[2025] NSWSC 1382
Patel v Dev Constructions (NSW) Pty Ltd
(1) The plaintiff is to email to the Chambers of Bennett J proposed Short Minutes of Order to give effect to this judgment by 4:00pm on 1 December 2025. (2) By 4:00pm on 1 December 2025, the plaintiff is to serve on Nidhiben Kamlesh Patel, the co-owner of the land in folio identifier X/XXXXX, known as X XXXX Street, Wentworthville, New South Wales: (a) a copy of these reasons for judgment; and (b) the proposed Short Minutes of Order prepared in accordance with order 1. (3) By 4:00pm on 8 December 2025, Nidhiben Kamlesh Patel is to notify the Chambers of Bennett J by email if she wishes to be heard. (4) Subject to order 5, the defendants are to pay the plaintiff's costs. (5) Within 7 days of the publication of this judgment, the parties may make an application by email to my Associate to vary order 4. Further orders will be made for the filing and serving of submissions by the parties in relation to any such application. (6) Any further issue as to costs will be determined on the papers.
Catchwords
EQUITY — Equitable remedies — Injunctions — Where plaintiff contracted with builder for the construction of a house — Where plaintiff terminated contract with builder — Where builder has left materials on the construction site where plaintiff’s house is being built — Where builder has since had altercations with plaintiff and contractors subsequently engaged by plaintiff — Whether the leaving of building materials is a trespass — Whether plaintiff entitled to injunction against builder preventing entry onto land LAND LAW — Co-ownership — Where plaintiff owns land as joint tenant — Where co-owner of land is not joined as a party to proceedings — Whether plaintiff can seek injunction to prevent entry onto land without joining other co-owner
Cases cited
- Bendal Pty Ltd v Mirvac Project Pty Ltd(1991) 23 NSWLR 464
- Blacktown City Council v Sharp (2000) 10 BPR 18,107;[2000] NSWSC 339
- Coles Group Property Developments Limited v Stankovic[2016] NSWSC 852
- Cowell v Rosehill Racecourse Company Limited (1937) 56 CLR 605;[1937] HCA 17
- Graham H Roberts Pty Ltd v Maurbeth Investments Pty Ltd [1974] 1 NSWLR 93
- Lincoln Hunt Australia Pty Ltd v Willesee(1986) 4 NSWLR 457
- Makucha v Preslands Finance[2005] NSWSC 41
- Merl v Merl[2022] NSWSC 434
- New South Wales v Koumdjiev (2005) 63 NSWLR 353;[2005] NSWCA 247
- Pitt v Baxter (2007) 34 WAR 102;[2007] WASCA 104
- Romani v State of New South Wales[2023] NSWSC 49
- Smethurst v Commissioner of Police (2020) 272 CLR 177;[2020] HCA 14
- Uber BV v Howarth (2019) 94 NSWLR 636;[2017] NSWSC 54
- White City Tennis Club Ltd v John Alexander’s Clubs Pty Ltd (2007) 13 BPR 24,835;[2007] NSWSC 1210
Legislation cited
- Civil Procedure Act 2005 (NSW), § 98
- Uniform Civil Procedure Rules 2005 (NSW), § 42.1
Judgment
Introduction
- [1]
Ms Harsha Janak Patel seeks orders principally to restrain the defendants from engaging in any conduct that prevents her from being able to complete the construction of her house. Originally, a Summons was filed on 5 February 2025 seeking that order only. When this matter came on for hearing on 27 August 2025, Harsha sought leave to file an Amended Summons seeking further orders restraining the defendants from entering onto what is identified in the Amended Summons as the “Wentworthville Property” (about which more will be said later) and requiring the defendants to remove goods that were left on the “Wentworthville Property”. The Court granted leave, and the Amended Summons was duly filed later that afternoon and supplied to my Associate.
- [2]
As the key individuals in this matter share the same surname, I will refer to them by their first names, without intending any disrespect or overfamiliarity.
- [3]
The first defendant is Dev Constructions (NSW) Pty Ltd (Dev Constructions). Harsha and Dev Constructions entered into a contract on 29 December 2020 (the Building Contract) pursuant to which Dev Constructions agreed to construct a new house. The second defendant is Kamleshkumar Kantilal Patel, who is the sole director and shareholder of Dev Constructions. Dev Constructions and Kamleshkumar filed submitting appearances, save as to costs, on 5 May 2025.
- [4]
Harsha and Ms Nidhiben Kamlesh Patel are the registered proprietors of the land in folio identifier X/XXXXX, known as X XXXX Street, Wentworthville, New South Wales (the Wentworthville Property). Harsha and Nidhiben hold the Wentworthville Property as joint tenants. Kamleshkumar is the father of Nidhiben.
- [5]
On 29 December 2021, Parramatta City Council (the Council) granted its consent for a two staged development to occur on the Wentworthville Property. The work to be undertaken in stage 1 of the development was “[d]emolition of existing structures, and construction of a two-storey detached dual occupancy and basement with Torrens title subdivision from one lot into two lots”. Stage 2 was the “[c]onstruction of a secondary dwelling on resultant Lot 2b”. The practical consequence of the Council’s development consent was that it had approved:
- (1)
the subdivision of the Wentworthville Property into two lots, with one of the lots to be known as “Lot 2b”; and
- (2)
the construction of two new houses, with each of the eventually subdivided lots to have one house on it.
- (1)
- [6]
It was not clarified in submissions, nor was it apparent on the evidence, where on the land comprising the Wentworthville Property each house actually was. That is, I am not sure whose house was supposed to go onto the land that, following subdivision, was to be known as “Lot 2b” (using the Council’s descriptor).
- [7]
Both Nidhiben and Harsha had entered into separate building contracts with Dev Constructions for the construction of House One and House Two respectively. Harsha’s understanding is that around the same time as she entered into the Building Contract, Nidhiben also entered into a contract with Dev Constructions pursuant to which Dev Constructions agreed to construct a new dwelling, being House One, at the Wentworthville Property (Nidhiben’s Building Contract).
- [8]
Only Harsha’s contract with Dev Constructions was in evidence in these proceedings. Nidhben’s Building Contract was not in evidence. Harsha subsequently terminated the Building Contract. Since the termination of the Building Contract, it seems that the construction of House Two has stalled.
- [9]
The concerning conduct in these proceedings is the alleged failure by Dev Constructions to remove building materials placed by it on the part of the Wentworthville Property where House Two is supposed to be, blocking Harsha’s access to that house, after she had terminated the Building Contract. Harsha also alleges that Kamleshkumar has entered onto the part of the Wentworthville Property where House Two is supposed to be without her consent since the Building Contract was terminated.
- [10]
The final hearing of this matter took place on 27 August 2025. Mr S Greenwood, the solicitor on the record for Harsha, appeared for Harsha. As already mentioned, Dev Constructions and Kamleshkumar had filed a submitting appearance and so did not appear on 27 August 2025.
- [11]
By reason of the submitting appearance, all of the evidence which was relied upon by Harsha in this proceeding is unchallenged evidence. Of course, this does not mean that I am bound to accept that evidence. However, in this case, there is nothing contained within the affidavits read and relied upon by Harsha which I consider to be inherently improbable, or which would otherwise suggest that I should doubt the credibility and reliability of those who have given evidence. I record expressly that I have accepted the evidence as contained in the affidavits read in this proceeding, the contents of which are recounted in some detail in the section titled “The facts”.
- [12]
Mr Greenwood had provided written submissions dated 26 August 2025 in advance of the hearing upon which he relied and made oral submissions.
- [13]
The evidence as at the date of the hearing was relatively confined. Harsha read and relied on a single affidavit which was sworn by her on 31 January 2025, and tendered the exhibit to that affidavit. Annexed to the PWS were some further documents which were also tendered as evidence in the proceedings.
- [14]
However, during the course of the hearing, I raised my concerns with Mr Greenwood as to the fact that Nidhiben, the co-owner of the Wentworthville Property, was not a party to these proceedings, and canvassed with Mr Greenwood the potential significance of that being the case. I raised my specific concerns as to it not being clear on the evidence read and tendered at the hearing as to whether Nidhiben was aware of these proceedings. Separately, I was also initially concerned with the adequacy of the submissions as to whether the defendants’ conduct constituted trespass, which is a key issue in this case given the basis for the injunction sought against the defendants was to restrain a trespass.
- [15]
In response to these concerns, Mr Greenwood said he would provide supplementary written submissions on Harsha’s behalf addressing the elements of the tort of trespass and as to Nidhiben’s awareness of these proceedings, including what procedural steps need to be taken. Mr Greenwood also said that he would obtain from his client a further affidavit specifically about what awareness Nidhiben has of these proceedings. Accordingly, at the conclusion of the hearing, the Court directed Harsha to provide the aforementioned supplementary written submissions and further affidavit by 4:00pm on Friday, 29 August 2025. The date by which the further submissions and affidavit were due was not one unilaterally decided by the Court; it was decided following a brief discussion with Mr Greenwood as to when he would be able to provide the extra material that was necessary in the circumstances.
- [16]
On 29 August 2025, Mr Greenwood emailed my Chambers to seek a short extension for his client to provide the supplementary submissions and affidavit as ordered, in light of a delay he had experienced in another matter which had meant he had been unable to prepare those documents. On 1 September 2025, I caused my Associate to email Mr Greenwood to indicate I was content to grant Mr Greenwood a short extension to 4:00pm that afternoon (ie, the afternoon of 1 September).
- [17]
Harsha provided by email to my Chambers a further affidavit sworn by Janak Patel (Harsha’s husband) on 2 September 2025 at 6:31pm (the affidavit had been filed online shortly before then), two working days after they were due in accordance with the Court’s direction and more than 24 hours after the extended time that was given to provide those documents. However, I did not receive on 2 September 2025 any supplementary written submissions as directed. In the email by which Mr Greenwood provided to my Chambers Janak’s affidavit, he wrote “[t]he plaintiff’s supplementary submissions will be sent to you shortly”.
- [18]
By 4 September 2025, I had still not received any supplementary written submissions as directed. That afternoon, I caused my Associate to email Mr Greenwood to follow up as to when I could expect the supplementary written submissions. My Chambers did not receive a response to this email.
- [19]
By 20 November 2025, my Chambers still had not received any supplementary written submissions. On that day, I instructed my Associate to list the matter for judgment on 24 November 2025 at 4:00pm, and to email the parties’ legal representatives to inform them that I was ready to deliver judgment.
- [20]
I consider it appropriate to explain why I was ready to deliver judgment in these proceedings despite not having received Harsha’s supplementary submissions. My reasons are as follows. Harsha has otherwise had the opportunity to make written and oral submissions in chief. I considered that Mr Greenwood had more than an ample opportunity to provide the supplementary submissions which he sought to provide on Harsha’s behalf. I note that at least the extra evidence as to Nidhiben’s awareness of the proceedings had been provided to my Chambers and I took it into account in the preparation of this judgment. In those circumstances, including where my Chambers had not received any communication which provided some explanation for the failure to provide the further submissions I ordered, I considered it appropriate to proceed without having those further submissions, lest the resolution of this matter be delayed any further.
- [21]
However, after my Associate’s email of 20 November 2025, my Chambers received an email from Mr Greenwood at 3:54pm on 21 November 2025. In that email, he attached the supplementary written submissions I had ordered. Those submissions are dated 21 November 2025 and were filed electronically at 3:47pm. While Mr Greenwood did apologise for the late provision of the submissions, the explanation he provided for their lateness was that he “(embarrassingly) overlooked” providing those submissions.
- [22]
Despite the lateness of their receipt, I have still read and considered those supplementary submissions. Nothing of substance has been added by those submissions with respect to both what I have named “issue 1” below, that is whether the defendants’ actions constitute a trespass, and the bulk of what I have named “issue 2” below, that is whether an injunction should be granted in this case.
- [23]
What is submitted in [13]-[16] and [20]-[21] of the supplementary written submissions concern Harsha’s ability to obtain relief without having joined her co-owner. Those paragraphs do not add to the oral submissions made on this issue on 27 August 2025. My consideration of this particular issue, from [115]-[121] already addresses the argument made at [16] of the supplementary submissions, and what is said at [20]-[21] of those submissions. What is submitted at [13]-[15] of the supplementary submissions merely establishes a plaintiff with exclusive possession of land may commence an action for trespass to land against a defendant. But that does not take anywhere consideration of whether Harsha can obtain the relief she seeks without Nidhiben – on the evidence before me, clearly, Harsha and Nidhiben currently have exclusive possession of the Wentworthville Property. The real issue is whether the fact Harsha and Nidhiben are joint tenants has any impact on Harsha’s ability to seek relief on her own.
- [24]
The balance of this judgment was prepared without having those supplementary written submissions to hand. For the reasons just explained, no further reference to those supplementary submissions is necessary. Accordingly, there are no further references to those submissions below.
- [25]
For the reasons set out below, I have determined that it would be appropriate to grant an injunction restraining the defendants from entering or occupying the Wentworthville Property and from engaging in or continuing to engage in conduct that prevents and/or which is intended to have the effect of preventing Harsha or any contractors engaged by her from completing the building works comprising the construction of House Two on the Wentworthville Property. Additionally, I have determined that it would be appropriate to make an order that the defendants are to remove any building materials which remain on the Wentworthville Property within 21 days.
- [26]
However, I have not granted an injunction in terms of the relief sought within the Amended Summons nor made any final orders yet because of concerns as to the precise terms of the injunction, which I shall detail later.
The facts
- [27]
As already mentioned, on 29 December 2020, Harsha and Dev Constructions entered into the Building Contract. The cover page to the Building Contract reveals it is some sort of standard form contract. The contract is headed “NSW Residential Building Contract for New Dwellings”. The cover page also indicates this is “edition 7” of the contract. The copyright attribution and apparent author of the contract is “HIA”.
- [28]
Both on the cover page and in item 2 of sch 1 to the Building Contract (titled “Particulars of Contract”) the “owner” of the land the subject of the contract is identified only as “Mrs Harsha Janak Patel” (ie, the plaintiff in these proceedings). There is no reference to Nidhiben in the Building Contract. The “builder” identified on the cover page and in item 3 of sch 1 is Dev Constructions.
- [29]
The “site address” on the cover page is “House 2, X XXXX St Wentworthville NSW 2145”. By contrast, the “site”, as defined in item 5 of sch 1 contains just the folio identifier and street address of the Wentworthville Property. There is no reference to “House 2” in item 5 of sch 1.
- [30]
The total contract price identified in item 4 of sch 1 was $685,000 including GST. Item 6 of sch 1 defines the “building period” by which the “building works” must reach the stage of practical completion – this period is defined as 52 weeks after the building period commences (subject to any extensions).
- [31]
Schedule 4 is titled “Description of Work”. It contains a direction to the drafter to insert a brief description of the “building works”. Schedule 4 of the Building Contract includes the following (capitalisation as per original):
- [32]
Relevantly, cll 13 and 26 of the Building Contract are as follows (italicisation in original):
- [33]
As mentioned earlier in this judgment, the evidence establishes that Nidhiben also had a contract with Dev Constructions which I am referring to as Nidhiben’s Building Contract.
- [34]
While Nidhiben’s Building Contract itself was not in evidence, there was in evidence a letter dated 3 October 2024 sent by a solicitor acting for Nidhiben to Dev Constructions giving notice Nidhiben intended to terminate Nidhiben’s Building Contract. That letter mentions some information about that contract. That letter establishes that Nidhiben’s Building Contract was entered into on 29 December 2020 (the same day as when Harsha entered into the Building Contract) – the letter expressly says as much. Given Harsha’s own evidence that she understands Nidhiben entered into a contract with Dev Constructions around the same time she did, I am satisfied Nidhiben’s Building Contract was entered into on the same date.
- [35]
The 3 October 2024 letter also gives rise to a strong suggestion that Nidhiben’s Building Contract and the Building Contract may have been in similar terms. The letter refers to the termination being “pursuant to Clause 27.1 of the contract”. The letter also says that Nidhiben instructs Dev Constructions to remedy its breaches, adding that “pursuant to Clause 27.3(b) we [Nidhiben’s solicitors] are instructed to provide you [Dev Constructions] with 10 working days to remedy the breach” (emphasis added). Clause 27.1 of the Building Contract is also the clause under which Harsha could terminate the contract for a substantial breach by Dev Constructions (a course she eventually did take, as recounted below). Similarly, cl 27.3(b) of the Building Contract is what empowers a party (such as Harsha) to terminate the Building Contract if a substantial breach notified to the breaching party is not remedied within 10 working days.
- [36]
Without more, I probably cannot be satisfied on the balance of probabilities that the Building Contract and Nidhiben’s Building Contract were in identical or materially similar terms. However, given what is set out in the 3 October 2024 letter and the correspondence between the right of termination Nidhiben’s solicitors say she had with the termination right Harsha had under the Building Contract, I can at least conclude that the rights of termination they had under their respective contracts with Dev Constructions were similar.
- [37]
By a letter dated 18 January 2021, Dev Constructions proposed a variation to the Building Contract to allow for additional works, which was to increase the price by $194,530 inclusive of GST, which would bring the total price payable by Harsha to $879,530. On 21 January 2021, Harsha agreed to the proposed variation by signing the letter from Dev Constructions indicating her agreement.
- [38]
As already mentioned, on 29 December 2021, the Council granted development approval for the demolition of existing structures on the Wentworthville Property, the construction of a “two storey detached dual occupancy and basement”, the subdivision of the Wentworthville Property from one to two lots and the construction of a secondary dwelling on the second lot.
- [39]
On or about 29 April 2022, Dev Constructions commenced performing the building works under the Building Contract.
- [40]
In or about March 2023, Dev Constructions suspended carrying out the building works at the Wentworthville Property. On 22 July 2023, Harsha and Dev Constructions agreed to vary the Building Contract in accordance with a document titled “Construction Agreement Amended Conditions”. The terms of that variation do not appear to be material to this dispute. Nonetheless, I note that the parties agreed here that House Two was to be completed by 6 March 2024, and the keys and certificates were to be handed over to Harsha by the same date. Following the agreed variations, Dev Constructions recommenced performing the building works at the Wentworthville Property.
- [41]
On 21 February 2024, Dev Constructions sent two letters to Harsha. In one letter, Dev Constructions indicates the contract price under the Building Contract was to be varied upwards a further $103,787.50 on account of the gross floor area exceeding that which was estimated under the original contract, with the total contract price including GST now to be $983,317.50. The other letter of the same date communicated Dev Constructions’ intent to suspend working on House Two by reason of Harsha’s failure to make progress payments totalling $439,765.
- [42]
In response to these letters, on 26 February 2024, Harsha sent an email (which is signed off by her and her husband, Janak) to Dev Constructions raising various issues. In this email, Harsha and Janak rejected Dev Constructions’ attempt to increase the contract price.
- [43]
On 4 March 2024, Dev Constructions sent an email in reply to Harsha’s email dated 26 February 2024. In that email, Dev Constructions claimed, amongst other things, that Harsha had breached numerous clauses of the Building Contract.
- [44]
On 26 March 2024, Harsha sent an email (again signed off by both her and her husband) in reply to the email of Dev Constructions of 4 March 2025. In that email, Harsha (and Janak) responded to the allegations she had breached the Building Contract, attached invoices totalling $439,765, indicated that payment had been released to Dev Constructions, and directed Dev Constructions to recommence building works pursuant to cl 25.3 of the Building Contract.
- [45]
Shortly after this email, on or around 8 April 2024, Janak says he had a conversation with Nidhiben about what he described as the slow progress of House Two. He says that he told Nidhiben that if Kamleshkumar did not complete the building works on time and in accordance with the previously agreed price, he and Harsha would have no choice but to get a lawyer involved with a view to terminating the Building Contract. Janak’s evidence is that Nidhiben said she spoke to her father about the lack of progress but that he (that is, Kamleshkumar) was not listening to her.
- [46]
Janak says he then had a further conversation with Nidhiben on or around 18 April 2024. He says he asked Nidhiben to talk to her father to resolve the issues in dispute between Harsha and Dev Constructions, but Nidhiben instead kept telling him that he would need to get a lawyer involved as her father was not listening to her.
- [47]
Sometime in late April 2024, Janak says he had a conversation with his business partner and Nidhiben’s husband, Darshan Patel about the matters the subject of this dispute. Janak’s evidence is that he explained to Darshan that he and Harsha would be appointing a lawyer to terminate the Building Contract, and encouraged Darshan to get Nidhiben to speak to the lawyer appointed by Harsha and Janak with a view to Nidhiben terminating her own building contract with Dev Constructions. Janak says Darshan’s response to this was to say that his wife would probably not want to speak with Janak and Harsha’s lawyer as she did not want to get into a legal dispute with her father.
- [48]
On 24 April 2024, Harsha issued a Notice of Dispute to Dev Constructions pursuant to cl 35 of the Building Contract (the Notice of Dispute). In the Notice of Dispute, amongst other matters raised, Harsha:
- (1)
disputed that Dev Constructions was entitled to increase the contract price under the Building Contract;
- (2)
disputed that Dev Constructions was entitled to suspend the carrying out of the building works;
- (3)
disputed that she had breached the Building Contract as Dev Constructions had alleged; and
- (4)
proposed a meeting with Dev Constructions within 10 working days to attempt to resolve the dispute or agree on methods of resolving the dispute.
- (1)
- [49]
Dev Constructions did not respond to the Notice of Dispute and otherwise refused to meet with Harsha to resolve the dispute.
- [50]
On 4 May 2024, Harsha received tax invoices from Dev Constructions in respect of the construction of House Two, one of which included a contract price adjustment in the amount of $88,219.35.
- [51]
On or about 5 May 2024, Janak says he had another conversation with Nidhiben. Janak says that in this conversation, Nidhiben suggested he and Harsha take legal action against her father (Kamleshkumar) and Dev Constructions as she thought that was the only way the issues in dispute could be sorted.
- [52]
On 8 May 2024, Harsha sent an email to Dev Constructions disputing the tax invoice that included the price adjustment of $88,219.35 including GST.
- [53]
At some point in this timeline, a complaint was lodged with Building Commission NSW. When that occurred is not revealed in the evidence, though there is evidence the Wentworthville Property was inspected on 10 May 2024. That complaint culminated in a rectification order under s 48E of the Home Building Act 1989 (NSW) being issued to Dev Constructions on 12 June 2024 by an inspector appointed under s 48D of that Act (the Rectification Order). The Rectification Order required Dev Constructions to complete all aspects of the agreed upon work and achieve practical completion of the work at the Wentworthville Property by 26 July 2024.
- [54]
By 29 July 2024, according to Harsha, Dev Constructions had failed to comply with the Rectification Order. Accordingly, Harsha issued a Notice of Intention to End Building Contract dated 29 July 2024 pursuant to cl 27 of the Building Contract (the Notice of Intention). In the Notice of Intention, Harsha notified Dev Constructions that she would terminate the Building Contract unless the Rectification Order was complied with within 10 working days (ie, that practical completion be achieved within that time), with the failure to comply with the Rectification Order said to be a substantial breach under the Building Contract giving rise to a right to terminate under cl 27.
- [55]
It appears that Harsha made a further complaint about Dev Constructions to Building Commission NSW, now saying that the Rectification Order had not been complied with. As with the initial complaint, it is not clear when this further complaint was made. What is in evidence is another report of the inspector who had issued the Rectification Order, dated 5 August 2024. In that report, the inspector concluded that the Rectification Order had not been complied with. I note that in the further report of 5 August 2024, the inspector reproduced comments made by Dev Constructions (specifically, Kamleshkumar, in his capacity as director) in relation to the complaints made, as sought by the inspector. The inspector summarised Dev Constructions’ representations as follows (the actual representations made by Dev Constructions to the inspector were not in evidence):
- [56]
On 8 August 2024, the inspector from Building Commission NSW sent an email to Harsha confirming that Dev Constructions had not complied with the Rectification Order.
- [57]
By about 21 August 2024, it appeared that Dev Constructions had still not complied with the Rectification Order. On 21 August 2024, Harsha issued to Dev Constructions a Notice of Termination in respect of the Building Contract (the Notice of Termination). After setting out some background, which largely reflects the chronology already stated above, in the Notice of Termination, Harsha stated:
- [58]
Harsha says that “a few days” after the Notice of Termination was provided to Dev Constructions, she noticed that someone had accessed the Wentworthville Property without her consent and had moved Dev Constructions’ materials from House One to inside her fence such that access to House Two had been blocked. Harsha says she suspected Kamleshkumar was the one who moved the materials.
- [59]
On 4 September 2024, Harsha and her husband Janak, sent the following email to Kamleshkumar (copying in what appears to be the email addresses of Nidhiben and Darshan):
- [60]
On 5 September 2024, Janak and Harsha provided access to a contractor Harsha had engaged to install CCTV cameras on House Two. Soon after, on the same day, Harsha says Kamleshkumar entered House Two (Harsha says he did so “forcefully”) despite Janak and Harsha reminding him that his access to House Two had been revoked and that he was therefore trespassing. Harsha says that Kamleshkumar proceeded to “threaten” the contractor who was present to install the CCTV cameras, including saying to the contractor that he would “go to jail” if he did not stop working immediately. The CCTV contractor left House Two without installing CCTV cameras.
- [61]
Someone appears to have called to the police during this verbal altercation alleged by Harsha, as she says that the police arrived by the time the contractor had left. The police first questioned Harsha and Janak about what had happened, and then, it appeared to Harsha, they spoke to Kamleshkumar. Harsha’s evidence is that she observed Kamleshkumar being warned by the police that he would be charged with trespassing if he disobeyed their direction to refrain from entering House Two.
- [62]
Around 10 September 2024, Harsha arranged for Mr Gavin Swain of Tyrrells Building Advisory to inspect the building site of House Two and to identify any incomplete or defective building work. Mr Swain prepared a “technical report” dated 18 September 2024 in which various items of work were described as incomplete or likely requiring “corrective treatments”.
- [63]
On 19 September 2024, Birch Partners Lawyers, the solicitors for Dev Constructions, sent a letter to Harsha, signed off by Mr Michael Birch. In that letter, Mr Birch said that Dev Constructions considered that the Notice of Termination was “unlawful and constituted a repudiation” of the Building Contract by Harsha, and that Dev Constructions had elected to accept Harsha’s alleged repudiation and terminate the Building Contract itself. The letter stated (emphasis added):
- [64]
By 20 September 2024, Dev Constructions had still not removed its materials such that they were still blocking access to House Two. In the circumstances of all that had happened, Harsha had arranged for a crane to arrive on that day to move these materials to make space for her and her future contractors to access House Two and deliver building materials.
- [65]
Not long after the crane arrived on 20 September 2024, Harsha says that Kamleshkumar arrived and parked his motor vehicle directly behind the crane, preventing it from being able to do any work. Harsha then says that Kamleshkumar entered House Two and started “threatening” the crane operator and his dogman, including by saying they would “go to jail” if they did not stop working. Once again, the police were called. Once they arrived, the police spoke to Harsha, Janak and Kamleshkumar. Harsha says she observed Kamleshkumar claim to the police that he was entitled to exclusive possession of the property and that his materials were being damaged by Harsha. Harsha said to the police that this was untrue. The police, crane operator and his dogman left the building site, leaving Dev Constructions’ materials in place.
- [66]
Also on 20 September 2024, Janak says he had a conversation with Darshan, although it is not clear if this was before or after the incident with the cranes recounted in the preceding paragraph. During this conversation, Janak says he told Darshan that Harsha had terminated the Building Contract and had been advised to commence proceedings in this Court to stop Kamleshkumar and Dev Constructions from entering the Wentworthville Property and disturbing Harsha and Janak’s contractors and new builder. Janak said he also told Darshan that if Nidhiben terminated Nidhiben’s Building Contract, legal proceedings may be unnecessary. Janak’s evidence is that in his presence Darshan then told Nidhiben, by a phone call to her, of Harsha’s intention to commence proceedings in this Court.
- [67]
Janak’s evidence is that on the next day, 21 September 2024, he and Harsha met Nidhiben in her apartment to further discuss matters. Janak says Nidhiben suggested that Harsha and Janak do what they contemplated, that is, commence proceedings in this Court, as Nidhiben’s father was still not listening to her. Janak says that Nidhiben also said that she was intending to terminate Nidhiben’s Building Contract but did not intend to join Harsha and Janak in commencing legal proceedings against her father.
- [68]
Harsha says that on 2 October 2024, Kamleshkumar again entered House Two without the consent of Harsha. She says she has CCTV footage of this occurring, though that CCTV footage was not in evidence.
- [69]
I interrupt this chronology to note that after Harsha sent the Notice of Termination and parallel to her attempts to remove Dev Constructions’ materials from blocking her access to House Two, she began trying to find another builder to complete House Two. Boutique Builders Pty Ltd (Boutique Builders) was chosen. On 21 September 2024, Boutique Builders sent to Harsha and her husband an email including a proposed building contract, a tender proposal (including a list of inclusions), and an invoice for the payment of an initial deposit. Harsha says she did not sign the contract given the incidents that she says had occurred on 5 and 20 September 2024, which had caused her to be concerned that Kamleshkumar might prevent or hinder her from giving Boutique Builders access to House Two as she was contractually required to do.
- [70]
On or about 3 October 2024, Darshan forwarded to Janak a copy of a notice of intention to terminate Nidhiben’s Building Contract which Nidhiben’s solicitors had sent to Dev Constructions. That letter was the letter referred to in [34] above.
- [71]
Again interrupting the chronology, I observe that precisely when Nidhiben’s Building Contract was finally terminated is not exactly clear from the evidence, though there is no doubt the contract has been terminated. The 3 October 2024 letter sent on Nidhiben’s behalf that was in evidence gave notice of her intention to terminate the contract. Any subsequent notice of termination was not in evidence. Janak’s evidence, which itself is derived from a conversation he had in or around July 2025 with an unnamed business partner of his (who is also a business partner of Darshan’s), only suggests Nidhiben terminated the contract in “late” 2024. The only other evidence is an email from Mr Birch, of Birch Partners Lawyers, to Mr Greenwood, in which he says that “[his] client understands that Nidhiben Patel considers the contract between [his] client and herself was terminated on or about 14 October 2024”. It will be observed that 14 October 2024 is not 10 working days after 3 October 2024, but 11 calendar days after. This minor distinction is of little moment. Based on this evidence, I am satisfied that by mid-October, Nidhiben’s Building Contract had also been terminated by Nidhiben.
- [72]
On 4 October 2024, Greenwood Lawyers, the solicitors for Harsha, sent a letter in response to the letter from Birch Partners Lawyers dated 19 September 2024, signed by Mr Greenwood. In that letter, amongst numerous other matters, a written undertaking was sought from Dev Constructions and Kamleshkumar that they would:
- [73]
No direct response to this letter was received and no undertaking by Dev Constructions or Kamleshkumar has been given. Mr Birch did send an email to Mr Greenwood on 8 October 2024 indicating he would need further time to seek instructions concerning a response to Mr Greenwood’s letter. Mr Greenwood sent follow-up emails on 30 October 2024 and 22 November 2024 (following an attempt to call Mr Birch) seeking a response. In this last email, Mr Greenwood indicated he had instructions to commence proceedings seeking injunctive relief against Dev Constructions and Kamleshkumar. These proceedings were commenced just over 2 months after this last email.
Legal principles
- [74]
As the Wentworthville Property is subject to a joint tenancy, and there are two separate building contracts pursuant to which Dev Constructions and Kamleshkumar were initially allowed onto the land, it is useful to briefly set out the law which governs the manner in which co-owners of land may singly grant and revoke licences. Significantly however, it will be noted that much of this law is in relation to tenants in common, rather than joint tenants.
- [75]
In New South Wales v Koumdjiev (2005) 63 NSWLR 353; [2005] NSWCA 247 (Koumdjiev), Hodgson JA (with whom Beazley JA and Hislop J agreed) considered the law where one tenant in common of land purports to grant permission to another person to enter the land, and another tenant in common purports to refuse or revoke that permission. His Honour remarked at [31] that there is “little authority or textbook discussion” with respect to the issue just mentioned.
- [76]
In that decision, his Honour distilled the relevant principles as follows (emphasis added):
- [77]
It follows that one tenant in common may grant a licence over his or her interest, which may grant a third party the right to enter and occupy the land: see White City Tennis Club Ltd v John Alexander’s Clubs Pty Ltd (2007) 13 BPR 24,835; [2007] NSWSC 1210 at [24]-[26] (Brereton J) (reversed on other grounds).
- [78]
To similar effect, Wheeler JA (with whom Buss JA and Miller AJA agreed) in Pitt v Baxter (2007) 34 WAR 102; [2007] WASCA 104 concluded that a single tenant in common could not unilaterally revoke an implied licence for the police to enter onto the common property of a unit block to conduct inquiries which had been granted by all of the tenants in common (see at [16], and [18]-[22] of that decision). I note that her Honour did not expressly approve of what is said in Koumdjiev. Rather, her Honour distinguished that case from the facts before her Honour and held that in any event, the conditions for a tenant in common to be able to unilaterally revoke a licence granted by other tenants in common had not been satisfied in that case.
- [79]
In Butt’s Land Law (Law Book Co, 7th ed, 2017) at 264, Professor Brendan Edgeworth provided the following distillation of the principles (emphasis added, footnotes omitted):
- [80]
It will be observed that, strictly speaking, Hodgson JA in Koumdjiev only dealt with how tenants in common could grant and revoke licences. His Honour did not address whether joint tenants could unilaterally grant or revoke licences. The learned author of Butt’s Land Law in the passage quoted above seems to assimilate the position of joint tenants and the position of tenants in common when explaining what Hodgson JA said in Koumdjiev. For reasons which are explained later (see [94], [100]-[101]), the facts of this case make it unnecessary to consider in any detail whether the right of joint tenants to unilaterally grant or revoke licences is any different to that of tenants in common.
- [81]
Having regard to the authorities cited above, it would appear that co-owners have the power to terminate a licence granted by another co-owner (assuming, without it being necessary to decide, that joint tenants and tenants in common are to be treated the same) if the licence:
- (1)
goes beyond what is reasonable and incidental to the grantor’s possession and enjoyment of the property as a co-owner; and
- (2)
interferes with the other co-owners’ rights to possess and enjoy the property.
- (1)
- [82]
In Romani v State of New South Wales [2023] NSWSC 49 (Romani), Wright J at [38]-[42] set out what is needed to establish the tort of trespass has been committed (emphasis added):
- [83]
In Makucha v Preslands Finance [2005] NSWSC 41 (Makucha), Campbell J at [13]-[14] addressed whether the presence of chattels on land could constitute a trespass:
- [84]
A court of equity has a well-established jurisdiction to grant injunctions to restrain legal wrongs: Uber BV v Howarth (2019) 94 NSWLR 636; [2017] NSWSC 54 (Uber) at [194] (Slattery J). An injunction in aid of a legal right or interest is granted in this Court’s auxiliary jurisdiction in equity: Smethurst v Commissioner of Police (2020) 272 CLR 177; [2020] HCA 14 (Smethurst) at [48] (Kiefel CJ, Bell and Keane JJ).
- [85]
This Court may grant an injunction in its auxiliary jurisdiction, whether interlocutory or final, if the plaintiff has a legal right that the injunction will protect: Smethurst at [77] (Kiefel CJ, Bell and Keane JJ).
- [86]
In Uber, at [194]-[199], Slattery J set out the following four requirements that must be satisfied for the Court to grant an injunction in its auxiliary jurisdiction:
- (1)
the plaintiff possesses a legal right;
- (2)
that right is arguably of a proprietary nature;
- (3)
that right is threatened or has already been infringed so as to show a threat of future infringement; and
- (4)
damages would not be an adequate remedy.
- (1)
- [87]
The onus rests on the plaintiff to show that an injunction is, in the circumstances an appropriate form of relief. This requires the plaintiff to persuade the court that an award of damages would not be an adequate remedy or that irreparable harm would be suffered if the injunction were refused: Graham H Roberts Pty Ltd v Maurbeth Investments Pty Ltd [1974] 1 NSWLR 93 (Graham H Roberts) at 107 (Helsham J); Blacktown City Council v Sharp (2000) 10 BPR 18,107; [2000] NSWSC 339 (Blacktown City Council) at [14] (Young J, in the context of an interlocutory injunction); Lincoln Hunt Australia Pty Ltd v Willesee (1986) 4 NSWLR 457 (Lincoln Hunt Australia) at 464 (Young J, in the context of an interlocutory injunction).
- [88]
In Coles Group Property Developments Limited v Stankovic [2016] NSWSC 852 (Coles Group Property), Sackar J at [54]-[60] summarises the principles relevant to a permanent injunction to restrain an act of trespass (emphasis in original):
- [89]
In Bendal Pty Ltd v Mirvac Project Pty Ltd (1991) 23 NSWLR 464 (Bendal), Bryson J at 468-9 addressed the availability of an injunction to a freehold owner of land:
Issues for determination
- [90]
Given the procedural and factual background set out above, together with the applicable legal principles, the real issues before the Court for determination are:
- (1)
Do the defendants have a valid licence to enter onto and occupy the Wentworthville Property?
- (2)
Should the Court exercise its discretion to grant an injunction in the terms sought by Harsha?
- (1)
Issue 1: Lawful authority to enter and occupy the Wentworthville Property
- [91]
Harsha accepted that she had granted Dev Constructions exclusive possession of the site to carry out the subject building works, namely the construction of House Two under the Building Contract. However, she submitted that the Building Contract was validly terminated by way of the Notice of Termination, on 21 August 2024. She submitted that even if the Building Contract was wrongfully repudiated, the defendants still had no right of access to the construction site of House Two under the Building Contract after 21 August 2024. In support of these submissions, Harsha cited Graham H Roberts and Cowell v Rosehill Racecourse Company Limited (1937) 56 CLR 605; [1937] HCA 17 (Cowell).
- [92]
Harsha recognised that this matter was complicated somewhat by the fact that the defendants were also authorised to enter and occupy the Wentworthville Property (or part of that property) under Nidhiben’s Building Contract. As has been previously mentioned, Nidhiben’s Building Contract was not in evidence. However, Harsha conceded in her oral submissions that given “there was clearly a joint endeavour to build two houses”, the Court should proceed on the basis that a valid licence had been granted by both co-owners to the defendants (TR P8 L24-39).
- [93]
But even if the defendants were granted a valid licence initially, as part of the two contracts to construct House One and House Two on the Wentworthville Property, Harsha submits that the defendants no longer had no entitlement to access any part of the Wentworthville Property (including that part of the property comprising House Two). Harsha’s principal submission appears to be that the right of the defendants to access the Wentworthville Property was revoked as early as when Harsha terminated the building contract on 21 August 2024. Harsha says that because of the joint tenancy between herself and Nidhiben, a valid licence to access the Wentworthville Property required the concurrence of all joint tenants, and so Harsha withdrawing her concurrence (by terminating the Building Contract) made invalid any separate licence granted by Nidhiben to the defendants under Nidhiben’s Building Contract. In support of this, Harsha cited Koumdjiev at [33] and Merl v Merl [2022] NSWSC 434 (Merl) at [38] (Campbell J).
- [94]
In any event, Harsha submitted that given the evidence establishes Nidhiben’s Building Contract was terminated in October 2024, the question of whether one joint tenant could revoke a licence granted by another joint tenant had fallen away. Accordingly, at least as of October 2024, Harsha submitted there is no valid licence on foot.
- [95]
For the reasons which follow, I have concluded that there is no valid licence which the defendants currently have vis-à-vis the Wentworthville Property.
- [96]
I start from the premise that Dev Constructions (and, by extension, Kamleshkumar) did initially have a valid licence to be on the Wentworthville Property for the purpose of carrying out the construction of House One and House Two, pursuant to both the Building Contract and Nidhiben’s Building Contract. So much was conceded by Harsha. Has that licence been revoked?
- [97]
The evidence establishes that Harsha had terminated the Building Contract by the Notice of Termination on 21 August 2024. Accordingly, any licence the defendants had to enter onto the Wentworthville Property under the Building Contract had been revoked. Whether that termination was wrongful, as the solicitors for the defendants claimed in the correspondence, which was in evidence, does not change that conclusion. If this had been a case where the Wentworthville Property had been solely owned by Harsha, then it seems clear that once Harsha had terminated the Building Contract, whether or not she had done so wrongly (and I record expressly that I am not expressing any opinion on the merits of the defendants’ assertion to this effect), the defendants would no longer have any right to come onto the land and would be considered trespassers if they did so: Cowell at 621 (Latham CJ); 630-631 (Dixon J).
- [98]
If Nidhiben’s Building Contract had still been on foot, or if this was an action which required me to characterise the state of affairs between August 2024 (when Harsha terminated her contract with Dev Constructions) and October 2024 (when Nidhiben terminated her contract with Dev Constructions), there would have been an interesting legal question as to the validity of any licence granted to the defendants by one joint tenant only. Harsha’s submissions proceeded on the footing that the fact of a joint tenancy meant both joint tenants had to concur in any licence granted to anyone else to enter the Wentworthville Property. Even just examining the passages of authority cited by Harsha, it is not immediately clear the footing on which she proceeded is correct.
- [99]
What Campbell J said in Merl at [38] and what Hodgson JA said in Koumdjiev at [33] was about the ability of joint tenants to grant leases. Whether, in the case of a joint tenancy, a licence requires the concurrence of all joint tenants would seem to be a different question. In Koumdjiev itself, a case about tenants in common, Hodgson JA reached different conclusions about the ability of one tenant in common to terminate a lease granted by another tenant in common (at [33], his Honour said the non-lessor tenant in common could not revoke the lease) and the ability of one tenant in common to revoke a licence granted by another (at [40]-[41] and following, his Honour suggested a tenant in common could revoke a licence granted by another, but only in the circumstances specified by his Honour). The learned author of Butt’s Land Law in the passage cited above at [79] suggests, contrary to Harsha’s submissions, that a joint tenant could solely grant a licence.
- [100]
However, I do not need to express any conclusions on these interesting issues. This is because I am satisfied on the evidence that Nidhiben has also terminated Nidhiben’s Building Contract: see [71] above. As I have said, while the precise date of termination is not clear, the evidence establishes that the contract is both at an end, and that it ended in mid-October 2024.
- [101]
It follows that since the time of Nidhiben’s Building Contract coming to an end, Dev Constructions (and Kamleshkumar, seeing as he does not appear to have had any right to enter the Wentworthville Property separate from any licence granted to Dev Constructions) has had no licence authorising it (and him) to enter onto the Wentworthville Property.
- [102]
Absent any contractual licence to enter the Wentworthville Property, any intrusion onto the land after October 2024 was unauthorised and constituted trespass: Romani at [38]-[42] (Wright J). The only conduct capable of constituting trespass that has occurred since October 2024 was the defendants leaving their building materials on the Wentworthville Property. As at the time of the hearing, the goods described as remaining on the Wentworthville Property included brick packs, a metal roof, scaffolding materials and wall frames.
- [103]
I note that in an email sent to Harsha’s solicitors by the defendants’ solicitors on 9 May 2025, the defendants appear to challenge the claim that they have dumped any materials on site. In that email, Mr Birch, on the defendants’ instructions, says “[his] client disputes that it has dumped any materials on site. Any materials that remain on site are building materials proposed to be utilised in the construction.” The sworn evidence from Harsha and Janak, in their respective affidavits, is that materials of Dev Constructions are blocking their access to House Two. I have no rational reason to doubt that evidence. Additionally, there is also an email from Boutique Builders sent on 7 April 2025 which refers to materials “from the previous builder” on the building site of House Two “which has left no space to enter to the side”. That email, from what is effectively a disinterested party in these proceedings, appears to confirm it is Dev Constructions’ materials which are blocking access to House Two, given there is no other “previous builder” whose materials it could be.
- [104]
The assertion that any materials that remain on site are “proposed to be utilised in the construction” also appears to be an entirely untenable one given both the Building Contract and Nidhiben’s Building Contract had been terminated by 9 May 2025. What is said in the portion of the 9 May 2025 email quoted above seems to itself acknowledge that there are in fact materials of Dev Constructions still on site, though whether or not this particular email should be read that way does not matter given the other evidence in this matter.
- [105]
In sum, there are materials of Dev Constructions that remain on the Wentworthville Property. Clearly, Harsha and Nidhiben have not authorised those materials to remain on the land. It follows that the conduct of the defendants in leaving their building materials on the Wentworthville Property constitutes a continuing trespass: Coles Group Property at [54]-[60] (Sackar J); Makucha at [13]-[14] (Campbell J).
- [106]
I am therefore satisfied on the evidence before the Court that, at least from October 2024 onwards, the defendants were not lawfully authorised to enter or occupy the Wentworthville Property and, accordingly, the leaving of building materials, which still remain on the site, constitute a continuing trespass.
Issue 2: Injunction
- [107]
Harsha submitted that landowners are prima facie entitled to an injunction to restrain trespasses on his or her land whether or not the trespass harms him or her. Accordingly, upon her establishing the invasion of a common law right and that there are grounds for believing there is likely to be repetition of the wrong, then, in the absence of special circumstances, she is entitled to an injunction against such repetition: Bendal at 468–469. Further, Harsha contended that damages are an inadequate remedy in this circumstance because any damages are likely to be merely nominal.
- [108]
Harsha was required to prove that an injunction is, in the circumstances, an appropriate form of relief, including by demonstrating that an award of damages would not be an adequate remedy or that irreparable harm would be suffered if the injunction were refused: Graham H Roberts; Blacktown City Council at [14]; Lincoln Hunt Australia. It is accepted, as put by Harsha, that equity will not ordinarily regard common law damages as an adequate remedy for an injury to land: Coles Group Property at [54]-[60] (Sackar J); Lord at [166]-[170] (Slattery J).
- [109]
I am of the view that it is appropriate to grant a permanent injunction restraining the defendants from entering upon or remaining on the Wentworthville Property or leaving any property on the land. The authorities make it clear that the auxiliary jurisdiction of a court of equity can be used to restrain trespasses to land: Lord at [168]. Mapping the facts of this case onto the preconditions for an injunction identified by Slattery J, Harsha as a co-owner of land, no doubt has a legal right of a proprietary nature. Given injunctions to prevent trespasses to land are well accepted, clearly courts of equity accept that an injunction of the kind sought in this case would be protecting a legal right of a proprietary nature.
- [110]
In this case, I also accept that right has already been infringed and is being infringed by Dev Constructions leaving its materials on the Wentworthville Property. For the reasons already set out above, I am satisfied that is a continuing trespass.
- [111]
Finally, I accept that damages will not be an adequate remedy in this case. Damages would not adequately compensate Harsha for the main harm she is suffering and would suffer from the continuation of the current trespassory conduct, namely the inability to complete the construction of House Two.
- [112]
I am also satisfied that any injunction should also capture Kamleshkumar in his own right. On one view, he may be adequately captured by any injunction restraining Dev Constructions given he appears to be the only natural person through whom it acts. But in any event, I am satisfied that his conduct demonstrates that he at least poses a threat to the rights of the co-owners of the Wentworthville Property. That conclusion is reached considering the cumulative effect of the following events evidenced by Harsha and Janak:
- (1)
the events of 5 September 2024, where Kamleshkumar entered onto the construction site of House Two and threatened the contractor hired by Harsha and Janak;
- (2)
the events of 20 September 2024, where Kamleshkumar prevented a crane from working on House Two, threatened a crane operator and his dogman (which happened after the police had, according to Harsha, warned him on 5 September 2024 to refrain from entering House Two);
- (3)
the apparent unauthorised entry on 2 October 2024 of Kamleshkumar onto the construction site of House Two; and
- (4)
Kamleshkumar’s refusal to provide the undertaking sought by Harsha that he (and Dev Constructions) refrain from engaging in conduct that is intended to prevent Harsha from completing the construction of House Two.
- (1)
- [113]
I also accept it would be appropriate to order the materials that have been left by Dev Constructions to be removed, so as to leave no room for doubt that this specific trespassory conduct ought be remedied.
- [114]
In my view, any order made should allow for a period of three weeks to enable the defendant to remove any remaining building material from the Wentworthville Property. In stating this, I note that Harsha’s Amended Summons sought an order allowing a period of 14 days.
- [115]
Harsha submitted that it was of no concern that the other co-owner of the Wentworthville Property was not a party to these proceedings, relying on the decision of Merl. At [40] of that decision, Campbell J discussed the effect of a co-owner not being party to the proceedings in somewhat similar circumstances:
- [116]
Harsha brought to my attention the orders of the Court in Merl as potentially available in this case. Justice Campbell made the following orders in Merl (see at [42] of Merl):
- [117]
Harsha also suggested that there be some regime of orders whereby Harsha notifies Nidhiben of any relief granted by the Court and Nidhiben is then given a period of time to potentially apply to vary or discharge any substantive orders made by the Court. Harsha also suggested that the operation of any injunction could then be stayed in the meantime. (See TR P23 L45-P24 L26.)
- [118]
Harsha submitted that Nidhiben is aware of the proceedings and has not joined the proceedings because she does not wish to get involved. Based on the supplementary evidence provided by Harsha, namely Janak’s affidavit, I am satisfied that Nidhiben is aware of these proceedings. I note that Janak’s evidence appears to suggest Nidhiben was not just aware, but also supportive of the proceedings being commenced, even though she herself did not wish to join as a plaintiff. I accept that this is an understandable position given the proceedings involve Nidhiben’s father.
- [119]
However, even though I am satisfied that Nidhiben is aware of these proceedings and has consciously chosen not to join them, I am not satisfied that Harsha is able to obtain, on her own, an injunction in relation to the Wentworthville Property. I have been pointed to no authority that would suggest a joint tenant is able to seek an injunction in relation to co-owned property without also joining their co-owner/s. I have also not been given any argument of principle that would lead me to conclude that is a permissible path to take.
- [120]
Even in Merl, it is not clear Campbell J accepted the plaintiff’s argument which is summarised in [40] of that decision, namely, that the mere fact co-owners have unity of possession mean any one co-owner can assert their right of possession independently of the others. His Honour still ordered the other joint tenant in that case be joined as a defendant. I am not necessarily suggesting that it is impermissible for one co-owner to come to court seeking relief in relation to a co-owned property without the other co-owner/s. If the plaintiff’s argument in Merl at [40] is correct, then that line of thinking does seem applicable to a case like the present, where an injunction is sought to prevent a trespass. Such an injunction would similarly seem to be part of vindicating a co-owner’s right to possession, such that a co-owner could be permitted to vindicate that right without needing to join their fellow co-owner/s. However, in the absence of any reasoned argument on the point, I am not inclined to proceed in that way, especially given the one case Harsha relied on did ultimately have both joint tenants joined as parties.
- [121]
I accept it is probably not necessary for Nidhiben to be joined to bind her in the way it was necessary to do so in Merl. In that decision, the co-owners had together purported to grant the defendant a lease. This grant was in issue and, accordingly, Campbell J thought it desirable for the co-owner to be joined as a defendant so as to ensure he was bound by the decision made. Here, no such issue arises. Nonetheless, for the reasons explained in the previous paragraph, my opinion is that Nidhiben should be given a formal opportunity to be heard. Given Nidhiben appears to be well aware of these proceedings, I propose only giving her a relatively short time to be heard.
- [122]
It is at this point appropriate to set out in full the substantive relief claimed by Harsha in her Amended Summons (underlining and bolding as per original):
- [123]
There are two problems with the form of the relief sought which I consider prevent me from being able to make the orders she seeks, even if I do accept, as I have, that Harsha is entitled to some sort of relief against the defendants.
- [124]
First, prayers 1-3 make reference to “the Wentworthville Property”. On the one hand, this could be a reference to the property at X XXXX Street, Wentworthville as a whole. Alternatively, given the way it is defined in prayer 1 and used in prayer 3, it could just be a reference to “House 2” at X XXXX Street, Wentworthville. Particularly for the purposes of prayer 2, whether the injunction prevents the defendants from just entering “House 2”, or the whole of the land at X XXXX Street, Wentworthville, should be clarified.
- [125]
Second, what is “House 2” at X XXXX Street, Wentworthville is not clear on the face of the order. It will be recalled that, at present, the subdivision of the land has not taken place. “House 2” (or “House Two” as I have called it in this judgment) is simply the informal designation given to the house on the land that is to be Harsha’s. The evidence also does not establish how someone is to identify “House 2” so as to comply with the terms of any injunction. Accordingly, I consider it appropriate that Harsha provide an alternative form of orders which clarifies where “House 2” sits on the land at X XXXX Street, Wentworthville.
- [126]
To enable her to address these concerns, I will order Harsha to provide the Court with proposed short minutes of order to give effect to this judgment.
Conclusion
- [127]
In relation to issue 1, I am satisfied on the evidence before the Court that the defendants are now not lawfully authorised to enter or occupy the Wentworthville Property and, accordingly, the leaving of building materials which still remain on the site constitutes a continuing trespass.
- [128]
As to issue 2, I am of the view that it is appropriate to grant a permanent injunction restraining the defendants from entering upon or remaining on the Wentworthville Property or leaving any property on the land. However, before making any final orders, I will give Harsha the opportunity to formulate orders to address the concerns I have outlined in relation to the form of relief sought. I will give Nidhiben the opportunity to be heard. With respect to the order requiring the defendants to remove building materials from House Two at the Wentworthville Property, I reiterate that I will allow the defendants three weeks, rather than the two weeks Harsha sought to give them.
Costs
- [129]
The plaintiff has been successful and has sought an order for her costs.
- [130]
Whilst costs are in the discretion of the Court under s 98 of the Civil Procedure Act 2005 (NSW), r 42.1 of the Uniform Civil Procedure Rules 2005 (NSW) provides that subject to Part 42 of the Uniform Civil Procedure Rules, if the court makes any order as to costs, the court is to order that the costs follow the event unless it appears to the court that some other order should be made.
- [131]
I am of the view there is no reason for the Court to otherwise order in the circumstances of the present case and I propose to make an order that the costs should follow the event and thus order the defendants to pay the plaintiff’s costs. However, given the submitting appearance of the defendants was “save as to costs”, it is appropriate they be given an opportunity to be heard as to any costs order.
- [132]
I will briefly explain why I am currently of the view the defendants should pay the plaintiff’s costs, despite their submitting appearance. I am of this view because it was the conduct of the defendants which has ultimately required Harsha to commence proceedings to obtain injunctive relief. As I have found, it is the defendants who have left their building materials on the Wentworthville Property. Especially after Nidhiben’s Building Contract was terminated in October 2024, those building materials have remained there without practical or legal justification. The evidence also shows that Harsha attempted to resolve the dispute without resorting to this Court, including by seeking an undertaking from the defendants which was not given. At least according to the evidence, Harsha (or rather, her solicitors) did not receive a response to the correspondence sent on her behalf on 4 October 2024. She should be compensated for the defendants’ conduct which has required her to incur legal expenses in coming to this Court.
- [133]
For the reasons set out above, I make the following orders:
- (1)
The plaintiff is to email to the Chambers of Bennett J proposed Short Minutes of Order to give effect to this judgment by 4:00pm on 1 December 2025.
- (2)
By 4:00pm on 1 December 2025, the plaintiff is to serve on Nidhiben Kamlesh Patel, the co-owner of the land in folio identifier X/XXXXXX, known as X XXXX Street, Wentworthville, New South Wales:
- (3)
By 4:00pm on 8 December 2025, Nidhiben Kamlesh Patel is to notify the Chambers of Bennett J by email if she wishes to be heard.
- (4)
Subject to order 5, the defendants are to pay the plaintiff's costs.
- (5)
Within 7 days of the publication of this judgment, the parties may make an application by email to my Associate to vary order 4. Further orders will be made for the filing and serving of submissions by the parties in relation to any such application.
- (6)
Any further issue as to costs will be determined on the papers.
- (1)