliability of two witnesses – findings not expressed to be based on demeanour – applicable test for appellate intervention – whether primary judge gave sufficient weight to combined effect of relevant circumstances EVIDENCE – tendency evidence – whether evidence relating to a separate building project was significantly probative of the issue concerning the alleged builder’s role in the building project the subject of the proceedings – s 97 of the Evidence Act considered EVIDENCE – whether the primary judge erroneously failed to draw a Jones v Dunkel inference CONSUMER LAW – misleading and deceptive conduct – causation – whether, absent the misleading and deceptive conduct, the property developer would have obtained a valid contract of insurance by honest means

Cases cited

  • Abigroup Contractors Pty Ltd v Sydney Catchment Authority (No 3) (2006) 67 NSWLR 341;[2006] NSWCA 282
  • Anthony v Morton[2018] NSWSC 1884
  • ASIC v Hellicar (2012) 247 CLR 345;[2012] HCA 17
  • Badenach v Calvert (2016) 257 CLR 440;[2016] HCA 18
  • Fox v Percy (2003) 214 CLR 118;[2003] HCA 22
  • Hughes v The Queen (2017) 263 CLR 338;[2017] HCA 20
  • I & L Securities Pty Ltd v HTW Valuers (Brisbane) Pty Ltd (2002) 210 CLR 109;[2002] HCA 4
  • Jacara Pty Ltd v Perpetual Trustees WA Ltd (2000) 106 FCR 51;[2000] FCA 1886
  • Jones v Dunkel (1959) 101 CLR 298;[1959] HCA 8
  • Lee v Lee (2019) 266 CLR 129;[2019] HCA 28
  • Mal Owen Consulting Pty Ltd v Ashcroft (2018) 97 NSWLR 1163;[2018] NSWCA 135
  • Marks v GIO Australia Holdings Ltd (1998) 196 CLR 494;[1998] HCA 69
  • Payne v Parker [1976] 1 NSWLR 191
  • R v Bauer (2018) 266 CLR 56;[2018] HCA 40
  • RHG Mortgage Ltd v Rosario Ianni[2015] NSWCA 56
  • Twynam Pastoral Co Pty Limited v AWB (Australia) Limited[2008] FCA 1922
  • Watson v Foxman(1995) 49 NSWLR 315

Legislation cited

  • Civil Liability Act 2002 (NSW)
  • Competition and Consumer Act 2010 (Cth), § 2 – Australian Consumer Law, ss 18, 236
  • Evidence Act 1995 (NSW), § 97, 101, 128
  • Fair Trading Act 1987 (NSW), § 42, 68
  • Home Building Act 1989 (NSW), § 92, 99

Judgment

  1. [1]

    BASTEN JA: The appellant in the first matter is The Owners – Strata Plan 87265, being the owners corporation of a strata scheme involving 11 residential townhouses on Livingstone Road, Marrickville. The townhouses were constructed in 2011 and 2012. Subsequently, major faults were identified which led to a claim by the owners corporation against the builder, Tony Saaib. In December 2016, the owners corporation commenced proceedings in the Equity Division.

  2. [2]

    Although Mr Saaib’s name appeared on various documents, including a building contract with the developer, The Transformer Group Pty Ltd (which has since been deregistered), Mr Saaib denied that he was the builder. On his case, the builder was his nephew, William Zaatini, or Award Build Pty Ltd. He said Mr Zaatini had forged his name on the contract (and other documents).

  3. [3]

    A critical step in entering into the contract for the construction of residential property was the obtaining of a home warranty insurance policy, as required under the Home Building Act 1989 (NSW). A policy was obtained in Mr Saaib’s name by a finance and insurance agent, Irena Alexandrova. In July 2019 the owners corporation commenced proceedings against Ms Alexandrova, on the basis that if Mr Saaib’s denials were true, then Ms Alexandrova had engaged in misleading or deceptive conduct in obtaining home warranty insurance on his behalf. On the basis that Mr Saaib was not the builder, her conduct was said to have led to the issue of a home warranty insurance policy under which the owners corporation could not recover its losses. It relied upon her conduct in identifying Mr Saaib as the builder as, if his denials were accepted, a misleading and deceptive representation causing damage to the owners corporation. Thus, the claim against Ms Alexandrova only arose if the Court accepted Mr Saaib’s defence that he did not authorise the inclusion of his name on the contract as the builder, and was not in fact the builder.

  4. [4]

    In a judgment delivered on 1 March 2021, in the Equity – Technology and Construction List, Henry J dismissed the proceeding brought against Mr Saaib, but upheld the claim against Ms Alexandrova and awarded damages against her in an amount of some $3.4 million. [1]

  5. [5]

    The trial judge dealt with the complex factual claims carefully and comprehensively. The case was largely circumstantial and undoubtedly a difficult one as to which reasonable minds might well differ. However, the judge’s assessment, entirely appropriately, turned to a significant extent upon the assessment of objective circumstances. Clearly the judge had to assess the credibility and reliability of the evidence of the two defendants, Mr Saaib and Ms Alexandrova. However, the findings were largely not based on demeanour in the witness box, but rather the inherent likelihood of particular circumstances and events.

  6. [6]

    For the reasons set out below, which benefit greatly from the reasoning of the trial judge, I have come to a different view as to where the probabilities lie on the critical issue, namely whether Mr Saaib in fact authorised his nephew and Ms Alexandrova to put him forward as the builder. Either he or Mr Zaatini (or both) acted quite improperly. He said Mr Zaatini was a scoundrel who was not to be trusted. No party sought to call Mr Zaatini. While the trial judge had the benefit of hearing Mr Saaib’s denials as to any involvement in the Marrickville development and hearing his cross-examination challenging those denials, there are a number of uncontested circumstances which rendered aspects of his evidence highly implausible. Further, accepting Mr Saaib cast Ms Alexandrova in a bad light. She had had a business relationship with Mr Saaib over some years. He trusted her and said she was a “good person”. She acted on the basis that he was the builder. She was in contact with Mr Zaatini, but also Mr Saaib at critical points in time. There was, understandably, no finding that she was part of a scheme of knowing deception. Rather, she too must have been a victim of fraudulent conduct on the part of Mr Zaatini. However, given her association throughout the relevant period with Mr Saaib, that seems implausible.

  7. [7]

    It will be necessary to explain the reasons why the trial judge did not accept key parts of Ms Alexandrova’s evidence. However, for reasons which will be explained below, contemporary circumstances and documents support the view that Ms Alexandrova acted appropriately and with knowledge of the true circumstances. What she may not have known was the role which Mr Saaib was to play in the development. In any event the appellant’s case on appeal relies on findings of primary fact made by the trial judge; the result turns on the inferences drawn from those facts.

  8. [8]

    The case turned on two possibilities. Either Mr Zaatini acted without the knowledge of his uncle with whom he was in close contact, or his uncle agreed to “front” for him to allow him to undertake a building project for which he was not qualified to obtain the necessary home warranty insurance.

  9. [9]

    If the finding is made on the probabilities that Mr Saaib was the builder, the case against Ms Alexandrova must fall away. The primary case run by the owners corporation was against Mr Saaib; its belated claim against Ms Alexandrova was contingent upon a finding that Mr Saaib was not the builder.

  10. [10]

    The most legally complex part of the case concerned the finding of causation in respect of Ms Alexandrova’s misleading or deceptive conduct. On the basis that Mr Saaib is liable, that issue need not be addressed.

Credit findings – Mr Saaib and Ms Alexandrova

  1. [11]

    The appellant did not seek to challenge the judge’s findings as to the reliability of the evidence given by Mr Saaib and Ms Alexandrova. In addition to what were uncontested or accepted facts, it sought to rely upon the available objective evidence, the relationship between various individuals including Mr Saaib and Mr Alexandrova, and the natural inferences which could be drawn from that material. Nevertheless, it is appropriate to record the judge’s findings and the reasons for them.

  2. [12]

    The critical issue, namely whether Mr Saaib authorised Mr Zaatini to enter into the building contract for the Marrickville project, did not directly involve Ms Alexandrova. Her role was, relevantly, to obtain home warranty insurance for the builder. She believed the builder was Mr Saaib or a company controlled by him. If she formed that belief on the basis of conversations with Mr Saaib, that would have been a matter of importance. If she formed the belief on the basis of information supplied by Mr Zaatini, the significance of the belief would turn upon separate findings as to the relationship between Mr Saaib and Mr Zaatini and their dealings with respect to the Marrickville project. It is convenient, therefore, to deal with the findings in relation to the credibility and reliability of Mr Saaib first.

  3. [13]

    The judge dealt with this issue at [252]-[269]. The judge was satisfied that English was not his first language. The judge’s assessment of his evidence was carefully considered and explained by reference to particular aspects of the evidence. Importantly, it was directed to a somewhat broad-brush approach on the part of the owners corporation “that Mr Saaib’s evidence cannot be accepted unless it is corroborated by reliable evidence or against his interest as he is an unreliable and dishonest witness”. [2] The judge concluded that “aspects of Mr Saaib’s evidence [were] unsatisfactory and unreliable” but did not find that he “deliberately gave false evidence” and made no finding of dishonesty. [3] Rather, the judge adopted a nuanced approach with respect to different aspects of Mr Saaib’s evidence. It will be necessary to return to specific aspects of Mr Saaib’s evidence and the judge’s findings in relation to them, in dealing with the relevant topics. However, there were three underlying reasons for doubting his reliability.

  4. [14]

    First, limitations on his language skills had an impact on his evidence; there were questions he did not understand and on occasion his answers were “far from clear and difficult to follow”. [4] (This is readily apparent from the transcript.) Secondly, he did not have written communications with the principal parties to the dispute, but relied on verbal exchanges, either by telephone or in person. He did not use a computer. It followed that there were no records of the content of communications which had occurred some 10 years before he gave evidence. The judge correctly adopted a guarded approach to his purported recollection of the subject matter and detail of such conversations. Thirdly, it was clear that Mr Saaib had an interest in denying any knowledge of the Marrickville project and did so “in an assertive manner”. [5] The judge accepted that demonstrating a fixed or strong view was not a reliable indicator of truthfulness. [6] Aspects of Mr Saaib’s evidence were described as “evasive”, [7] and internally inconsistent. [8]

  5. [15]

    No complaint is made in relation to these findings, which were soundly based.

  6. [16]

    Similar difficulties arose with respect to Ms Alexandrova. As with Mr Saaib, English was not her first language. [9] She also suffered from difficulty recalling the contents of conversations, to the extent that they were not recorded, some 10 years after the events. As a defendant, she too had an interest in a particular outcome of the proceedings.

  7. [17]

    The judge’s findings with respect to Ms Alexandrova are sufficiently summarised in the following passage:

  8. [18]

    Again, the judge supported her conclusions with explanations and examples. It will be appropriate to deal with relevant aspects of these findings in respect of the particular topics addressed.

  9. [19]

    There was no challenge to the general findings as to Ms Alexandrova’s credit and reliability, which were undoubtedly soundly based.

Admissibility of evidence

  1. [20]

    The appellant’s case was that Mr Saaib allowed his nephew to use his name on a building contract so as to obtain the benefit of his (Saaib’s) asserted entitlement to home warranty insurance with respect to the project. The appellant relied on evidence that Mr Saaib had, virtually contemporaneously, undertaken a similar role “fronting” as the builder on a construction project in Leura. The appellant contended that this otherwise extraneous evidence was admissible to show that Mr Saaib was not averse to allowing his name to be used for such an improper purpose to assist a friend, or in the present case, a nephew.

  2. [21]

    The excluded evidence included a letter (identified as Ex E) dated 31 July 2010 addressed to the owner of land at Mount Hay Road, Leura, wishing to construct a three-bedroom home. Mr Saaib wrote the letter on his own letterhead as builder, giving his ABN and licence number. He identified the total cost of the project as $305,000. The project was identified by reference to a lot and deposited plan number on Mount Hay Road. The letter commenced:

  3. [22]

    Exhibit H was a volume of material relating to the construction of the home at Mount Hay Road.

  4. [23]

    In an affidavit dated 28 February 2019, Mr Saaib stated: [10]

  5. [24]

    The affidavit described his relationship with Ms Alexandrova. He stated: [11]

  6. [25]

    Mr Saaib was cross-examined about the Leura project. It was put to him that he agreed to be the builder of the Leura house in March 2010. He eventually agreed. [12] The evidence continued: [13]

  7. [26]

    However, the evidence of Mr Saaib’s involvement in the Leura project did not merely commence at a similar time as did the Marrickville project, it continued throughout the construction of the Marrickville townhouses, namely through 2011 and 2012.

  8. [27]

    In 2010 little progress was made with respect to the Leura development. In August 2011 the previous owners transferred the property to their daughter and their son-in-law, George O’Beid. Mr O’Beid was the director of a company that held a builder’s licence between 11 May 2010 and 10 May 2015. [14] The judge noted:

  9. [28]

    The judge appears not to have made an express determination that Mr Saaib did sign the application for home warranty insurance dated 13 February 2012. However, his name appears on the section under “Builder Licence Details” with a licence expiry date which appears to read “01/11/2013”. The judge stated:

  10. [29]

    This later material was not addressed by the judge in dealing with the question of admissibility, although many of the excluded documents related to the period 2011-2012. Arguably a propensity to allow third parties without necessary qualifications to obtain insurance for residential work by putting his name on a contract as builder when he did not intend to undertake the work appears strongly from the evidence relating to this latter period.

  11. [30]

    Counsel for Mr Saaib took a timely objection to this evidence, conceding in effect that it might be relevant because it involved contact with Ms Alexandrova, but noting that it was going to be said that “Mr Saaib has a tendency to give out his builder’s licence for use by others or something like that. I take a tendency and coincidence objection to evidence of that nature.” [15] The objection was not ruled on until the final judgment. The judge rejected both the documentary evidence and the cross-examination in relation to the Leura project, [16] which was not specifically identified but must have included the cross-examination set out above.

  12. [31]

    The admissibility of tendency evidence turns on compliance with s 97 of the Evidence Act 1995 (NSW). Section 97(1) provides that “[e]vidence of the character, reputation or conduct of a person, or a tendency that a person has or had, is not admissible to prove that a person has or had a tendency (whether because of the person’s character or otherwise) to act in a particular way, or to have a particular state of mind unless … the court thinks that the evidence will, either by itself or having regard to other evidence adduced or to be adduced by the party seeking to adduce the evidence, have significant probative value.”

  13. [32]

    It is clear that this requires a contextual analysis having regard to the circumstances of the case. The circumstances include the burden of proof on the party adducing the evidence. If, as in a criminal case, it is necessary to establish something beyond reasonable doubt, a higher level of probative value is required for it to be significant, as compared with a civil case where it is sufficient to establish a fact on the balance of probabilities. Further, in a civil case there is no requirement (as there is in a criminal proceeding) for the probative value to outweigh substantially any prejudicial effect: Evidence Act, s 101(2). The danger that evidence will be unfairly prejudicial, misleading or confusing, so as to engage grounds for excluding it under s 135, will rarely arise in a civil matter heard by a judge alone.

  14. [33]

    In this case, the trial judge obtained some assistance from the reasoning of Sackville J (with whom Whitlam and Mansfield JJ agreed) in Jacara Pty Ltd v Perpetual Trustees WA Ltd: [17]

  15. [34]

    Sackville J distinguished such reasoning from evidence which appeared to establish a “system” and thus provided a basis for a circumstantial inference as to a fact in issue. [19] Whether the distinction was relevant in the present case is unclear. In any event, the judge excluded the evidence on the basis that it did not have “significant probative value”, thus applying s 97. The heart of the judge’s reasoning appeared in the following passage:

  16. [35]

    The final reference was to a decision of Jagot J in a case in which, despite differences in the conversations and representations relied upon, the judge held there were “striking similarities in respect of the essential allegation”. [22] Jagot J did not say that this reflected the statutory test, as opposed to being an apt description of the evidence before her.

  17. [36]

    However, the phrase “striking similarities” is apt to invoke reliance upon the pre-Evidence Act common law principles governing similar fact evidence. It is not a requirement of s 97(1); it is not an appropriate substitute for “significant probative value”. Further, the tabulation of differences between conduct in one circumstance and conduct in another is not a mechanical exercise. It must be undertaken contextually. The fact that a holder of a builder’s licence, who was not at the time running a building business requiring use of the licence, on his own evidence, has permitted a third party to use the licence, in effect “fronting” for that person, is a remarkable and unusual circumstance. As noted above, that is the substance of the accusation in the present case. That someone has done precisely that, virtually contemporaneously, in another matter, might strike the objective observer as highly significant, in circumstances where the material conduct is denied. Especially is that so where the holder of the licence asserts that another person, with no knowledge that the licence holder had permitted such conduct himself, has used his licence without his permission in the same way.

  18. [37]

    In my view the evidence of the Leura arrangements had significant probative value and should have been admitted.

  19. [38]

    Once the evidence is admitted, the error in its exclusion must be overcome by reassessing the critical finding of fact as to whether Mr Saaib authorised his nephew to use his name on the building contract for the Marrickville project.

  20. [39]

    Before considering this central issue and the challenges by the appellant to particular factual findings, it is convenient to set out a brief chronology of the Marrickville project from its inception until the signing of the contract. No issue was raised as to the judge’s findings with respect to this material.

Brief chronology

  1. [40]

    On 6 August 2008 the developer obtained development consent for the Marrickville project. The sole director of the developer was Nemer Antoun, who was the brother of Joe Antoun (deceased) who, from September 2008 until February 2012, was the sole director of a building company, Award Build Pty Ltd. Both the developer and Award Build have since been deregistered. [23] Mr Zaatini appears to have been employed by, or worked with, Award Build.

  2. [41]

    The relationship between Mr Zaatini, Mr Saaib and Ms Alexandrova was a matter of critical importance. Mr Zaatini was known as William (Wajih) Zaatini and as William Mowad. [24] With respect to their relationship, the judge set out a narrative of facts as to which she was satisfied, [25] including the following matters:

  3. [42]

    Several versions of the building contract were prepared and executed.

  4. [43]

    The first contract, dated 24 November 2009, was between Mr Nemer Antoun as owner and Mr Saaib as builder. The contract price was $2.4m and a commencement date of 11 January 2010 was included. The contract bore a signature purporting to be that of Mr Saaib but, as the judge accepted, it was not in fact his signature. Each signature was said to have been done in the presence of “William Mowad” (Zaatini) but the witness did not sign.

  5. [44]

    The status of the first contract was not resolved in the proceedings. It appears to have been superseded by a second contract which came into existence at some time between 17 June and 6 September 2010. [26] That contract was provided to the ANZ Bank in support of an application for finance on 6 September 2010. (The judge referred to the second contract, but it was not in evidence and nothing turns on it.)

  6. [45]

    On 13 September 2010 a letter was signed in the name of Mr Saaib recounting that he had entered into the agreement with the developer for construction of 11 townhouses at Livingstone Road, Marrickville. The letterhead bore the name “Tony Saaib Pty Ltd”. A letter of offer issued by ANZ Bank to the developer on 28 September 2010 required a tripartite agreement between the bank, the developer and the builder, identified as “Tony Saaib Pty Ltd”. All risk insurance was to be taken out by contractors and “evidence of a home owner’s warranty insurance policy” provided. The developer accepted the offer on 1 October 2010. A “builder’s side deed” was prepared which was also purportedly executed by Mr Saaib. Mr Zaatini and Ms Alexandrova then took steps to obtain the home owner’s warranty insurance. On 30 September 2010 Ms Alexandrova advised Mr Zaatini that Mr Saaib was eligible, but had to complete an application form.

  7. [46]

    The trial judge accepted that Mr Saaib signed an “eligibility application” to permit him to obtain home warranty insurance in relation to a contract in an amount of $2.4 million. [27] The circumstances surrounding that event are of importance in determining whether he was aware of the building contract and the use of his name as the builder. That matter will be addressed below.

  8. [47]

    The contract which was treated as the third and final agreement, bore the date 4 October 2010. In other respects it was identical with the contract which bore the date 24 November 2009. Although an additional page was included in the earlier contract (being instructions with respect to signatures), it appeared that the new contract was a photocopy of the first contract with only the date changed.

  9. [48]

    On 12 October 2010 Mr Saaib signed an eligibility profile change application for the purpose of obtaining home owner’s warranty insurance for a project of the size of the Marrickville contract. (His actual experience did not permit the upgrade in eligibility.) He said the form was “blank” when he signed it. His purpose in signing the document will be addressed below.

  10. [49]

    The following day, Ms Alexandrova raised with Mr Zaatini aspects of the documentation which would need to be addressed before the proposed insurer (QBE) would accept the application. Mr Saaib spoke to both Ms Alexandrova (twice) and Mr Zaatini on 13 and 14 October 2010.

  11. [50]

    On 15 October 2010 Ms Alexandrova emailed Mr Zaatini stating:

  12. [51]

    No finding was made at that point in the judgment, but there was no later finding that the content of the email was false; it was inherently plausible.

  13. [52]

    Certificates of insurance were issued by QBE for each townhouse in the proposed development on 18 January 2011. On 15 February 2011 the certifying authority for the project issued a construction certificate.

Authority to sign contract

  1. [53]

    The critical issues in the appellant’s case against Mr Saaib were that, (i) he knew of the Marrickville project, (ii) he knew that Mr Zaatini was intending to undertake the building work and (iii) in fact did so, using Mr Saaib’s name as the builder. There is no dispute that the signature on the contract purporting to be Mr Saaib’s was not his signature. The appellant’s case was, however, that Mr Saaib authorised Mr Zaatini to sign that, and other documents, on his behalf.

  2. [54]

    In his first affidavit of 28 February 2019 Mr Saaib described himself as a formworker. He was categorical in his denials of building the 11 residential units, visiting the property, having any knowledge of or contact with the developer, having seen the “alleged contract” dated 4 October 2010 until after the works had been completed and a dispute arose. He further said:

  3. [55]

    The appellant’s case was that these denials were extreme and inherently implausible. There were a number of factual elements which supported that case. Many of the steps in the argument relied upon findings made by the trial judge.

  4. [56]

    First, the judge made findings at [31], set out at [41] above. The finding that Mr Saaib and Mr Zaatini spoke quite regularly, “almost daily during some periods” was generic. However, the telephone records (Ex G) revealed that Mr Saaib called Mr Zaatini on no fewer than 66 occasions between 2 August 2010 and 26 October 2010. (It was probable that Mr Zaatini also called Mr Saaib.) Mr Saaib provided no account in his evidence as to what they spoke about, but the proposition that they did not discuss the Marrickville project at all was implausible.

  5. [57]

    The regular communications referred to by the trial judge continued through the two years during which Mr Zaatini was engaged in the construction of the townhouses.

  6. [58]

    The cross-examination of Mr Saaib in relation to the Leura property obtained the unsurprising concession that Mr Saaib was aware of the requirements for home warranty insurance in undertaking residential building work. Again, taken in isolation, the likely inference was that he knew that Mr Zaatini did not have the experience to make him eligible for the necessary insurance; nor did Mr Saaib. However, it is not necessary to draw that inference merely from the close relationship and almost daily contact, as opposed to the whole of the evidence.

  7. [59]

    As has been noted, the insurance broker, Ms Alexandrova, had known Mr Saaib from around 2005. She had assisted him to obtain a loan for his Mulgoa home in 2009. In March or April 2010 she assisted him to obtain home warranty insurance for the Leura project. Mr Saaib agreed that in 2010 he spoke to Ms Alexandrova regularly. [28] Further, Mr Saaib introduced Mr Alexandrova to Mr Zaatini, probably in early 2010. [29] The judge found that Mr Zaatini used a mobile telephone in his own name and a telephone held by Award Build in the second half of 2010 and early 2011. [30] The judge made critical findings in relation to the steps taken by Ms Alexandrova with respect to the home warranty insurance which was arranged with QBE. The chronology commenced, relevantly for present purposes, the day after the contract was executed on 4 October 2010. The judge stated:

  8. [60]

    There was a dispute as to what happened after the email from Mr Zaatini. The dispute was identified by the judge in the following terms:

  9. [61]

    There were further communications between Mr Zaatini and Ms Alexandrova over the next two days. The judge made further findings:

  10. [62]

    On 13 October 2010 Mr Zaatini sent an email to Ms Alexandrova attaching “builder’s eligibility forms”. The judge observed:

  11. [63]

    The evidence with respect to the completion of the increased eligibility application was summarised by the judge in the following passages:

  12. [64]

    The judge made the following critical findings in relation to this material:

  13. [65]

    The judge noted in this context that “[a] discussion referring to or knowledge of the Marrickville project on the part of Mr Saaib at that time is not, in my view, sufficient evidence from which to infer implied actual authority on the part of Mr Zaatini to enter into the 4 October Contract or to find that Mr Saaib knowingly authorised Ms Alexandrova to lodge the Home Warranty Application with the insurer naming him as the builder of the project.” [31]

  14. [66]

    That conclusion was available to the judge on the basis of discussions of the Marrickville project at that time. However, there were other factors to be taken into account before reaching a negative conclusion in relation to the authority of Mr Zaatini to enter into the 4 October contract on behalf of Mr Saaib.

  15. [67]

    Further, the judge observed: [32]

  16. [68]

    Although the judge considered that the application might have been lodged with an eye to future “big projects”, none was ever identified. Conceding the possibility that Mr Saaib may have believed that other projects were possibilities, that does not affect the casualness with which he permitted the application to be filled in by Mr Zaatini, having regard to the period for which his eligibility would be granted, his lack of experience which would warrant an increase in his eligibility if it were to be correctly recorded in the application, and the fact that he was in constant contact with Mr Zaatini at the time the Marrickville project was being planned.

  17. [69]

    Finally, the judge’s conclusion was inconsistent with the express rejection of Mr Saaib’s evidence that the Marrickville project was not mentioned.

  18. [70]

    It was not in doubt that Ms Alexandrova had the 4 October contract and lodged it with the insurance broker, OAMPS, on 6 October 2010, with the QBE application. [33] Further, the judge accepted “the logic” of the owners corporation submission in the following terms:

  19. [71]

    If the last sentence in that passage constitutes a rejection of the inference sought by the owners corporation, it is unpersuasive. It gives insufficient weight to (i) the daily communications between Mr Zaatini and Mr Saaib; (ii) the absence of any evidence that Ms Alexandrova was asked by Mr Zaatini to keep Mr Saaib’s role a secret; (iii) the nature of the relationship between Mr Saaib and Ms Alexandrova, which was an established business relationship, and (iv) her very recent engagement by Mr Zaatini, on Mr Saaib’s introduction. The implicit assumption of some form of conspiracy against Mr Saaib is implausible. There was no finding to that effect, but in its absence, there is much weight in the owners corporation’s submission.

  20. [72]

    There is more material to support that conclusion. The judge made the following further findings:

  21. [73]

    The judge downplayed these circumstances in two further passages. First, she found that Ms Alexandrova “acted on instructions from Mr Zaatini (not Mr Saaib) when she lodged the QBE application and the 4 October Contract with OAMPS on 6 October 2010.” [34] In the sense that Mr Zaatini completed the application and provided the documentation, that finding may be accepted. It is not inconsistent with Mr Zaatini having authority from Mr Saaib to take these steps.

  22. [74]

    Further, the judge observed:

Specific grounds of appeal

  1. [75]

    Ground 1 of the appeal challenged the rejection of Mr Saaib’s evidence that he spoke to Ms Alexandrova “regularly” in 2010. The challenge was based on the proposition that Mr Saaib’s evidence in that respect was unchallenged. It was, however, open to interpretation. So long as it is borne in mind that, as the judge had correctly noted, there was no record of outgoing calls from Ms Alexandrova’s phone, nothing turned on that evidence. That there were communications at the key time was accepted.

  2. [76]

    More specifically, ground 2 took issue with the finding that Ms Alexandrova did not speak to Mr Saaib about the Marrickville project prior to 12 October 2010. However, I do not read the judge’s reasoning at [319]-[325] as making that finding. Rather, the judge was not affirmatively satisfied that Ms Alexandrova discussed the Marrickville project with Mr Saaib, as opposed to discussing it with Mr Zaatini, at that time. The absence of the affirmative finding sought by the appellant does not demonstrate error. However, and more importantly, the absence of a finding as to the communications is of little relevance given, (i) that Mr Saaib introduced Mr Zaatini to Ms Alexandrova in 2010, (ii) the apparent purpose of the introduction, and (iii) the close communications between Mr Saaib and Mr Zaatini. The findings as to the later conversations, at [332] and [333], set out above, were firmly based in the evidence and support the appellant’s case.

  3. [77]

    Ground 3 took issue with the statement by the trial judge at [336] that she was “unpersuaded” that a reference to the Marrickville project in the communications on 13, 14 and 15 October and to the eligibility application which needed to be signed, “was understood by Mr Saaib to be to anything other than a reference to the Eligibility Application and a possible project or future ‘big job’.” An affirmative finding, as noted above, may not have arisen from that material alone, but should have been made on the basis of the whole of the evidence. To that extent, ground 3 should be upheld.

  4. [78]

    Ground 4 was a composite ground addressing the critical ultimate conclusion on the basis of 10 independent factors. It is appropriate to return to that when the other grounds have been addressed.

  5. [79]

    Ground 5 asserted that the judge was wrong in failing to draw a Jones v Dunkel [35] inference from the failure of Mr Saaib to call Mr Zaatini as a witness. Based on their close relationship in 2009-2012, Mr Zaatini was clearly a person who might be expected to give evidence for Mr Saaib. He might have given evidence that Mr Saaib authorised him to sign documents in relation to the project, including the contract. In the alternative, he might have given evidence that he had no authority and had forged Mr Saaib’s signature. The latter evidence might, as the appellant submitted, have required a certificate under s 128 of the Evidence Act to protect him from future prosecution. However, it was submitted that the failure to call Mr Zaatini at all should have supported an inference that his evidence would not have assisted Mr Saaib.

  6. [80]

    Whether such an inference should be drawn may require taking into account current circumstances, not merely a relationship as at the time of the events in question. Mr Saaib’s evidence was to the effect that he had fallen out with his nephew. That may have been true, or it may have been untrue. It may have been the case that Mr Saaib was angry with his nephew because he was being sued for Mr Zaatini’s poor construction work. Alternatively, they may have fallen out because Mr Zaatini had acted without authority, but would not take responsibility for that.

  7. [81]

    The trial judge declined to draw the relevant inference from the failure to call Mr Zaatini on two grounds. First, being unpersuaded by the other evidence that “reasonable and definite inferences [arose] that Mr Zaatini and Mr Saaib had discussed and agreed that Mr Saaib would be named in the 4 October contract as the builder of the Marrickville property”, it followed that a Jones v Dunkel inference would not assist the appellant’s case. [36] Such an inference cannot constitute affirmative evidence to fill a gap. However, for the reasons set out above and discussed further below, the circumstantial case relied on by the appellant has sufficient support to permit an inference to be drawn on the balance of probabilities. In that circumstance, it is open to this Court to have regard to the fact that Mr Zaatini was not called.

  8. [82]

    The judge further held that Mr Zaatini was not in Mr Saaib’s camp and it would not be natural to expect him to call Mr Zaatini. [37] She noted that Mr Saaib had described Mr Zaatini in adverse terms and that Mr Saaib’s lawyer had reported him to the police for fraud. [38]

  9. [83]

    Mr Saaib did speak of him adversely, but incidentally and did not address the issue as to why he would not call him. At the beginning of his cross-examination, he was asked about his state of knowledge of the Marrickville project prior to receiving a letter of 22 February 2017 which he claimed was the first time he had heard about the Marrickville project. He conceded that he did know a fair bit about Marrickville as at 22 February 2017. [39] It was then put to him that he had spoken “several times or many times” to Mr Zaatini prior to 22 February 2017; he replied: [40]

  10. [84]

    Later in the cross-examination he confirmed that he had a close relationship with Mr Zaatini “throughout 2011” and that they spoke daily. [41] It was then put to him: [42]

  11. [85]

    Mr Saaib was cross-examined about the acceptance of his application for an increase in his home warranty insurance eligibility. The following exchange took place: [43]

  12. [86]

    If the inference from the last passage is that in 2010 he did not like Mr Zaatini and did not trust him, that would be inconsistent with much of the other evidence, including the daily contacts, and the findings of the trial judge. If the inference is that in hindsight Mr Saaib is bitter about Mr Zaatini’s conduct, that provides no justification for not calling him if his evidence would support Mr Saaib. With respect to his communications in 2012, he gave evidence of his close contact then, but suggested that at some undefined time after that, there had been a “bullshit scene”. He had earlier accepted that he spoke to Mr Zaatini prior to 22 February 2017 about the Marrickville project, despite adding his abusive statement that he was “a bullshit person.”

  13. [87]

    The appropriate inference to draw from this material was that Mr Saaib did not think that Mr Zaatini would give evidence which would support Mr Saaib’s case, but that that was because he was a liar; yet he was not prepared to allow the Court to determine if that were correct.

  14. [88]

    There was no evidence as to why Mr Saaib’s lawyer had reported Mr Zaatini to the police for fraud, nor as to whether the police had taken steps to investigate or prosecute him. As this Court said in RHG Mortgage Ltd v Rosario Ianni, [44] a suggestion that the witness might be reluctant to give evidence because it may constitute an admission of wrongful conduct on his part, would invite an application for a certificate under s 128 of the Evidence Act. The fact of the report to the police was consistent with Mr Saaib taking a particular view of Mr Zaatini’s conduct, at least after he had obtained legal advice; it does not follow that the person would lie on oath. As in RHG v Ianni, because one member of a family has caused loss and damage to other members of the family does not mean that there is necessarily a rift in the family which would prevent the wrongdoer giving evidence in support of the case for the other family members who suffered by his or her conduct.

  15. [89]

    In my view, it may properly be inferred that Mr Zaatini’s evidence would not have assisted Mr Saaib’s case.

  16. [90]

    The final ground of appeal challenged the judge’s finding that, although there was clear evidence, accepted by the trial judge, that Mr Saaib and Mr Zaatini spoke regularly and constantly through 2011 and 2012, there was insufficient material from which to infer that Mr Zaatini did building work under Mr Saaib’s supervision.

  17. [91]

    That conclusion is said to have followed from the judge’s rejection of the contention that Mr Saaib had authorised Mr Zaatini to enter into the 4 October 2010 contract. However, if that finding were set aside, it is not clear that the finding with respect to events of 2011 and 2012 would take the matter further. Whilst there may be grounds for an inference that Mr Saaib discussed the Marrickville project with Mr Zaatini during the course of its construction, that does not give rise to an inference that he attended at the site or took steps to supervise the work.

  18. [92]

    It is convenient then to return to ground 4. As noted above, the combination of 10 factors identified in ground 4 were said to be sufficient to ground an inference that Mr Saaib had authorised Mr Zaatini to enter into the Marrickville building contract on his behalf. The appellant submitted that the judge’s conclusion that she was not persuaded as to that fact should be set aside as contrary to compelling inferences and as glaringly improbable.

  19. [93]

    Each of the findings relied upon from which a relevant inference could be drawn has been addressed above. Some of the 10 factors, including the undisputed emails during 2010 between Ms Alexandrova and Mr Zaatini and the uncontested testimony that Mr Saaib did not use a computer or email but typically communicated by telephone, were, as the respondent submitted, neutral, at least when viewed in isolation. However, the appellant was correct to submit that they should not be viewed in isolation and that the error of the trial judge was, in effect, to consider carefully each separate item of evidence, but give insufficient weight to possibilities which should, in combination, have led to the inference of authority contended for by the appellant.

  20. [94]

    In addition to the matters discussed above, it is necessary to have regard to the tendency evidence which should have been admitted and can now be taken into account. That evidence demonstrated that, throughout the period during which Mr Zaatini was dealing with the Marrickville project, Mr Saaib was allowing his name to be used as the builder on the Leura development, including for the purpose of obtaining home warranty insurance and at a time when his entitlement to such insurance was not in force. This material demonstrated a propensity to allow others to use his builder’s licence and obtain home warranty insurance in his name when they had no entitlement (and indeed when he had no entitlement). That is quite similar to conduct that occurred in relation to the Marrickville development. There being no reason to believe that Mr Zaatini knew of Mr Saaib’s conduct in relation to the Leura project, there is an inference available from the existence of the propensity in favour of the view that Mr Saaib was knowingly involved in the presentation of himself as a builder with an entitlement to home warranty insurance with respect to the Marrickville development, when he did not intend to carry out the building work.

  21. [95]

    Although it may add little to the inferences which can be drawn from the material set out above, the Court can be satisfied that Mr Zaatini would not have given evidence favourable to Mr Saaib. The evidence may have been of limited weight because of doubts as to Mr Zaatini’s honesty, but it should not be assumed that he would have lied in critical respects.

Notice of contention

  1. [96]

    Mr Saaib filed a notice of contention identifying a further ground upon which the decision of the trial judge should be upheld, namely:

  2. [97]

    Mr Saaib submitted that it was an essential element of the case against him that he had “built the townhouses”. Even if he had signed the 4 October contract, it was submitted, if he did not perform it, he could not be liable for breach of a warranty against defective performance contained in it. The judge said she could see “no basis on which it could be said that Mr Saaib undertook the work leading to the construction of the Marrickville property.” [45]

  3. [98]

    However, it is not entirely clear what is meant by these propositions. The appellant’s case was that Mr Zaatini undertook the work, but that he was in touch on a regular, almost daily, basis with Mr Saaib throughout 2011-2012 when the work was being undertaken, as the trial judge found. The available inference, which should be drawn on the probabilities, was that Mr Saaib and Mr Zaatini discussed the project, possibly among other things. The contention assumes that Mr Saaib did not have to physically construct the buildings, so long as he supervised the work of others. However, if his supervision was deficient, it did not follow that he was not responsible for the results. If the contract was concluded in his name with his authority, it may be inferred that he maintained responsibility. There is no evidence that there was any separate contract between the developer, the bank and some other builder, such as Award Build Pty Ltd.

  4. [99]

    The ground raised by the notice of contention should be dismissed.

Conclusions

  1. [100]

    It follows that the appellant is entitled to a judgment against Mr Saaib. The amount of its damages was assessed by the trial judge and there has been no challenge to that assessment. Accordingly, with respect to Mr Saaib, the Court should make the following orders:

    1. (1)

      Allow the appeal.

    2. (2)

      Set aside the orders made in the Equity Division on 1 March 2021 as varied on 21 April 2021.

    3. (3)

      In place thereof,

    4. (4)

      Order that Mr Saaib pay the appellant’s costs in this Court.

  2. [101]

    In these circumstances, it is not necessary to address the substance of the grounds raised by Ms Alexandrova in her appeal. The judgment against her should be set aside. As the contingent claim against her by the owners corporation failed, she should have her costs of the trial (as an unrepresented party.)

  3. [102]

    As Ms Alexandrova did not actively support the owners corporation’s case against Mr Saaib, there should be no order as to the costs of her appeal.

  4. [103]

    The Court should make the following orders:

    1. (1)

      Allow the appeal and set aside the orders made in the Equity Division on 1 March 2021.

    2. (2)

      In place thereof,

  5. [104]

    No order as to the costs of the appeal.

  6. [105]

    MACFARLAN JA: The Owners - Strata Plan 87265 is the Owners Corporation of the strata scheme in respect of a block of 11 townhouses located in Marrickville NSW. It is the successor in title to the previous owner and the developer of the property, Transformer Group Pty Ltd (“Transformer Group”). This appeal arises out of separate proceedings that the Owners Corporation brought in the Equity Division against Mr Tony Saaib and Ms Irena Alexandrova.

  7. [106]

    The Corporation claimed damages from Mr Saaib in respect of the costs of rectifying defects in the common property of the building on the basis that Mr Saaib had entered into, as “builder”, a contract with Transformer Group dated 4 October 2010 for construction of the building. The Corporation’s case was that, even if (as Mr Saaib asserted) he did not sign the contract, he authorised his nephew, Mr William Zaatini, to enter into it on his behalf and to deal with Ms Alexandrova, an insurance and finance broker, to arrange home warranty insurance in relation to the construction of the building. Mr Saaib’s case in response was that the building contract and a number of other forged documents were brought into existence without his knowledge by Mr Zaatini and/or Mr Joe Antoun and Mr Nemer Antoun in order to obtain for Transformer Group home warranty insurance and bank finance for the development. He also contended that he did not undertake or supervise any building works for the construction of the building.

  8. [107]

    The Corporation’s claim failed because the primary judge held, by a finding that was not disputed on appeal, that Mr Saaib’s purported signature on the contract was forged and held, notwithstanding evidence given by Ms Alexandrova of implied admissions by Mr Saaib to the contrary, that Mr Saaib did not authorise his name to be used as “builder” and held that he did not play any role in the construction of the building.

  9. [108]

    In separate proceedings the Corporation claimed damages from Ms Alexandrova against the possibility, which in fact eventuated, that it failed in its claim against Mr Saaib. The primary judge accepted the Corporation’s case that, by submitting documents to the prospective insurer (the NSW Self Insurance Corporation for whom QBE acted as agent), purportedly on behalf of Mr Saaib, but in fact without his authority, Ms Alexandrova engaged in misleading or deceptive conduct which led to the Corporation’s predecessor, Transformer Group, not having the benefit of enforceable home warranty insurance, with consequent loss to the Corporation.

  10. [109]

    On appeal, the Corporation contended that the primary judge erred in finding that:

    1. (1)

      Mr Saaib did not speak regularly to Ms Alexandrova during 2010;

    2. (2)

      Ms Alexandrova did not speak to Mr Saaib about the Marrickville project prior to 12 October 2010;

    3. (3)

      references to the Marrickville project during calls between Ms Alexandrova and Mr Saaib in October 2010 were understood by Mr Saaib as references to an Eligibility Application (see [127] below) and to “a possible project or future job”;

    4. (4)

      Mr Saaib did not authorise Mr Zaatini to enter into the Marrickville building contract on Mr Saaib’s behalf;

    5. (5)

      a Jones v Dunkel inference did not arise from Mr Saaib’s failure to call Mr Zaatini as a witness;

    6. (6)

      evidence relating to the Leura project (see [148] below) did not have significant probative value and was not admissible as tendency evidence;

    7. (7)

      Mr Saaib’s evidence that he spoke to Mr Zaatini regularly in 2011 and 2012 was not a sufficient basis for inferring that Mr Zaatini did the building work under Mr Saaib’s supervision.

  11. [110]

    On appeal, Ms Alexandrova contended that:

    1. (1)

      the primary judge erred in finding that Ms Alexandrova engaged in misleading or deceptive conduct;

    2. (2)

      the Corporation did not prove that it suffered loss that was caused by Ms Alexandrova’s alleged misleading or deceptive conduct;

    3. (3)

      she was denied procedural fairness at the hearing at first instance;

    4. (4)

      the Corporation’s claim against her is statute-barred.

  12. [111]

    For the reasons that appear below, I have concluded that the Corporation’s appeal in the proceedings against Mr Saaib fails and that Ms Alexandrova’s appeal in the separate proceedings brought against her by the Corporation succeeds, in relation to the latter on the basis that the Corporation did not establish that it suffered loss that was caused by Ms Alexandrova’s alleged misleading or deceptive conduct. The overall result therefore is that the Corporation fails in both of its proceedings.

THE REGULATORY BACKGROUND

  1. [112]

    The primary judge summarised the regulatory background to the proceedings as follows:

THE FACTUAL CIRCUMSTANCES

  1. [113]

    The following summary of the factual circumstances relevant to the issues on appeal is drawn from her Honour’s description of the evidence before her at [24]-[228] of her judgment of 1 March 2021 ([2021] NSWSC 150).

  2. [114]

    From 2008 to June 2013, Mr Nemer Antoun was Transformer Group’s sole director. He was the brother of the late Mr Joe Antoun who had been the sole director of a building company named Award Build Pty Ltd between September 2008 and February 2012. That company was deregistered on 27 January 2013.

  3. [115]

    Mr Saaib obtained his builder’s licence on 18 October 2001 and between August 2004 and 31 March 2012 was licenced to carry out building work that required home warranty insurance. He is a director and secretary of Australian Metropolic Developments Pty Ltd and is or has been associated with two other building companies. He does not know how to use a computer, has difficulties with written English and normally communicates by telephone.

  4. [116]

    Ms Alexandrova is a self-employed insurance and finance broker. She assists clients with applications for construction, residential and commercial finance, as well as for home warranty insurance for building projects. Relevant to the present case, she had between 2004 and 2013 a referral agreement with OAMPS Insurance Brokers Limited (“OAMPS”) pursuant to which she earned commission for introducing licensed builders to OAMPS. QBE was the insurer agent to whom Ms Alexandrova submitted documents through OAMPS.

  5. [117]

    Ms Alexandrova met Mr Saaib in about 2005 and subsequently helped him obtain insurance in connection with his work as a builder. Mr Saaib gave evidence that in 2010 he spoke to Ms Alexandrova “regularly”. From at least February 2010 Ms Alexandrova also assisted Award Build with insurance for building projects. She spoke to Mr Joe Antoun once or twice and otherwise liaised with Mr Zaatini in relation to Award Build matters.

  6. [118]

    Limited telephone records were in evidence. These included records of calls made to Ms Alexandrova’s and Mr Zaatini’s mobile telephone numbers in 2010-2011.

  7. [119]

    A residential building contract dated 24 November 2009 (the “First Contract”) naming Mr Nemer Antoun as the owner and Mr Saaib as the builder for works at the Marrickville property was in evidence. It purported to be signed by Mr Saaib but it is uncontested that he did not sign it.

  8. [120]

    Ms Alexandrova deposed that in or about mid-2010 she had a telephone conversation with Mr Saaib in which he told her about “…a new project which I will be doing with my nephew [Mr Zaatini]”, being the Marrickville project (the “First Saaib Conversation”). Thereafter she had a number of communications with Mr Zaatini about the project.

  9. [121]

    Between 17 June 2010 and 6 September 2010 a further building contract for the Marrickville project (the “Second Contract”) came into existence, bearing the same date as the First Contract (that is, 24 November 2009). It named Transformer Group as the owner and, again, bore a purported signature of Mr Saaib as the builder. It was not in fact his signature.

  10. [122]

    Ms Alexandrova said that on about 29 or 30 September 2010 she came to believe that the Marrickville project had to be in Mr Saaib’s name as builder and not in the name of Award Build because of the latter’s limited eligibility to obtain insurance. She said that the initial intention of those involved had been for Award Build to be the builder and that she had been assisting Award Build to obtain an increase to its home warranty insurance eligibility limit to facilitate this but became aware that that would not be possible.

  11. [123]

    Ms Alexandrova gave evidence that, shortly after speaking to Mr Zaatini on 29 September 2010, she had a telephone conversation with Mr Saaib in which he stated “[b]oth the building contract and the home warranty insurance will be in my name” (the “Second Saaib Conversation”).

  12. [124]

    On 30 September 2010, Ms Alexandrova sent Mr Zaatini an email stating:

  13. [125]

    On 5 October 2010, Ms Alexandrova received an email from Mr Zaatini attaching a “QBE Builders’ Warranty Insurance” application form and a copy of a further building contract for the Marrickville project, dated 4 October 2010 (the “4 October Contract”). The 4 October Contract listed Transformer Group as the owner and Mr Saaib as the builder. Again, it is uncontested that Mr Saaib did not sign this contract. The 4 October Contract was the contract on which the Corporation sued (see [106] above). At about this time a document entitled “Building Contract Side Deed” between Australia and New Zealand Banking Group (the project financier) (“ANZ Banking Group”), Transformer Group and Mr Saaib was also created. It again bore Mr Saaib’s purported signature, which he denied signing or authorising anyone to sign on his behalf.

  14. [126]

    Ms Alexandrova deposed that, shortly after receiving the 5 October 2010 email, she had a telephone conversation with Mr Saaib (the “Third Saaib Conversation”) in which the following was said:

  15. [127]

    On 6 October 2010, Ms Alexandrova sent the 4 October Contract and the QBE insurance application form to OAMPS for submission to QBE. Mr Saaib gave evidence that on or about 12 October 2010 he signed and dated a blank Builder Eligibility Profile Change Application (the “Eligibility Application”) when he was in Mr Zaatini’s office. This was an application to increase Mr Saaib’s eligibility for home warranty insurance from $500,000. Mr Saaib deposed that Mr Zaatini told him that “there were lots of construction jobs around” and that the Eligibility Application was necessary if Mr Saaib was to do those jobs.

  16. [128]

    Ms Alexandrova gave further evidence that, following a number of communications with Mr Zaatini, on 13 October 2010 she had a conversation with Mr Saaib (the “Fourth Saaib Conversation”) which included the following:

  17. [129]

    Ms Alexandrova said that she had a further conversation with Mr Saaib on 14 October 2010 concerning “financials” that the intended insurer would or did require (the “Fifth Saaib Conversation”).

  18. [130]

    On 15 October 2010 at 11:31am, Mr Saaib sent Ms Alexandrova a text message (which was not in evidence). Ms Alexandrova’s evidence in cross-examination was that the text message said “Please call me”.

  19. [131]

    Also on 15 October 2010 Ms Alexandrova sent an email to Mr Zaatini saying that she had asked Mr Saaib for his 2009 and 2010 Financial Statements and that he said he only had those for 2009. Ms Alexandrova referred then to Mr Saaib’s accountant and said that if she received “all docs as per my previous email”, she would submit “the proposal” that day. She concluded by saying “the ball is in your court”.

  20. [132]

    Later that day, at 4:18pm, Ms Alexandrova sent a fax to OAMPS comprising seven documents: the Eligibility Application, a reference from an engineer, a reference from an architect, a statement purportedly signed by Mr Saaib as builder, financial statements for Saaib Construction Pty Ltd (a company of which Mr Saaib had previously been a shareholder and director), a home warranty insurance application dated 15 October 2010 which was purportedly signed by Mr Saaib and a payment sheet identifying expected progress payments for the Marrickville project works.

  21. [133]

    After further communications, on 18 January 2011 QBE, as agent for the NSW Self Insurance Corporation, issued home warranty certificates of insurance in respect of each of the Marrickville units identifying Mr Saaib as the builder of the works.

  22. [134]

    Construction of the Marrickville townhouses commenced soon after a construction certificate for the Marrickville project was issued on 15 February 2011. The construction continued until a final occupation certificate was issued on 20 December 2012. The primary judge found that, at about that date, “various subcontractors issued final trade certificates. Many of those trade certificates refer to ‘Mr Joe Anto[u]n’ or Transformer Group as the client. None refer to Mr Saaib”.

  23. [135]

    Her Honour made the following further findings concerning the construction:

  24. [136]

    The primary judge also referred to evidence of efforts to trace payments made by the project financier, ANZ Banking Group, to Transformer Group (the payments were made into Transformer Group’s bank accounts with ANZ Banking Group and with the Commonwealth Bank of Australia). Her Honour concluded:

THE PRIMARY JUDGMENT – THE SAAIB PROCEEDINGS

  1. [137]

    Success for the Owners Corporation in its proceedings against Mr Saaib was in practical terms dependent upon the Court’s acceptance of Ms Alexandrova’s evidence that she and Mr Saaib spoke on a number of occasions in a way that indicated his involvement as builder in the Marrickville project and indicated that he gave his authority to her to obtain home warranty insurance in relation to the project. This was so because her Honour accepted evidence that the purported signatures of Mr Saaib on critical documents, including the 4 October Contract, were forgeries and found that there was no basis on which it could be said that Mr Saaib undertook building work in relation to the Marrickville project.

Ms Alexandrova’s evidence

  1. [138]

    The primary judge referred at the outset to Mr Saaib’s reliance on the well-known statement of McLelland CJ in Eq in Watson v Foxman (1995) 49 NSWLR 315 at 319 as follows:

  2. [139]

    Her Honour made a number of general observations in the course of her careful consideration of Ms Alexandrova’s reliability as a witness and expressed the following conclusions:

  3. [140]

    Mr Saaib gave evidence denying speaking to Ms Alexandrova in the terms to which she deposed. Although the primary judge found aspects of his evidence to be unsatisfactory and unreliable, her Honour did not conclude that he deliberatively gave false evidence and made no finding of dishonesty against him.

  4. [141]

    Her Honour then turned to examine the five relevant conversations Ms Alexandrova said that she had with Mr Saaib in the period mid-2010 to October 2010 in which he allegedly acknowledged his role as builder in respect of the Marrickville project (see [120], [123], [126] and [128]-[129] above).

  5. [142]

    As to the First Saaib Conversation (see [120] above), her Honour concluded that Ms Alexandrova’s evidence was:

  6. [143]

    As to the Second Saaib Conversation referred to in [123] above, her Honour said:

  7. [144]

    In the absence of any documentary support, her Honour did not accept Ms Alexandrova’s evidence of the Third Saaib Conversation (see [126] above). Instead, her Honour found that Ms Alexandrova acted on the instructions of Mr Zaatini, rather than Mr Saaib, when she lodged the QBE insurance application form and the 4 October Contract with OAMPS on 6 October 2010.

  8. [145]

    The primary judge accepted Ms Alexandrova’s evidence that on 13, 14 and 15 October 2010 (in the Fourth and Fifth Saaib Conversations and the 15 October 2010 text message – see [128]-[130] above) she and Mr Saaib discussed her request for Mr Saaib to “sign the application” and that the Marrickville project may have been mentioned, there not being any reason for that not to occur. However her Honour was “unpersuaded that a reference in those calls to the Marrickville project or to an application that needed to be signed was understood by Mr Saaib to be anything other than a reference to the Eligibility Application and a possible future project or future ‘big job’”.

  9. [146]

    Speaking generally, her Honour noted the absence of any documentary evidence to support Ms Alexandrova’s evidence that her conversations with Mr Saaib indicated that he knew and approved of his name being used in the 4 October Contract as “builder” and concluded:

  10. [147]

    The primary judge added that she was not persuaded that a Jones v Dunkel inference should be drawn against Mr Saaib by reason of him not calling Mr Zaatini to give evidence (see Jones v Dunkel (1959) 101 CLR 298; [1959] HCA 8). Her Honour’s reasoning included the following:

Mr Saaib’s evidence

  1. [148]

    Mr Saaib deposed that in 2012 he was named as the builder in a home warranty insurance policy relating to the construction of a house in Leura that belonged to one of his close friends (the “Leura project”). He said that he was happy to assist in the construction as a “special favour”, that he was the builder but never got paid for the job, that the works are incomplete and that no works have been undertaken for about five years.

  2. [149]

    The Owners Corporation relied on the evidence relating to the Leura project to support the conclusion that Mr Saaib was willing to make the “same type of arrangement” for Mr Zaatini. However, the primary judge held that this evidence did not have significant probative value in relation to the factual issues in the present case and was not therefore admissible as tendency evidence. Her Honour’s reasoning included the following:

THE PRIMARY JUDGMENT – THE ALEXANDROVA PROCEEDINGS

  1. [150]

    The primary judge first noted that during closing submissions she granted the Owners Corporation leave to amend its Technology and Construction List Statement to rely, in the alternative to ss 18 and 236 of the Competition and Consumer Act 2010 (Cth), Sch 2 – Australian Consumer Law (“the ACL”), on ss 42 and 68 of the Fair Trading Act 1987 (NSW) as in force before the commencement of the ACL. Her Honour said that the amendments did not raise any new factual matters in the Owners Corporation’s misleading or deceptive conduct claim against Ms Alexandrova, or change the nature of its case.

  2. [151]

    In addressing that claim, her Honour found that, by submitting the insurance application and related documents to OAMPS (for transmission to QBE), Ms Alexandrova impliedly represented that Mr Saaib authorised her to do that on his behalf as the builder in respect of the Marrickville project. Her Honour rejected Ms Alexandrova’s submission that she was simply passing on information, finding:

  3. [152]

    Her Honour also found that this representation was misleading and deceptive because Mr Saaib did not enter into the 4 October Contract, did not authorise anyone else to do so on his behalf and did not authorise Ms Alexandrova to lodge the insurance application with OAMPS. Her Honour noted that Ms Alexandrova’s intent and honesty were not relevant in this respect.

  4. [153]

    In respect to causation, her Honour noted that the Owners Corporation’s case was one of reliance on misleading and deceptive conduct by a third party (namely OAMPS and QBE) causing the Owners Corporation loss. Her Honour then found that reliance by both OAMPS and QBE was established as it was not necessary for the Corporation to adduce direct evidence of reliance, it being open to the Court to infer reliance in an appropriate case.

  5. [154]

    Her Honour then turned to consider whether the Owners Corporation had established that it suffered loss by reason of Ms Alexandrova’s conduct, noting its submission as follows:

  6. [155]

    Her Honour concluded that causation of loss had been established, observing:

  7. [156]

    Her Honour then noted that Ms Alexandrova had “raised, by way of defence, that others are responsible for causing the Owners Corporation loss and should be liable” and that there were provisions in the Competition and Consumer Act 2010 (Cth) and the Civil Liability Act 2002 (NSW) providing for proportionate liability of apportionable damages claims where there are concurrent wrongdoers.

  8. [157]

    Her Honour noted:

  9. [158]

    As Ms Alexandrova had not pleaded a proportionate liability defence, her Honour found that Ms Alexandrova had no right to raise it. Her Honour therefore found Ms Alexandrova liable in respect of the full costs of rectifying the common property defects, totalling $3,425,583.54.

Ground 4 – whether Mr Saaib authorised Mr Zaatini to enter into the Marrickville building contract on his behalf

  1. [159]

    It is convenient to address Ground 4 first as it directly challenges the correctness of the primary judge’s ultimate finding in the Saaib proceedings and enables the following general, and later more specific, observations to be made concerning that challenge.

  2. [160]

    As noted in [137] above, in light of the primary judge’s forgery findings, success for the Owners Corporation in its claim against Mr Saaib was in practical terms dependent upon her Honour accepting Ms Alexandrova’s evidence of Mr Saaib making statements to her implicitly acknowledging his involvement in the Marrickville project as builder.

  3. [161]

    Ms Alexandrova was cross-examined at length, with the cross-examination occupying some 133 pages of transcript. In seeing and hearing Ms Alexandrova give her evidence, the primary judge had a considerable advantage over this Court in assessing her evidence. This advantage was enhanced by her Honour’s opportunity to hear the other evidence called in the proceedings, including that of Mr Saaib, and to consider the relevant documentary material over the seven days of the hearing.

  4. [162]

    Although her Honour’s rejection of Ms Alexandrova’s evidence was not based on any finding of dishonesty on her part, it was based on conclusions concerning her reliability which, as is apparent from the passages of the primary judgment quoted in [139] above, inevitably took into account her Honour’s observations of Ms Alexandrova in the witness box and her Honour’s assessment of Ms Alexandrova’s evidence when placed in the context of the whole of the evidence in the case.

  5. [163]

    As Mr Saaib submitted on appeal, the considerations to which McLelland CJ in Eq adverted in Watson v Foxman (see [138] above) often enable the rejection of evidence which has been given honestly, as it needs to be assumed it was in the present case. Mr Saaib contended that Ms Alexandrova’s evidence constituted evidence of the nature contemplated in Watson v Foxman, that is, evidence that is subconsciously reconstructed in a way that is self-serving.

  6. [164]

    Her Honour thoroughly considered all relevant contemporaneous documentary evidence when determining whether to accept or reject Ms Alexandrova’s evidence. There would be no point in repeating here the detail of her Honour’s reasoning to which I have referred in [139], [142]-[143] and [146] above. It is sufficient to draw attention to the following conclusory paragraphs:

  7. [165]

    Whilst this Court is obliged to conduct “a real review of the trial” and of the judge’s reasons (Fox v Percy (2003) 214 CLR 118; [2003] HCA 22 at [25]), it must refrain from interfering with a trial judge’s factual findings where, as in the present case, they:

  8. [166]

    As is apparent from its terms, that statement of principle applies not only in relation to factual findings likely to have been affected by the judge’s impressions about a witness’ “credibility” (if that term is taken in its narrow sense of honesty) but also to factual findings likely to have been affected by the judge’s impressions of a witness’ “reliability”.

  9. [167]

    Before referring to the matters upon which the Owners Corporation relies in support of Ground 4, I observe that there are at least four significant, unchallenged on appeal, aspects of evidence or findings that strongly support the primary judge’s conclusion.

  10. [168]

    First, Mr Saaib gave unchallenged evidence that he had never been to the Marrickville property and that he received no benefit, monetary or otherwise, from the construction on the property (J[186] quoted in [135] above).

  11. [169]

    Secondly, the primary judge made an unchallenged finding that there was “no evidence of any subcontracts between Mr Saaib and tradespersons who worked on the Marrickville project, purchase orders signed by Mr Saaib, invoices issued by subcontractors to Mr Saaib or receipts issued by Mr Saaib to subcontractors relating to the construction of the Marrickville property”. (J[185] quoted in [135] above).

  12. [170]

    Thirdly, an extensive tracing exercise did not identify the payment to Mr Saaib of any part of the funds drawn down by the property developer and owner (Transformer Group) from its financier (ANZ Banking Group). The evidence was that, once drawn down from the financier to Transformer Group’s bank accounts, the funds were paid out to a variety of recipients who included Award Build, Mr Nemer Antoun and Mr Zaatini.

  13. [171]

    Fourthly, the primary judge made a finding, unchallenged on appeal, “that at least 24 documents were created in relation to the Marrickville project that involved the falsification of Mr Saaib’s signature, the use of contact details of others, fake company names, false statutory declarations and an illegitimate insurance certificate” and that there was “no evidence that Mr Saaib received copies of those documents or was involved in their creation”.

  14. [172]

    To establish that her Honour’s ultimate finding as to Mr Saaib’s involvement in the project was “glaringly improbable” or “contrary to compelling inferences” (see [165] above), the Owners Corporation relied on the following matters:

  15. [173]

    These matters, whether taken individually or collectively, are in my view insufficient to render her Honour’s finding glaringly improbable or contrary to compelling inferences. Rather, the finding was consistent with the significant unchallenged matters referred to at [167]-[171] above and with the other evidence.

  16. [174]

    I nevertheless add the following specific comments concerning the matters relied upon by the Owners Corporation, as listed in [172] above:

  17. [175]

    For these reasons, Ground 4 should be rejected.

Ground 1 – whether Mr Saaib and Ms Alexandrova spoke regularly

  1. [176]

    By this ground the Corporation challenged the primary judge’s finding that the telephone call records in evidence supported her view that Mr Saaib and Ms Alexandrova were not in regular contact. Her Honour had said that by “regular” she was referring to something that was done “routinely or at uniform times”. Mr Saaib gave evidence that he spoke to Ms Alexandrova “regularly” in 2010 but what precisely he meant by that was not clearly elucidated.

  2. [177]

    In any event, the challenged finding was of limited significance in that it did not address the question of what Mr Saaib and Ms Alexandrova spoke about, a subject her Honour dealt with elsewhere in her judgment.

  3. [178]

    Further, the limited telephone records in evidence in any event suggested that Ms Alexandrova spoke far more frequently to Mr Zaatini than to Mr Saaib and did not indicate that Ms Alexandrova was “in regular contact” with Mr Saaib in the sense identified by her Honour .

  4. [179]

    For these reasons, Ground 1 should be rejected.

Ground 2 – whether Mr Saaib and Ms Alexandrova spoke about Marrickville

  1. [180]

    By this ground the Corporation challenged her Honour’s failure to be satisfied that Ms Alexandrova “spoke to Mr Saaib about the Marrickville project, his ‘role’ as builder or Mr Zaatini’s authority in relation to documents naming Mr Saaib as builder in the terms in which he deposes or more generally in relation to those matters prior to 12 October 2010”. One corollary of that failure to be so satisfied was a rejection of Ms Alexandrova’s evidence of the First, Second and Third Saaib Conversations to which I have referred above in [120], [123] and [126].

  2. [181]

    That rejection was supported by her Honour’s general reasoning which I have quoted in [146] above and by the following more specific observations:

  3. [182]

    As no error in this reasoning was demonstrated, Ground 2 should be rejected.

Ground 3 – whether Mr Saaib understood any references to the Marrickville project in his conversations with Ms Alexandrova in October 2010 as references to the Eligibility Application and the prospect of future work

  1. [183]

    Mr Saaib’s evidence that he had this understanding is not contrary to any evidence (other than that of Ms Alexandrova’s), nor is it improbable. As her Honour held, he gave a plausible explanation for that understanding, namely, that he had been told that the Eligibility Application was needed in relation to possible future projects or jobs, not that it was needed because he was the builder in respect of the Marrickville project.

  2. [184]

    Ground 3 should accordingly be rejected.

Ground 5 – whether a Jones v Dunkel inference arose from Mr Saaib’s failure to call Mr Zaatini as a witness

  1. [185]

    The primary judge declined to draw such an inference, being unpersuaded that Mr Zaatini was, at least at the time of trial, to be regarded as in Mr Saaib’s “camp” or that it was natural for Mr Saaib to call him (see Payne v Parker [1976] 1 NSWLR 191 at 201; ASIC v Hellicar (2012) 247 CLR 345; [2012] HCA 17 at [169]). As her Honour held, it was clear that there was no ongoing relationship between Mr Saaib and Mr Zaatini. Indeed, Mr Saaib regarded Mr Zaatini as a fraudster, describing him as such in a fraud report lodged on Mr Saaib’s behalf with the NSW Police. In evidence, Mr Saaib vehemently criticised Mr Zaatini as a “liar” and a “bullshit person”.

  2. [186]

    This ground of appeal should in these circumstances be rejected.

Ground 6 – whether the evidence relating to the Leura project was admissible as tendency evidence

  1. [187]

    The evidence relating to the Leura project and the use to which the Corporation sought to put it are referred to in [148] and [149] above, as are the primary judge’s reasons for concluding that the evidence did not have “significant probative value”.

  2. [188]

    As her Honour recognised, the evidence concerning the Leura project was not admissible as evidence relevant to Mr Saaib’s role in relation to the Marrickville project unless it had “significant probative value” (see s 97(1)(b) of the Evidence Act 1995 (NSW)). Although “s 97(1) does not… condition the admission of tendency evidence on the court’s assessment of operative features of similarity with the conduct in issue” (Hughes v The Queen (2017) 263 CLR 338; [2017] HCA 20 at [39]), “there must ordinarily be some feature of or about the offending [in a criminal case, or the fact in issue in a civil case] which links the two together” (R v Bauer (2018) 266 CLR 56; [2018] HCA 40 at [58]).

  3. [189]

    For good reason, the primary judge was satisfied in the present case that the circumstances of the Leura project were quite distinct from those of the Marrickville project, with the result that the former was not significantly probative of the issue concerning the Marrickville project that her Honour was required to determine.

  4. [190]

    No error having been shown, this ground of appeal should be dismissed.

Ground 7 – whether Mr Zaatini undertook the building work under Mr Saaib’s supervision

  1. [191]

    This ground partially overlaps with matter (e) quoted in [172] above. It should be rejected at least for the reason that the glaring improbability that the Corporation sought to be established was expressly based upon the proposition that “Mr Saaib had authorised Mr Zaatini to enter into the Marrickville project building on Mr Saaib’s behalf”. The primary judge however rejected this proposition and I have rejected the challenge to that rejection (see [173] above).

  2. [192]

    As none of the Corporation’s appeal grounds have merit, its appeal in the Saaib proceedings should be dismissed. In these circumstances it is unnecessary to address Mr Saaib’s Notice of Contention by which he sought to uphold the primary judge on a ground additional to those given by her Honour.

DETERMINATION OF THE APPEAL IN THE ALEXANDROVA PROCEEDINGS

  1. [193]

    Ms Alexandrova’s appeal against the primary judge’s finding that she is liable in damages to the Owners Corporation was based on the four contentions that are described in [110] above.

  2. [194]

    As I consider that her causation ground (that the Corporation did not prove that it suffered loss that was caused by Ms Alexandrova’s alleged misleading or deceptive conduct) should be upheld, it is unnecessary to deal with the other grounds.

  3. [195]

    As to the issue of causation, the primary judge noted that there was no evidence of what Transformer Group could and would have done absent the misleading and deceptive conduct and the issue of the home warranty insurance. Her Honour then concluded that Transformer Group “could not have proceeded with construction without that insurance and it seems reasonable to infer that it would have contracted with a licensed builder in order to do so” (J[505] quoted in [155] above).

  4. [196]

    As the Owners Corporation claimed damages from Ms Alexandrova under the Competition and Consumer Act 2010 (Cth), Sch 2 – Australian Consumer Law (“the ACL”) and, alternatively, under the Fair Trading Act 1987 (NSW) (as in force before the commencement of the ACL, see [150] above), it was necessary for it to establish that it suffered loss “because of the conduct” of Ms Alexandrova (in the case of s 236(1) of the ACL) or “by” that conduct (in the case of s 68 of the Fair Trading Act).

  5. [197]

    The plurality in Marks v GIO Australia Holdings Ltd (1998) 196 CLR 494; [1998] HCA 69 at [42] stated that in this context “that a comparison must be made between the position in which the party that allegedly has suffered loss or damage is and the position in which that party would have been but for the contravening conduct” but qualified that observation by indicating that the “but for” test embodied in it may not provide an answer to a causation issue in all cases.

  6. [198]

    The Owners Corporation relied on statements in I & L Securities Pty Ltd v HTW Valuers (Brisbane) Pty Ltd (2002) 210 CLR 109; [2002] HCA 41 at [33], [57] and [62] that it is sufficient that contravening conduct be a “material” cause of the plaintiff’s loss, as distinct from the “sole” or “predominant” cause. In that case the Court was concerned with the reason or reasons the representee entered into the relevant transaction, not with the “but for” question relevant to that case of whether entry into the transaction was detrimental to it. The Court did not suggest that the latter question was not relevant. Rather, the answer was treated as obvious in light of the evidence in the case.

  7. [199]

    The parties in the present case did not otherwise suggest that a “but for” approach to the issue of causation was inappropriate. Rather, they differed as to what the outcome of adoption of that approach was in this case. The Court was referred by Ms Alexandrova to Abigroup Contractors Pty Ltd v Sydney Catchment Authority (No 3) (2006) 67 NSWLR 341; [2006] NSWCA 282 at [36] et seq for a consideration of the general concepts involved but that was a different case to the present in that it only involved what is a familiar inquiry as to what a representee, who sues the representor for damages, would have done if a misleading and deceptive representation had not been made to it. A similar inquiry had to be made in the present case but a further inquiry needed to be made as well.

  8. [200]

    As to the initial inquiry, it can readily be concluded in the present case that QBE, as the insurer’s agent, would not have proceeded to have the insurance issued unless someone such as Ms Alexandrova had represented to it that Mr Saaib was the builder in respect of the Marrickville project and had authorised the application for insurance. Likewise, it is clear that if QBE had been told that those assertions were not accurate, it would not have proceeded to arrange the insurance.

  9. [201]

    Resolution of the causation issue in the present case however ultimately involves consideration of whether the Owners Corporation (through its predecessor, Transformer Group) would have obtained the benefit of valid insurance but for Ms Alexandrova’s misleading and deceptive conduct. The Corporation needed to show what would probably have occurred in that circumstance. That involved postulating who would have sought the insurance as, or on behalf of, the builder. Those who did so in the events that actually occurred engaged in extensive dishonest and fraudulent conduct by forging Mr Saaib’s signature on at least 24 documents (see [171] above). Can it be inferred that such conduct would not have been repeated?

  10. [202]

    I do not consider that there is any basis in the evidence for drawing in the Corporation’s favour either of the inferences that might have resolved the causation issue in its favour.

  11. [203]

    First, there is no basis for inferring that if the same individuals, other than Ms Alexandrova, were involved in the hypothetical circumstance that they would have sought and obtained home warranty insurance by honest means. There was, for example, no evidence that the services of a suitably qualified builder were available and acceptable to them. The inference at least equally available is that a different name to that of Mr Saaib would have been dishonestly proffered to an insurer, or insurer’s agent, or that different means would have been found to advance his purported application.

  12. [204]

    Secondly, there is no basis in the evidence for an alternative inference that if Ms Alexandrova had not been involved, or at least had not engaged in the conduct she did, that Transformer Group (whose actions are relevant because it is its rights to which the Corporation succeeded) would have engaged a completely different, and suitably qualified, builder. No evidence was called to suggest this and it seems an unlikely occurrence as the evidence did not enable any clear distinction between Transformer Group, Award Build and Mr Zaatini, some or all of whom seem to have been responsible for the forgeries and for the construction work that occurred, as well as being recipients of construction finance draw downs (see [170] above).

  13. [205]

    As consideration of how persons other than the representee would have acted is required, there is some analogy, albeit limited, to Badenach v Calvert (2016) 257 CLR 440; [2016] HCA 18 in which proof of causation in an action by an intended beneficiary against a solicitor involved proof of how the solicitor’s client would have acted if the solicitor had not given the client allegedly negligent advice. The intended beneficiary’s claim was for the loss of a chance (a claim that was eschewed in the present case). Even so, that intended beneficiary failed to discharge his onus of demonstrating that there was at least a substantial prospect that the client, who was not the representee, would have acted in a manner favourable to the intended beneficiary’s interests (see [40] and also Mal Owen Consulting Pty Ltd v Ashcroft (2018) 97 NSWLR 1163; [2018] NSWCA 135 at [60]-[70]).

  14. [206]

    Returning to the primary judge’s reasoning in the present case, it is certainly correct that Transformer Group could not have proceeded with the building work without home warranty insurance, as s 92 of the Home Building Act required the builder of a residential construction such as the Marrickville project to ensure that a contract of insurance that complied with the Act was in force. However I do not, with respect, agree with the primary judge that in the circumstances of this case it should be inferred that, absent the misleading and deceptive conduct that her Honour found, Transformer Group would have contracted with a licensed builder and would have obtained the benefit of a valid contract of insurance. For the Corporation to succeed on this point the Court would have to have had “a reasonable basis for a definite conclusion affirmatively drawn of the truth of which” it was reasonably satisfied (Jones v Dunkel (1959) 101 CLR 298 at 305; [1959] HCA 8). There is no such basis in the present case.

  15. [207]

    As I have indicated, a positive inference cannot be drawn that those associated with Transformer Group and/or Award Build would have acted any differently than they did in the circumstances that in fact occurred. When it became apparent that Award Build was not qualified to obtain home warranty insurance for the Marrickville project, persons associated with Transformer and/or Award Build caused the creation and utilisation of forged documents that created the charade that Mr Saaib, who was a licensed builder with the potential to obtain entitlement to the relevant home warranty insurance, was the builder in respect of the Marrickville project, or at least had authorised use of his name as such builder. As her Honour held in a finding that was not challenged on appeal, at least 24 documents involving the falsification of Mr Saaib’s signature were created in relation to the Marrickville project. It is not necessary for present purposes to determine who precisely was responsible for this. It is sufficient to note that Mr Zaatini, Mr Joe Antoun and Mr Nemer Antoun were associated at the relevant time with Transformer Group and/or Award Build and that the evidence suggests that one or more of them was likely to have been responsible (see [106] and [114] above).

  16. [208]

    In these circumstances it cannot be concluded that, but for the assumed misleading and deceptive conduct, the Corporation would have obtained valid insurance. Any loss it suffered was thus not demonstrated to have been caused by that conduct.

  17. [209]

    As the primary judge found otherwise, the appeal should be allowed. It is unnecessary to address the Owners Corporation’s Notice of Contention as it did not relate to the ground upon which I have found that the appeal should succeed.

ORDERS

  1. [210]

    For the reasons given above, I propose the following orders:

    1. (1)

      Dismiss the appeal.

    2. (2)

      Order the appellant to pay the respondent’s costs of the appeal.

    3. (1)

      Appeal allowed.

    4. (2)

      Set aside the orders made in the Equity Division on 1 March 2021.

    5. (3)

      Dismiss the Owners Corporation’s amended summons filed in the Equity Division on 11 March 2020.

    6. (4)

      Order the respondent to pay the appellant’s costs of the proceedings at first instance and on appeal.

In the Alexandrova proceedings (NSWCA No 140048 of 2021)

  1. [211]

    GLEESON JA: I agree with Basten JA.

Unofficial copy. Source: NSW Caselaw. Refer to the official version for authoritative text.