[2025] NSWSC 1005
CPB Contractors Pty Limited v Transport for NSW
Paragraphs of the Second Further Amended Technology and Construction List Statement are struck out
Catchwords
PRACTICE AND PROCEDURE – Practice Note SC Eq 3 – CONTRACTS – Construction – Application to strike out paragraphs of a Technology and Construction List Statement pleading a claim in contract on the basis that no reasonable cause of action is disclosed – Whether such an application should be entertained – Where plaintiff claims an entitlement to delay costs for delay or disruption to it carrying out work on a substantial contract to the upgrade of a highway – Where the Contract, on its proper construction, makes no provision for the Claim – HELD – Claim struck out
Cases cited
- Aon Risk Services Australia Ltd v Australian National University (2009) 239 CLR 175;[2009] HCA 27
- Australian Broadcasting Commission v Australasian Performing Right Association Ltd (1973) 129 CLR 99;[1973] HCA 36
- Baffico v YMCA of Great Lakes Inc[2014] NSWCA 61
- David William Pallas & Julie Ann Pallas as trustees for the Pallas Family Superannuation Fund v Lendlease Corporation Limited; Martin John Fletcher v Lendlease Corporation Limited[2019] NSWSC 1631
- Electricity Generation Corporation Ltd v Woodside Energy Ltd (2014) 251 CLR 640;[2014] HCA 7
- General Steel Industries Inc v Commissioner for Railways (NSW) (1964) 112 CLR 125;[1964] HCA 69
- Harrington v Browne (1917) 23 CLR 297;[1917] HCA 36
- HNOE Limited v Angus & Julia Stone Pty Ltd[2024] NSWCA 271
- Lepcanfin Pty Ltd v Lepfin Pty Ltd (2020) 102 NSWLR 627;[2020] NSWCA 155
- McCann v Switzerland Insurance Australia Ltd (2000) 203 CLR 579;[2000] HCA 65
- Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd (2015) 256 CLR 104;[2015] HCA 37
- Pacific Carriers Ltd v BNP Paribas (2004) 218 CLR 451;[2004] HCA 35
- Voth v Manildra Flour Mills Pty Ltd (1990) 171 CLR 538;[1990] HCA 55
- Wilkie v Gordian Runoff Ltd (2005) 221 CLR 522;[2005] HCA 17
- Zhu v Treasurer of the State of New South Wales (2004) 218 CLR 530;[2004] HCA 56
Legislation cited
- Civil Procedure Act 2005 (NSW) § 15
- Practice Note SC Eq 3
Judgment
- [1]
The plaintiff is a construction company. The defendant is Transport for New South Wales, a New South Wales government agency. They are embroiled in a substantial building dispute about an upgrade to the Pacific Highway between Woolgoolga and Ballina on the NSW North Coast.
- [2]
By written instrument styled Deed of Contract Agreement made on 25 October 2017 (the Contract), the defendant as Principal retained the plaintiff as Contractor to do the upgrade. The Contract incorporates General Conditions and a schedule entitled Contract Information.
- [3]
References below to clauses are references to clauses in the General Conditions and references to Items are references to Items in the Contract Information.
- [4]
The principal proceedings were initiated on 28 July 2022 by the plaintiff filing a Summons and Technology and Construction List Statement (the List Statement). The List Statement runs to over 200 pages. The List Statement spawned a List Response and Cross-Claim Statement, running with annexures to some 1000 pages. There is also a List Reply running to some 70 pages and a brief Cross-Claim List Response.
- [5]
The plaintiff’s claims total $188 million.
- [6]
One of its claims is for further allowances for delay costs from wet weather or its consequential effects, which are said to have delayed the Contractual Completion Date. There is no dispute that if the facts support it, such a claim can be brought under the Contract.
- [7]
Another claim (the Claim) – the subject of the immediate controversy –introduced by an amendment to the List Statement on 29 November 2024, is for “delay costs for disruption” amounting to $63.4 million (of the total).
- [8]
For its part, the defendant cross-claims for liquidated damages for delay. The defendant’s claim is of the order of $36 million.
- [9]
By Notice of Motion filed 8 July 2025, the defendant moves for the Claim to be struck out because the Contract, on its proper construction, cannot support it.
- [10]
The question first to arise was whether the Court should entertain the application.
- [11]
Practice Note [1] SC Eq 3 (the Practice Note) applies to proceedings in the Commercial List and Technology and Construction List (the Lists) of the Equity Division. It contains the following paragraph 65:
- [12]
This provision is one of a number in the Practice Note calculated towards ensuring speedy resolution of the real issues in commercial causes [2] by avoiding time consuming and possibly fruitless applications and the corresponding waste of judicial resources.
- [13]
Commonly, the assessment of whether an application should be entertained or not can (and should) be made summarily (in particular where the Court has received written submissions in advance which is usually the position). This is the same approach to be taken with respect to forum non conveniens applications Voth v Manildra Flour Mills Pty Ltd (1990) 171 CLR 538 at 565; [1990] HCA 55 and class action carriage applications David William Pallas & Julie Ann Pallas as trustees for the Pallas Family Superannuation Fund v Lendlease Corporation Limited; Martin John Fletcher v Lendlease Corporation Limited [2019] NSWSC 1631 at [37].
- [14]
The object of the provision will be defeated if a significant amount of time, that is more than a few minutes, is taken up in oral argument on whether the application should be entertained (especially when the Court then decides not to entertain it).
- [15]
In this case written submissions had been received from both sides. On reading them, my initial impression was that the application had some force, whereas the plaintiff’s position was correspondingly lacking in force, although not necessarily hopeless. However, the ostensible complexity of the argument made it inappropriate, without more, to make an abbreviated upfront determination that the application should or should not be entertained. Rather, I took the course of hearing substantive argument on the footing that a determination that the application should not be entertained remained an option.
- [16]
In a well-known and oft-cited passage in General Steel Industries Inc v Commissioner for Railways (NSW) (1964) 112 CLR 125 at 130; [1964] HCA 69 Barwick CJ said of the jurisdiction to terminate an application summarily for want of a cause of action in the plaintiff is to be sparingly employed and ought not to be used save where the lack of the cause of action is clearly demonstrated. Yet the jurisdiction should not be reserved for those cases where argument is unnecessary to evoke the futility of the plaintiff’s claim. Argument, even of an extensive kind, may be necessary to demonstrate that the plaintiff’s case is so clearly untenable that it cannot possibly succeed.
- [17]
In the context of an application like the present one, founded on the proper construction of a contract, the Court of Appeal in Lepcanfin Pty Ltd v Lepfin Pty Ltd (2020) 102 NSWLR 627; [2020] NSWCA 155 at [97] observed that the issue was essentially a question of construction and referred to the statement of Isaacs J in Harrington v Browne (1917) 23 CLR 297 at 307; [1917] HCA 36 that “there can only be one construction given to a contract”.
- [18]
Although the Practice Note adds an additional barrier to applications for summary judgment and striking out, there are cases where they are warranted: see HNOE Limited v Angus & Julia Stone Pty Ltd [2024] NSWCA 271 at [58]-[59].
- [19]
As it turned out, this is such a case.
- [20]
Because of the apparent complexity of the application, I took the course of hearing substantive argument without initially deciding separately whether the application should not be entertained.
- [21]
When close attention is paid to the words of cl 51 of the Contract – around which the immediate controversy is centred – the futility of the Claim is evoked. It is demonstrated to be so clearly untenable that it cannot possibly succeed.
- [22]
The Contract defines Contractual Completion Date to mean, relevantly, the last date by which the Contractor must achieve Completion of the Works. [3] It defines Completion, relevantly, to mean the state of the Works being complete (cl 79).
- [23]
Clause 50, headed Changes to Contractual Completion Dates, provides, relevantly, that the Contractor is entitled to an extension of time to any Contractual Completion Date for the number of days assessed by the Principal if the Contractor satisfies the Principal that the Contractor is or will be delayed in achieving Completion by a cause beyond the control of the Contractor which occurs on or before the Contractual Completion Date.
- [24]
It is appropriate to set out the whole of cl 51 even though doing so contributes to the prolixity of this judgment:
- [25]
Clause 8.8 makes provision for the Principal to instruct the Contractor to use a particular work method or change a specified work method and that if the Principal does so without the Contractor first agreeing in writing the effects of the instruction, the Contractor may claim an extension of time in accordance with cl 50 and consequent delay costs under cl 51. Clause 48 entitles the Principal to instruct a Variation before Completion of the whole of the Works.
- [26]
The Contract includes as Item 49A Table 2 which sets out the monetary rates which apply for delay costs per working day for any “delay to Completion of the whole of the Works”. A working day is defined in Item 18 as Monday to Friday and Saturdays but excluding proclaimed public holidays and the Contractor’s rostered days off.
- [27]
Paragraph 7 of the List Statement pleads express terms of the Contract. Paragraph 7(wA)(i) and (ii) plead:
- [28]
Paragraph 7(wB) pleads:
- [29]
Paragraph 329 (read with paras 324 to 328) pleads that the plaintiff was delayed in achieving Completion because of instructions amounting to Variations given by the defendant. In the particulars to the paragraph, it is said that achieving Completion was delayed by 159 working days. Paragraphs 331 and 332 plead that the plaintiff is entitled to an extension of time to the Contractual Completion Date of at least 159 working days. Paragraph 334 pleads that by reason of these matters the plaintiff is entitled to delay costs for delay or disruption calculated in accordance with the Contract Information for at least 159 working days which yields a figure of $11.9 million. This number of working days is particularised as comprising four different periods of working days, each said to be due to a particular instruction. The periods in working days are 17, 62, 32 and 48, respectively.
- [30]
It will be readily appreciated that this claim squares with the uncontroversial elements of cll 50 and 51 namely:
- (1)
a Variation and/or instructions (cll 51.1.1 and 51.1.3);
- (2)
entitlement to an extension of time in a specified number of working days to the Contractual Completion Date for the whole of the Works;
- (3)
application of the delay costs rate to that number of working days;
- (1)
- [31]
But then, the plaintiff goes on to plead (para 334(b)) that, because of the defendant’s instructions, it is also entitled to delay costs for delay or disruption calculated at the applicable rate in the Contract for “the number of working days of disruption within the meaning of cl 51.1 of the Contract that occurred during the period of the delays to Completion” referred to. In the particulars it says that the instructions caused 839 days of disruption valued at $63.4 million.
- [32]
The plaintiff identifies that during each period of working days forming part of the delay claim a significantly greater number of working days of disruption “occurred across the Project” for which it is entitled to delay costs for disruption. In relation to the 17 working days component of the delay claim it says that 109 working days of disruption occurred during that period.
- [33]
The underlying thesis of the Claim is that cl 51 permits two kinds of claims for delay costs for delay or disruption. The first (and uncontroversial for present purposes) is for those working days by which the Contractual Completion Date has blown out for a cause specified in cl 51.1. The second (and highly controversial) is for working days of disruption which played no part in the blowout of the Contractual Completion Date but which were lost due to disruption during the period of working days by which the Contractual Completion Date must be extended (and claimed for in the first claim).
- [34]
Paragraphs 381(b) and 383(b) refer to paras 7(wA), 7(wB), 335-6 and 376-9. They plead the Claim slightly differently, based on a failure by the defendant to be satisfied of the plaintiff’s entitlement to delay costs for “the number of working days of disruption that occurred during the period of the delays to Completion specified in paragraph 334(a) above because of the instructions”. The difference in pleading is immaterial for present purposes. It was not suggested that the outcome of the application is affected by the difference.
- [35]
The defendant argues that:
- (1)
the plaintiff pleads an express term of the Contract as the basis for the Claim;
- (2)
an examination of the Contract reveals that it contains no such term;
- (3)
clauses 50 and 8.8 work clearly and congruently with cl 51.1. The first two contain a structure for the granting of extensions of time and the third provides an entitlement to delay costs calculated by multiplying the number of working days by which the Contractual Completion Date is extended by the specified monetary rate;
- (4)
the plain meaning of cl 51.2 is that delay costs are calculated at the applicable rate for – meaning in respect of – the number of working days by which the Contractual Completion Date for the whole of the Works is extended leaving no room for a separate claim for delay costs for disruption which has no effect on the Contractual Completion Date.
- (1)
- [36]
The plaintiff argues that:
- (1)
clause 51 distinguishes between, and permits separate claims for, delay costs respectively, for delay and disruption;
- (2)
the terms delay and disruption have the following different and specialised meanings which are well-known in the construction industry: delay means an event that gives rise to an extension of the time required to complete a project – sometimes called “critical path delay”; disruption is “non-critical delay”; being an event which causes delay to work activities off the critical path, that is, not causing completion of the Project to be delayed. The plaintiff intends to call expert evidence to support this;
- (3)
clause 51 should thus be construed as recognising claims for disruption which have not caused any delay in Completion of the whole of the Works;
- (4)
where used in cl 51.2, the word for in the phrase “for the number of working days” means during;
- (5)
accordingly, provided the disruption occurs during the working days which are lost and which cause an extension of the Contractual Completion Date, it is compensable at the specified rate (even though it does not itself cause any delay in the Completion of the Works);
- (6)
limiting claims for disruption in that way is a brake on claims for disruption.
- (1)
- [37]
The Contract is a commercial contract which is to be given a business-like interpretation. Interpreting it requires attention to the language used by the parties, the commercial circumstances which it addresses, and the objects which it is intended to secure. The meaning of the words chosen is determined objectively by reference to its text, context, and purpose, the question being what a reasonable businessperson would have understood them to mean. Preference is given to a construction supplying a congruent operation to the various components of the whole, so as to avoid commercial inconvenience. Where language is open to more than one construction, the Court will prefer a construction which avoids consequences which are capricious, unreasonable, inconvenient or unjust (see Australian Broadcasting Commission v Australasian Performing Right Association Ltd (1973) 129 CLR 99 at 109; [1973] HCA 36; McCann v Switzerland Insurance Australia Ltd (2000) 203 CLR 579; [2000] HCA 65 at [22]; Pacific Carriers Ltd v BNP Paribas (2004) 218 CLR 451; [2004] HCA 35 at [22]; Zhu v Treasurer of the State of New South Wales (2004) 218 CLR 530; [2004] HCA 56 at [82]; Wilkie v Gordian Runoff Ltd (2005) 221 CLR 522; [2005] HCA 17 at [15]; Electricity Generation Corporation Ltd v Woodside Energy Ltd (2014) 251 CLR 640; [2014] HCA 7 at [35]; Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd (2015) 256 CLR 104; [2015] HCA 37 at [47]-[51]). See too Lepcanfin (supra).
- [38]
The plaintiff’s construction cannot be right because:
- (1)
contrary to the settled canon that the words of a contract can only have one construction, the plaintiff’s construction requires the word for (where it first appears in cl 51.2) to be given ambulatory construction and therefore operation, when applied to a claim for delay which caused an extension of the Contractual Completion Date as opposed to a claim for disruption which did not cause such an extension. In the first case, for bears its ordinary English meaning of “in respect of”, but in the second case, ie. the Claim, it has to mean “during”;
- (2)
when the phrase “for the number of working days by which the Contractual Completion Date for the whole of the Works is extended” is applied in the first case, what is required is simply to multiply the applicable rate in Item 49A Table 2 by the number of working days of the extension. However, with the Claim the plaintiff would have it that one takes a number of working days calculated by periods of disruption during the period when there were events which caused an extension of the Contractual Completion Date and multiplies that by the applicable rates in Item 49A Table 2. This gives no work to the words “by which the Contractual Completion Date for the whole of the Works is extended”. It entails an operation for which cl 51.2 does not provide;
- (3)
the only provision for calculation of delay costs is cl 51.2 and the only method of calculation is the application of the specified rate to the number of working days by which the Contractual Completion Date for the whole of the Works is extended. It is not necessary to determine whether the terms delay and disruption are terms of art having some meaning different from their ordinary English one. Even if they do, all the rates specified in Item 49A Table 2 are expressly “For any delay to Completion of the whole of the Works…”. There is no provision in the Contract for any other calculation such as that required by the plaintiff’s construction. There is no machinery for any claim to be made or assessed whether for delay or disruption which does not cause an extension to the Contractual Completion Date for the whole of the Works;
- (4)
there is no discernible commercially rational reason why the plaintiff should be compensated where there is an extension to the Contractual Completion Date for the whole of the Works as well as for disruption during the period which gives rise to the extension of the Contractual Completion Date but which itself plays no part in bringing about that extension. Its construction and operation leads to the commercially irrational possibility that the plaintiff is entitled to two heads of compensation referable to a single period, the second head of which does not entail any extension to the Contractual Completion Date of the whole of the Works and which (as it does in the case of the Claim) can exceed the compensation referable to the period of the extension by multiples. The claim in the first category is for $11.9 million, the claim in the second is for $63.4 million, a commercially absurd result;
- (5)
there is no commercially rational reason for the brake for claims for disruption which the plaintiff suggests;
- (6)
the plaintiff’s construction requires an examination of periods of disruption and conversion of those periods into working days without any reference to the number of working days by which the Contractual Completion Date is extended, an exercise for which the Contract makes no provision.
- (1)
- [39]
Paragraphs 7(wB)(ii), 334(b), 337(b), 381(b) and 383(b) of the Second Further Amended Technology and Construction List Statement are struck out.
- [40]
I provisionally order that the plaintiff is to pay the defendant’s costs of the motion. This order will solidify seven days after delivery of this judgment unless any party notifies the other party and my Associate, in writing, that some other order is sought, specifies the order and provides brief grounds. If notice is given, the order will not take effect and I will determine any costs issues.
- [41]
The proceedings are stood over into the Technology and Construction List on 19 September 2025 with liberty to apply on three days’ notice.