[2015] NSWSC 1058
Wang v Kaymet Corporation Pty Ltd
Tender of expert report rejected
Catchwords
EVIDENCE – admissibility – expert opinion – whether opinion shown to be based on expert’s specialised knowledge – whether expert’s process of reasoning revealed – whether mere ipse dixit – whether report unfairly prejudicial to the plaintiffs
Legislation cited
- Civil Liabilities Act 2002 (NSW)
- Evidence Act 1995 (NSW)
Judgment
- [1]
The hearing of these proceedings commenced on 20 July 2015. This is the fifth day of the hearing.
- [2]
The proceedings concern the development of two towers of apartments at Wolli Creek, adjacent to the East Hills railway line.
- [3]
By contracts entered into with the defendants between November 2009 and April 2010, the plaintiffs agreed to purchase "off the plan" 43 of the 94 residential apartments proposed to be built in the development.
- [4]
Each contract contained a promise by the defendants to use their "reasonable endeavours", in effect, to complete the project within 30 months of contract, and provided that either party could rescind the contract if completion did not take place within that time.
- [5]
The project was not completed by the relevant date. The defendants have purported to rescind the contracts. The plaintiffs dispute that the defendants were entitled to rescind.
- [6]
The property market has risen. It is common ground that the now complete apartments are worth very much more than the contract prices. In those circumstances, the plaintiffs seek specific performance of the contracts.
- [7]
The ultimate matter for determination in these proceedings is whether the defendants used reasonable endeavours to finish the project by the critical date.
- [8]
The defendants seek to tender a report of Mr Michael Wynn-Jones.
- [9]
Mr Wynn-Jones is a practising building surveyor and certifying authority. He is a Conjoint Professor at the School of Architecture and Built Environment at the University of Newcastle and a Fellow of the Australian Institute of Building Surveyors and of the Australian Institute of Building.
- [10]
In his report, Mr Wynn-Jones states that his instructions were:
- [11]
Mr Wynn-Jones adopts defined meanings for "foreseeable time" and thus for "unforeseeable time".
- [12]
Mr Wynn-Jones states that, for the purpose of his report, "foreseeable time" is the "estimated time allowed to complete an event or stage" of the development. He continues that "a reasonable developer would estimate the time allowed for the various stages and events therein to be completed". I infer from that statement that Mr Wynn-Jones envisages that the estimate of time to which he refers is that which would be made by a "reasonable developer".
- [13]
"Unforeseeable time" is, unsurprisingly, defined as time which is not “foreseeable”.
- [14]
One difficulty I see with Mr Wynn-Jones's report is that there is no exposition by him of the basis upon which the hypothetical reasonable developer would make the estimate to which Mr Wynn-Jones refers.
- [15]
Mr Wynn-Jones goes on to purport to identify a "reasonable certifying authority" and a "reasonable consent authority" by reference to s 5O(1) of the Civil Liability Act 2002 (NSW).
- [16]
Thus, Mr Wynn-Jones states:
- [17]
Mr Wynn-Jones's overall conclusions as to "unforeseeable time" are as follows:
- [18]
Mr Wynn-Jones also concluded:
- [19]
Mr Wynn-Jones had no involvement in the construction of this project and has not inspected any part of the building.
- [20]
His report does not set out any assumptions he has made other than to refer globally to the various documents set out at appendix C.
- [21]
Mr Wynn-Jones’s report concludes that there has been "unforeseeable time" in relation to four matters. The first is "RailCorp's requirements". The second is "work on or over a public road". The third is "landscape plan and statement". The fourth is "construction certificates for upper levels".
- [22]
The extent to which Mr Wynn-Jones has exposed his process of reasoning may be demonstrated by his treatment of "RailCorp's requirements".
- [23]
Mr Wynn-Jones has calculated that, as a matter of fact, it took 707 days for RailCorp to consent to the relevant development.
- [24]
Mr Wynn-Jones opines that of those 707 days, only 100 days were "foreseeable".
- [25]
As I read Mr Wynn-Jones's report, his reasoning commences with consideration of a letter that RailCorp sent to Rockdale City Council on 24 April 2008.
- [26]
Mr Wynn-Jones sets out the following extracts from that letter:
- [27]
And:
- [28]
Having recited those extracts, Mr Wynn-Jones states:
- [29]
Mr Wynn-Jones does not state what "statutory clock" is being referred to (other than, inferentially, being that which RailCorp referred to in its letter). He simply asserts that RailCorp could "reasonably be expected" to indicate its concurrence within 21 days after an application was lodged with "sufficient information". He does not explain by what measure that reasonable expectation would arise.
- [30]
Mr Wynn-Jones then states:
- [31]
I am unable to see, from Mr Wynn-Jones's report, by which process of reasoning he comes to the conclusion he sets forth in that paragraph.
- [32]
It seems to me to be mere ipse dixit.
- [33]
I invited Mr Corsaro of senior counsel, who appears with Mr Bambagiotti and Mr Auld for the defendants, to direct me to any passages later in Mr Wynn-Jones's analysis of the RailCorp situation which might explain how it was that Mr Wynn-Jones settled on 100 days as being foreseeable. He was not able to do so.
- [34]
Following that passage in Mr Wynn-Jones's report is an analysis of documents passing to and from RailCorp.
- [35]
I do not see, within that analysis, any conclusion reached by Mr Wynn-Jones as to when "sufficient information" was provided to RailCorp.
- [36]
Mr Wynn-Jones's final conclusion is as follows:
- [37]
I am not able to see by what process of reasoning Mr Wynn-Jones concluded that “say” 100 days was “foreseeable time” and that the balance of 607 days was not.
- [38]
Mr Wynn-Jones's analysis of the other three areas to which I have referred is similar.
- [39]
In relation to "work on or over a public road", Mr Wynn-Jones analyses a number of conditions evidently imposed on the development by Rockdale City Council, sets out extracts from some document, and then simply concludes:
- [40]
Again, I see no indication at all of the process of reasoning that Mr Wynn-Jones adopted.
- [41]
The situation is even worse in relation to Mr Wynn-Jones’s treatment of the "landscape plan and statement".
- [42]
Mr Wynn-Jones sets out briefly some aspects of that matter and then simply says that his opinion concerning work on or over a public road “applies”.
- [43]
Mr Wynn-Jones adopts a similar process in relation to the remaining subject matter; "construction certificates for upper levels".
- [44]
Whilst Mr Wynn-Jones doubtless has specialised knowledge in his area of expertise, his report does not reveal how the conclusions to which he has come are based on that knowledge.
- [45]
He seeks to apply his defined terms of "reasonableness" and "foreseeability" to reach untestable conclusions.
- [46]
I see no exposition of the chain of reasoning that has led him to those conclusions.
- [47]
In my opinion, the report is unfairly prejudicial to the plaintiffs. In that regard, I accept the submission made by Mr McInerney of senior counsel, who appears with Mr Jacobs for the plaintiffs, that if the defendants:
- [48]
In any event, Mr Wynn-Jones's conclusions are, to a large extent, directed to the ultimate question of whether the defendants used reasonable endeavors to finish the project by the critical date, particularly his overall conclusion which I have set out at [18] above.
- [49]
The fact that Mr Wynn-Jones expresses opinions directed to the ultimate question in the proceedings is not necessarily a reason to reject the report (see s 80 of the Evidence Act 1995 (NSW)). However, in this case, I do not see how I will be assisted by Mr Wynn-Jones's untestable conclusions as to the very question I have to decide.
- [50]
It may be that some of the matters contended for by Mr Wynn-Jones could form the basis of a submission by counsel. But I do not accept that they can be advanced as expert opinion.
- [51]
I reject the tender of Mr Wynn-Jones's report.