← All cases

[2021] NSWSC 581

Pheonix Builders Pty Ltd v Deca Australia Pty Ltd

Refuse interim relief staying enforcement of adjudicator’s determination.

Catchwords

BUILDING AND CONSTRUCTION – interim relief –applicant claims no construction contract – similar contention made to adjudicator, but withdrawn – adjudicator determined had jurisdiction – jurisdictional challenge now revived in this Court – respondent alleged to be insolvent – interim relief refused.

Cases cited

  • Brodyn Pty Ltd v Davenport (2004) 61 NSWLR 421;[2004] NSWCA 394
  • Hakea Holdings Pty Limited v Denham Constructions Pty Ltd[2016] NSWSC 1120
  • IWD No 2 Pty Ltd v Level Orange Pty Ltd[2012] NSWSC 1439
  • Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd (2018) 264 CLR 1;[2018] HCA 4
  • Samsung Electronics Co Ltd v Apple Inc (2011) 217 FCR 238;[2011] FCAFC 156
  • Shell Refining (Australia) Pty Ltd v AJ Mayr Engineering Pty Ltd[2006] NSWSC 94

Legislation cited

  • Building and Construction Industry Security of Payment Act 1999 (NSW) § 24, 25

Judgment

  1. [1]

    HER HONOUR: This is an application by the plaintiff, Pheonix Builders Pty Ltd, for an interim order restraining the first defendant, Deca Australia Pty Ltd, from:

  2. [2]

    In support of the application for interim relief, the plaintiff relied on an affidavit by its solicitor, David Jury, and accompanying documents in relation to the adjudication.

Facts

  1. [3]

    In July 2019, Deca submitted a quotation to the plaintiff and, in November 2019, a further quotation. The plaintiff says that, in January 2020, Deca's quotation was accepted, leading to a construction contract to undertake demolition and excavation works in Blakehurst. The contract price was $696,000 plus GST. The plaintiff advanced the same contention to the adjudicator, which was accepted: Determination at [24]. Assuming that the construction contract came into existence as pleaded, the relevant version of the Act is the current version.

  2. [4]

    As pleaded in the Technology and Construction List Statement, supported by Mr Jury's affidavit on information and belief, the plaintiff contends that, on 25 September 2020, a site meeting took place between representatives of the plaintiff and Deca, at which it was agreed (the Agreement):

  3. [5]

    On 19 October 2020, pursuant to the Agreement, the plaintiff paid 65% of the contract price to Deca and, on 20 October 2020, an email was sent by Deca to the plaintiff which is said to evidence the new construction contract. The email, entitled “removal of imported fill”, is equivocal in this regard.

  4. [6]

    On 17 March 2021, Deca issued a payment claim, which included invoices issued after the site meeting of 25 September 2020. The plaintiff contends this was not a valid payment claim by reason of the accord and satisfaction arising from the Agreement and the plaintiff’s payment. By reason of the accord and satisfaction, the construction contract no longer existed, nor Deca’s entitlement to make the progress claim.

  5. [7]

    On 31 March 2021, the plaintiff provided a payment schedule which, in part at least, set out the Agreement as follows: (emphasis added)

  6. [8]

    On 16 April 2021 Deca filed an adjudication application. On 26 April 2021, the plaintiff provided an adjudication response, which included:

  7. [9]

    As part of the adjudication response, the plaintiff also submitted a statutory declaration by the plaintiff’s site foreman, who described the meeting on 25 September 2020 in the following terms:

  8. [10]

    On 11 May 2021, the Determination was issued. The adjudicator noted at [30] and [33]: (footnotes omitted)

  9. [11]

    On 13 May 2021, the plaintiff's solicitor requested details of Deca's financial position, noting that an application to wind up Deca had been filed in this Court by another creditor, and various defaults in payment were noted on a company search. On 14 May 2021, Deca's solicitor advised that Deca had discharged most of the debts referred to and entered into agreements in relation to other outstanding amounts, including with the petitioning creditor.

  10. [12]

    On 17 May 2021, the plaintiff commenced these proceedings ex parte seeking orders for short service. It was not drawn to the attention of the Court, either in Mr Jury’s affidavit or the plaintiff's written submissions, that the jurisdictional challenge now sought to be advanced had been put before the adjudicator, albeit in a somewhat different form, and withdrawn. Mr Jury deposed, on information and belief, that the plaintiff raised the Agreement in its payment schedule, including challenges to the validity of Deca’s payment claim and jurisdictional challenges, and the Determination “did not property consider the nature and effect of the Agreement”. Unless the plaintiff brought the additional fact that the plaintiff withdrew its challenge to the adjudicator’s jurisdiction to the Court’s attention, the Court may well have proceeded on an incorrect understanding of the facts.

Interlocutory injunction

  1. [13]

    The question is whether the interim relief should be granted.

  2. [14]

    This Court can only quash an adjudicator’s determination for jurisdictional error: Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd (2018) 264 CLR 1; [2018] HCA 4 at [35]. An essential prerequisite to the exercise of an adjudicator’s powers, and thus jurisdiction, is the existence of a construction contract: Brodyn Pty Ltd v Davenport (2004) 61 NSWLR 421; [2004] NSWCA 394 at [53]-[54] per Hodgson JA; IWD No 2 Pty Ltd v Level Orange Pty Ltd [2012] NSWSC 1439 at [9]-[11] per Stevenson J. Having regard to the Technology and Construction List Statement and Mr Jury’s affidavit, there is a serious issue to be tried as to whether there was a construction contract at the time when the progress claim was issued. If the plaintiff succeeds in establishing the Agreement in these proceedings, then the Determination may be quashed for jurisdictional error.

  3. [15]

    In considering whether to grant an interlocutory injunction, the Court is entitled to take into account the apparent strength of the parties' substantive cases, as noted by Dowsett, Foster and Yates JJ in Samsung Electronics Co Ltd v Apple Inc (2011) 217 FCR 238; [2011] FCAFC 156 at [67]:

  4. [16]

    Here, the strength of the plaintiff’s case is undermined by the manner in which that issue was put to the adjudicator – being inconsistent with the manner in which it is now put – and then withdrawn. It may undermine the operation of the Act – which is to ensure prompt payment to contractors through clear, quick procedures – for a party to an adjudication to challenge jurisdiction, withdraw the challenge, only to contend in this Court that the adjudicator has made a jurisdictional error by reason of the same issue abandoned before the adjudicator.

  5. [17]

    In addition, according to the Technology and Construction List Statement, the plaintiff has a claim against Deca for breach of contract, including abandonment of the site and seawall collapse in excess of $250,000. The suggested counterclaim is put in wide and general terms.

  6. [18]

    As to the balance of convenience, the relevant principles are explained in Hakea Holdings Pty Limited v Denham Constructions Pty Ltd [2016] NSWSC 1120 by Ball J at [4]-[6], and particularly at [6]:

  7. [19]

    Here the plaintiff points to the fact that Deca appears to have been experiencing cash flow difficulties. In particular, a default payment was notified in June 2020 by the petitioning creditor in the winding-up application to which I have already referred, in the amount of some $53,000. In November 2020, another creditor notified default payments totalling some $100,000. In February 2021, default judgment was entered against Deca in the amount of some $9,000. A further default judgment was entered against Deca in April 2021 in the amount of some $15,000. Thus, it is said that, if the moneys are paid to Deca – as they will have to be in the event that the interim relief is not granted – then the moneys may not be recoverable.

  8. [20]

    Accepting that, I note that the policy underlying the Act is that contractors such as Deca should have their bills paid promptly as cash flow is the life blood of the industry: Shell Refining (Australia) Pty Ltd v AJ Mayr Engineering Pty Ltd [2006] NSWSC 94 at [14] per Bergin J. The moneys which Deca is prima facie entitled to be paid, being some $240,000, is in a sum which seems likely to be able to address the cash flow problems identified by the plaintiff.

  9. [21]

    Having regard to the issue to be tried, the strength of the plaintiff’s claim and the balance of convenience, as set out at [14] to [20], I decline to make the orders sought.

Unofficial copy. Source: NSW Caselaw. Refer to the official version for authoritative text.