[2024] NSWCA 162
EnerMech Pty Ltd v Acciona Infrastructure Projects Australia Pty Ltd
(1) Allow the appeal from the judgment in the Equity Division given on 14 December 2023. (2) Set aside orders 1, 2 and 5 entered on 15 December 2023 and in their place order that: (a) the amended summons dated 24 October 2023 be dismissed; (b) the plaintiffs pay the costs of the first defendant of the summons; (c) the first defendant pay the plaintiffs’ costs of the cross-summons. (3) Order that the first to third respondents pay the appellant an amount of $10,160,109.77, together with interest at 9.1% per annum from 7 July 2023 to the date of payment. (4) Order that the first to third respondents pay the appellant’s costs in this Court.
Catchwords
BUILDING AND CONSTRUCTION – payment claim – validity – claim for payment due under construction contract – whether claim must be “for construction work” – purpose of claim to recover an amount obtained by respondents through recourse to bank guarantees provided by claimant – defence asserted in payment schedule – whether issue to be determined by adjudicator or Court
Cases cited
- Brodyn Pty Ltd t/as Time Cost and Quality v Davenport & Anor (2004) 61 NSWLR 421;[2004] NSWCA 394
- BSA Advanced Property Solutions (Fire) Pty Ltd v Ventia Australia Pty Ltd (2022) 108 NSWLR 350;[2022] NSWCA 82
- Ceerose Pty Ltd v A-Civil Aust Pty Ltd (2023) 112 NSWLR 225;[2023] NSWCA 215
- Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd (2010) 78 NSWLR 393;[2010] NSWCA 190
- Coordinated Construction Co Pty Ltd v J M Hargreaves (NSW) Pty Ltd (2005) 63 NSWLR 385;[2005] NSWCA 228
- Grocon (Belgrave St) Developer Pty Ltd v Construction Profile Pty Ltd[2020] NSWSC 409
- Illawarra Retirement Trust v Denham Constructions Pty Ltd[2015] NSWSC 823
- Nepean Engineering Pty Ltd v Total Process Services Pty Ltd (in liq) (2005) 64 NSWLR 462;[2005] NSWCA 409
- Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd (2018) 264 CLR 1;[2018] HCA 4
- Quasar Constructions NSW Pty Ltd v Demtech Pty Ltd (2004) 20 BCL 276;[2004] NSWSC 116
- Sopov v Kane Constructions Pty Ltd (No 2) (2009) 24 VR 510;[2009] VSCA 141
- Southern Han Breakfast Point Pty Ltd (in liq) v Lewence Construction Pty Ltd (2016) 260 CLR 340;[2016] HCA 52
- Witron Australia Pty Ltd v Turnkey Innovative Engineering Pty Ltd[2023] NSWCA 305
Legislation cited
- Building and Construction Industry Security of Payment Act 1999 (NSW), § 3, 4, 7, 8, 9, 10, 12, 13, 14, 15, 16, 20, 22, 25, 27, 34
- Supreme Court Act 1970 (NSW), § 69
Judgment
- [1]
MEAGHER JA: I agree with the reasons of Basten AJA and the orders he proposes.
- [2]
BASTEN AJA: By an agreement dated 3 June 2020 the appellant, EnerMech Pty Ltd entered into a Major Works Subcontract (subcontract) with the first–third respondents (who were engaged in a joint venture known as “ASBJV”) to undertake electrical works on the M4-M5 Link main tunnel which was part of the WestConnex project. The subcontract had a completion date of 31 May 2022, which appears to have been extended. On 8 June 2023, the appellant served a progress payment claim No 29 (PC 29) on the respondents. The amount of the claim was a little over $10 million.
- [3]
The respondents served a payment schedule indicating that, with minor variations, no amount was owing or payable. In accordance with the provisions of the Building and Construction Industry Security of Payment Act 1999 (NSW) (Security of Payment Act) on 7 July 2023 the appellant submitted PC 29 for adjudication. On 14 July 2023, the respondents provided an adjudication response and on 25 July 2023 an adjudicator gave a determination in favour of the appellant. The determination was reissued on 3 August 2023, after correction was sought on a slip rule application.
- [4]
A day before the amendment to the determination, the respondents had commenced proceedings in the Equity Division, Technology and Construction List, seeking orders quashing the determination and permanently restraining the appellant (the first defendant below) from requesting an adjudication certificate or otherwise taking steps to enforce the determination. The nature of the dispute was succinctly identified in the respondents’ (plaintiffs below) amended Technology and Construction List statement in the following terms:
- [5]
On 14 December 2023 the primary judge, Stevenson J, delivered judgment upholding the respondents’ challenge to the validity of the determination. [1] By orders made on 15 December 2023, the adjudication determination was quashed and the appellant was permanently restrained in the terms referred to above.
- [6]
On 13 February 2024, the appellant filed a notice of appeal seeking to have the judgment set aside. The appellant alleged error on the part of the primary judge in holding:
- (1)
that a “payment claim” must be a claim for payment “for construction work”, within the meaning of the Security of Payment Act, and
- (2)
PC 29 was not a claim “for construction work”.
- (1)
- [7]
The premise underlying the challenge to the first finding was twofold: first, that the Security of Payment Act did not prescribe, as an essential condition of the validity of a payment claim, that it be “for construction work”; secondly, if there were such a condition, it was a matter to be determined by the adjudicator and not by the Court. (The adjudicator had in fact determined the issue favourably to the appellant, and there was no challenge to her determination of that issue.) The challenge to the second finding was that, if there were a jurisdictional condition to be determined by the Court, the primary judge wrongly held it was not satisfied in this case.
- [8]
For the reasons explained below, whatever the meaning of the phrase “for construction work”, it was not an essential element of a progress payment claim that it be so characterised. While a payment claim must assert an entitlement to payment for work done under a construction contract, fulfillment of that entitlement is a matter to be determined by the adjudicator, subject to limited rights of review for jurisdictional error. Accordingly, the appeal should be allowed and the decision of the primary judge set aside. As compliance with such a condition is not a matter for the Court, this Court should not consider whether PC 29 complied. If the Court did so and came to a different answer to that given by the adjudicator, it would in effect be reviewing the decision of the adjudicator for non-jurisdictional error of law, an exercise which is not permitted under the Security of Payment Act [2] and, in any event, was not sought.
Essential requirements of a payment claim
- [9]
The point of departure in considering the essential preconditions to a valid payment claim under the Security of Payment Act must be the terms of the Act itself. However, in the 24 years since the Act commenced (on 26 March 2000) there has been considerable judicial analysis, both of the specific issue as to the nature of a payment claim, and as to principles governing the construction of the Security of Payment Act. It will be necessary to address the cases in due course. However, it is convenient to note at the outset that for some 20 years, since Brodyn Pty Ltd t/as Time Cost and Quality v Davenport, [3] this Court has been restrained in implying essential preconditions to the engagement of statutory powers, which would invite judicial intervention. Thus, in BSA Advanced Property Solutions (Fire) Pty Ltd v Ventia Australia Pty Ltd [4] a five-judge bench observed:
- [10]
Part 1 of the Security of Payment Act (Preliminary) contains a statement of the object of the Act (s 3), together with definitions. Part 2 confers a right to progress payments in the following terms:
- [11]
Section 8 was amended in 2002 and again in 2018, but at all times relevant for present purposes (other than with respect to earlier cases) it was in the current form.
- [12]
Section 9 states that the “amount of a progress payment to which a person is entitled in respect of a construction contract is to be … the amount calculated in accordance with the terms of the contract”. If the contract does not so provide, the amount is to be calculated “on the basis of the value of construction work carried out … by the person … under the contract”: s 9(b). Section 10 elaborates on the process of valuation.
- [13]
Part 3 is titled “Procedure for recovering progress payments”. Part 3, Div 1 is titled “Payment claims and payment schedules” and commences with s 13, which is central to the issues in the present case, and relevantly reads as follows: [10]
- [14]
Counsel for the respondents sought to identify three elements in s 13(1). [11] The first was the identification of the claimant as a person referred to in s 8, namely a person who has undertaken to carry out construction work under a construction contract. There was no dispute that the appellant satisfied that requirement. The second element was a requirement that the claimant be a person “who is or claims to be entitled to a progress payment”. Where the person has served what appears to be a claim for payment under a construction contract, the respondents submitted there was a separate issue as to whether what was claimed amounted to a “progress payment”, as opposed to a claim for damages for breach of a contract or for an account of payments made. That was an important element in the respondents’ case because they sought to characterise the claim as one for an account of payments made between the parties. The third element identified what the claimant is entitled to do, namely serve a payment claim on the person who is or who may be liable to make the payment.
- [15]
The first element requires reference to the definition of “construction contract”; the second element turns on the meaning of “progress payment”. The respective definitions in s 4 are in the following terms:
- [16]
Two points are immediately apparent from these provisions: first, the Security of Payment Act does not purport to limit the amount or nature of a payment to which a party is entitled under a construction contract; secondly, there is a risk in compartmentalising payments according to their character, regardless of the terms of the contract, so as to contend that some fall within the concept of a progress payment for which a claim may be made, and some do not. It will be necessary to return to this point in considering the terms of the subcontract.
- [17]
This approach is consistent with the following reasoning in Southern Han Breakfast Point Pty Ltd (in liq) v Lewence Construction Pty Ltd: [12]
- [18]
In its original form, s 8 provided for payment claims to be made “on and from each reference date”. The term “reference date” has been removed, but the concept remains, namely that a payment claim may be served “on and from the last day of the named month in which the construction work was first carried out”, unless the contract expressly permitted a claim to be served from an earlier date. [13]
- [19]
Section 13(2) provides, in obligatory terms, three matters which a payment claim must contain. However, the respondents accepted that the use of the imperative did not necessarily indicate an essential precondition to validity, and did not do so in s 13(2). [14] These are factors of which an adjudicator will need to be satisfied in the case of an adjudication. (In most cases, these matters will not be in issue.)
- [20]
Section 13(3) identifies two amounts which may be included in a payment claim, the first being a payment under s 27(2A). Section 27(1) permits a claimant to suspend work under a construction contract (after giving notice to do so for non-payment of an amount payable which has fallen due and not been paid); s 27(2A) permits a claim for loss or expenses incurred as a result of suspending work. The second claimable amount is one withheld under the terms of the construction contract by the respondent, which the claimant says is due for release. For example, the subcontract provided for the appellant to provide security (cl 5.2), for release of the security (cl 5.8), and further that where the contractor has wrongfully had recourse to the security, the subcontractor’s sole remedy is “repayment of the security” (cl 5.5(b), (c)). There was no claim for release of the security, nor for repayment of the security, in the present case, but the fact that a payment claim may be made for such an amount is relevant in determining what it may mean to require that a payment claim must be “for construction work”.
- [21]
In form, PC 29 set out all amounts which had been claimed under previous payment claims, together with a record of payments made, for the purpose of identifying the amount payable. That formulation was not challenged, and may be justified either by reference to s 13 (5) and (6) read together, or by reference to the terms of the subcontract.
- [22]
Section 14 provides that a party served with a payment claim may in response provide a payment schedule indicating the amount of the payment (if any) proposed to be made. Failure to provide a payment schedule within the prescribed time (10 business days after service of the payment claim) will render a respondent liable to pay the claimed amount.
- [23]
Section 14 recognises that non-payment may be justified under a construction contract where a respondent is permitted to withhold payment. In that case, the payment schedule is required to indicate “the respondent’s reasons for withholding payment”: s 14(3).
- [24]
The Security of Payment Act then provides for two circumstances in which a respondent may default. The first is where no payment schedule is provided pursuant to s 14 (see s 15); the other is where a payment schedule indicates that while part of the payment claim is payable another part is not payable, but the admitted part is not paid (s 16). In each case, the claimant is permitted to recover the unpaid amount as a debt in a court of competent jurisdiction. There are limits on the defences which a respondent can raise in such proceedings, as provided, for example, in s 15(4):
- [25]
Part 3, Div 2, provides for the adjudication of disputes which arise where a payment claim has been made and a payment schedule provided indicating a scheduled amount less than the amount claimed.
- [26]
The deadlines are extremely tight: for serving a payment schedule (10 business days), for making an adjudication application (in the usual case, 10 business days after the payment schedule is received), for lodging an adjudication response to the adjudication application (generally, 5 business days after receiving the application) and for determination of the application (10 business days after notifying the parties of acceptance of the application, unless further time is agreed). Importantly, the respondent “cannot include in the adjudication response any reasons for withholding payment unless those reasons have already been included in the payment schedule”: s 20(2B).
The “construction contract”
- [27]
Before identifying the steps taken in the present case by reference to the payment claim and payment schedule, it is convenient to identify relevant aspects of the subcontract, pursuant to which the construction work was undertaken. In doing so, the factual matters indicating the relevance of the clause will be noted. (In the subcontract, the appellant was the “Subcontractor” and the respondents the “Contractor”.) Clauses 5 and 42 were of central importance.
- [28]
Clause 5 of the subcontract required that the appellant provide security within 10 days after the date of the subcontract or the commencement of any work under the subcontract: cll 5.2, 5.4. The amount of the security was fixed at 10% of the subcontract sum. [15] Clause 5.5 read as follows:
- [29]
Clause 5.8(b) provided that upon the subcontractor complying with cl 42.12, the contractor must release security pursuant to cl 42.8(d).
- [30]
Clause 42 (Payment) commenced with cl 42.1 providing for “Payment Claims, Payment Schedules and Payment”. The entitlement to payment under a payment claim was said to be subject to provision of security, obtaining insurance and payment of secondary subcontractors and employees. In other respects, cl 42.1 mirrored the Security of Payment Act. However, given the reliance placed on it by counsel for the appellant it is convenient to set out the following provisions (emphasis added):
- [31]
PC 29 did not purport to be a “Final Payment Claim”, however, it may be noted that provision for such a claim was made in cl 42.7:
- [32]
The term “Claim” was defined in cl 2.1 in the following terms:
- [33]
Clause 42.8 dealt with a “Final Payment Schedule”; subject to a number of preconditions, par (d) stated that “within 45 days after the Due Date for Payment, the Contractor must release to the Subcontractor any security then held by the Contractor”. The term “Due Date for Payment” was defined in cl 2.1 to mean “thirty (30) Business Days after a claim for payment is made by the Subcontractor”.
- [34]
Further, cl 42.8(e) provided that, subject to specified conditions, and exceptions for fraud and mistake,
- [35]
The significance of cll 42.7 and 42.8 is that they bring within the scheme of the Security of Payment Act the resolution (subject to specified exceptions and conditions) of all entitlements to payment under the subcontract. Clause 42.1(d) required that a payment claim include the value of work carried to that time, “together with all amounts then due to the Subcontractor arising out of or in connection with this Subcontract or for any alleged breach thereof”. Clause 42.1(g) required that a payment schedule must allow for all payments made or due, both by and to each party under the subcontract: that requirement was consistent with the description of payments in accordance with a payment schedule being “on account only” and not determining “whether the amount so paid is the amount properly due and payable under this Subcontract”. Similarly the requirement that a payment schedule include “amounts paid under this Subcontract and amounts otherwise due from the Contractor to the Subcontractor … including but not limited to any amount due or to be credited under any other provisions of this Subcontract”, may be broad enough to include amounts withheld by way of security, where the amount has been appropriated or “converted” to the use of the contractor.
- [36]
The contractual basis for the recourse by the respondents to the security was partly cl 5.5 (set out at [28] above) and partly cl 42.11 which read as follows:
The payment claim (PC 29)
- [37]
PC 29 issued on 8 June 2023 included a variation claim in an amount of $15,372.67 and a claim for payment of an amount of $69,906.26 resulting from a slip rule amendment to a previous adjudication determination, together with interest thereon in an amount of $3,240.49. Otherwise, the payment claim listed in a series of schedules all the works which had been undertaken under the contract, and variations to it. However, the column of each schedule headed “value claimed this period” was left blank. As explained in a coversheet, the current claims totalled $106,941,444.09 and the previous determinations totalled $106,922,872.42, being a difference of $18,611.67. That last amount constituted the variation, together with interest, referred to above. The claim further identified the amount certified and paid to date as $97,622,808.76. That was said to leave a net amount outstanding of $9,318,675.33, which, together with GST, gave a total amount of $10,250,542.86, from which the amount paid under the slip rule was deducted, leaving a net balance to be paid by the respondents of $10,180,582.60.
- [38]
Schedule 5 to PC 29, headed “Previous Payments”, included the amounts paid under each of the previous payment claims, from which a deduction of $9,230,157.40 was made, leaving the figure outstanding as the total paid to date – $97,622,808.76 – which accorded with the figure in the cover/summary sheet.
- [39]
On 23 June 2023, the respondents sent a covering letter, attaching a payment schedule, alleging that the payment claim was not valid because “it is not a claim for a progress payment (that is, a claim for payment for construction work (or related goods and services) in respect of which it is said that the claimant has an entitlement to payment under the Act)”. The letter continued:
- [40]
With respect to the slip rule amendment and interest (totalling $73,146.72), the respondents did not deny that the amount was unpaid, but stated that it was not properly included within a payment claim and should have been sought in accordance with “the enforcement provisions of the Act”. Nevertheless, the amount was paid on 23 June 2023 (that is, the date of the payment schedule). (In fact, the amount of the amendment was not included in PC 29, but the interest was so included.) With respect to the amount covered by the variation (identified as $15,371.18), the respondents stated in the letter accompanying the payment schedule that there had been no compliance with the requirements of the subcontract in relation to variations, but continued:
- [41]
That left the amount of $9,230,157.40 to be addressed. The respondents noted that there was no explanation of the deduction from payments made but inferred that, as the amount was that to which they had had recourse under the bank guarantees, it was a reference to that recourse. The letter continued:
- [42]
As a footnote to the last submission, there was a reference to Grocon (Belgrave St) Developer Pty Ltd v Construction Profile Pty Ltd [2020] NSWSC 409, a judgment of Ball J, relied upon by the primary judge, to which reference will be made below.
- [43]
The issue before the primary judge, and now before this Court, is whether, for the reasons stated in the payment schedule, PC 29 was not a valid payment claim under the Security of Payment Act.
Judgment below
- [44]
On 9 November 2023, Ball J identified five questions which he directed be determined separately from any other questions in the proceedings. Apart from costs, there do not appear to have been any other questions arising in the proceedings: however, the matter was complicated at that stage by the existence of the appellant’s cross-claim which gave rise to separate questions 2, 3 and 4. Those questions were resolved against the appellant, which has not appealed from the dismissal of its cross-claim. Question 5 assumed that there might be a discretionary issue as to the grant of relief if the respondents were otherwise successful. Putting that to one side, the question addressed by the primary judge, and the subject of the appeal, was whether the adjudication determination dated 25 July 2023 was “affected by jurisdictional error and thus liable to be quashed”.
- [45]
That statement of the issue reflected the proposition, confirmed in Probuild Constructions, [17] that a determination by an adjudicator under the Security of Payment Act may only be set aside by this Court in its supervisory jurisdiction under s 69 of the Supreme Court Act 1970 (NSW) for jurisdictional error.
- [46]
Further, the statutory scheme which was accepted by the High Court as inconsistent with any broader form of review is also consistent with a restrained approach to the construction of the Act in identifying matters which may constitute essential preconditions to the exercise of the adjudicator’s function. In the present case, the question of construction arises only with respect to the validity of PC 29 in the context provided by the contract.
- [47]
Both parties approached the question as one of characterising the nature of the claim. Unsurprisingly, and as appears from the description of the payment claim and the content of the payment schedule, they characterised it in different ways. The two grounds of appeal assumed that the question turned upon whether the claim was for payment of an amount “for construction work” undertaken by the appellant.
- [48]
The primary judge noted that the respondents’ case, as set out in the respondents’ written submissions before him, was:
- [49]
The judge then considered the terms of s 13(1), the definition of “progress payment”, the terms of ss 8 and 9 and concluded:
- [50]
What was to be implied from those two passages in the reasons of the primary judge was a finding that unless the Court was satisfied that the payment claim was a claim “for” work carried out under the construction contract, PC 29 was invalid. That can be inferred because the judge then set about answering the question, “Was Payment Claim 29 a claim for construction work?” From there on the judge addressed that question: as will be explained below, that was an impermissible step. The reasoning need not be addressed in detail.
- [51]
The appellant contended that it had never claimed a payment by way of damages or restitution, or on any other basis which might possibly have fallen within the reasoning in Southern Han, but only for construction work undertaken pursuant to the construction contract. When the respondents called on the security, the appellant was effectively deprived of part of the benefits obtained by it under the subcontract which had been paid on a contingent basis pursuant to the terms of the subcontract and in accordance with the Security of Payment Act, and recorded, in accordance with the terms of cl 42.1(h) and (i), by way of a running account. Although the appellant could not then say of which particular amounts it had been deprived, it could say that the balance of the account was less than the amount of its entitlements for construction work undertaken and carried out, and could therefore be the subject of a payment claim. This analysis was not accepted.
- [52]
After referring to further submissions by the parties, the judge stated:
- [53]
The primary judge stated that that was not an end to the matter, noting the appellant’s contention that the effect of certain clauses in the subcontract was that “the cash position between the two parties during the pendency of the works” was in the nature of a “running account”: at [79]. The judge accepted that the submission required reference to the terms of cl 42, which have been set out above. The judge considered those matters and concluded:
- [54]
However, the central issue for present purposes is not whether the reasoning of the primary judge was correct, but whether he was correct to undertake that exercise himself, rather than leave the question of the amounts, if any, to which the appellant was entitled for determination by the adjudicator having regard to the “jurisdictional” issue raised squarely by the payment schedule.
- [55]
Nevertheless, it was in this context that the primary judge considered and followed the reasoning of Ball J in Grocon:
- [56]
In accepting that the issue was jurisdictional, Ball J relied on the reasoning in Southern Han at [66]. [20] He did not refer to a different view adopted by Darke J in Illawarra Retirement Trust v Denham Constructions Pty Ltd, [21] accepting that the inclusion in the claim of an amount taken by the respondent under a guarantee was “merely an item that forms part of the actual monetary position between the plaintiff and the defendant which may be taken into account in the [adjudicator’s] determination of the amount (if any) that should be paid to the defendant in respect of its claim”.
- [57]
When the primary judge came to consider these judgments, he distinguished that of Darke J on the basis that the present argument had not been raised, but also preferred the reasoning of Ball J. [22]
Ground 1 – must a payment claim be “for construction work”?
- [58]
Ground 1 was in the following terms:
- [59]
Neither the primary judge, nor the respondents in this Court, identified any provision in the Security of Payment Act which required a payment claim to be made “for construction work”. As the primary judge acknowledged at [71] (set out at [49] above), having had regard to the definition of progress payment, “the Act does not provide, in terms, that a payment claim must be ‘for’ construction work”. The respondents did not take issue with that proposition.
- [60]
However, that linguistic feature is not determinative. Grammatically, a payment claim is not “for construction work”; it is a claim for money owing on account of construction work (or related goods or services). Thus, while s 13(5) and (6) use the phrase “for construction work” in relation to a payment claim served in a particular month, it is part of a shorthand phrase, namely “for construction work carried out or undertaken to be carried out (or for related goods and services supplied or undertaken to be supplied) in that month”. To similar effect, the term is used in relation to “money owing” or “consideration payable”: s 12(2); s 7(2); and in relation to the “claimed amount”: s 4(1).
- [61]
The point arises most relevantly for present purposes in the definition of “progress payment”, set out at [15] above. The definition gives a primary meaning, namely “a payment to which a person is entitled under section 8”, and a secondary meaning, by way of inclusions, each of the three matters identified being illustrative and not restrictive. As a matter of construction, there is no doubt that a payment claim must be for an amount of money, and the claim must assert that the amount is for work done, goods supplied or services rendered, under a construction contract. Those three categories of items are expansive and cover the range of primary obligations which are likely to form the basis of a right to payment under a construction contract. The two critical elements are that there be a “construction contract” and that there be consideration or amounts payable under it.
- [62]
Whether an amount is in fact payable will depend on the proper construction of the contract, identification of the work which has been carried out and a determination as to whether that work has already been paid for. These are matters to be determined by an adjudicator in the case of a dispute; they are not preconditions to the validity of a claim. If the entitlement is claimed to arise “under” a construction contract, as required by s 13(1) of the Act, the soundness of a claim denied in the payment schedule is for the adjudicator. Use of the word “for” to describe the required relationship between the amount and the basis of liability to pay is not a reason to substitute that word for the language of the statute, let alone to create a novel precondition to engagement.
- [63]
The passage in Southern Han at [66], set out above, does not contradict that approach. Southern Han did not purport to create an implied condition of the validity of a payment claim. It would, to say the least, be surprising if the High Court had sought to impose an implied constraint on the operation of the Act, without identifying the basis upon which it did so. The passage relied upon from Southern Han did not purport to undertake that task.
- [64]
Southern Han addressed three concepts, namely (i) the terms of the construction contract, (ii) the terms of the Security of Payment Act and (iii) relief available under the general law. It is uncontroversial that a progress payment cannot claim amounts which might be recoverable under the general law by way of damages, restitution, or by way of an account. The distinction drawn by the High Court was between such remedies and “payment ‘for’ work carried out or to be carried out … ‘under’ a construction contract”. The first sentence of the passage relied upon does not, it may be noted, use the term “for construction work”. The “important limitation” identified in the following sentence, being the matter with which the Security of Payment Act was "concerned”, was to secure payment “of an amount claimed to be payable in … discharge of an obligation to pay for work … imposed by the contractual force of a construction contract”. This refers, in the clearest possible terms, to the contractual basis of the obligation. (The contract must qualify as a “construction contract”, but there was no suggestion that the subcontract did not so qualify.)
- [65]
The distinction thus drawn in Southern Han was central to the reasoning of the Court. It occurred in the course of concluding that, in accordance with the Security of Payment Act as then in force, “the existence of a reference date under a construction contract within the meaning of s 8(1) is a precondition to the making of a valid payment claim under s 13(1)”: at [63]. The Court turned to the issue as to “how any such reference date is to be determined”. The Court then accepted that, at least by way of an amendment to s 8, the Security of Payment Act contemplated that “a claim for a progress payment might be made after the contract has expired”: at [65]. The entitlement of the subcontractor turned upon whether it was entitled to a payment in respect of work done under the contract at a time when the contract had been terminated and the work taken out of its hands.
- [66]
Rejecting the possibility that the Security of Payment Act protected a claim for damages, the joint reasons in Southern Han continued:
- [67]
Hodgson JA in JM Hargreaves asked whether a claim based on an extension of time could be made for “any amount that a construction contract requires to be paid as part of the total price of construction work”. Properly understood, the approval of these passages confirmed that the focus of consideration must be on payments due under the construction contract. (It is not necessary in this case to address the effect on this reasoning of the inclusion of “damages” in the definition of “Claim” in the subcontract.)
- [68]
This approach is consistent with the language of s 13(1), which refers to a person claiming to be entitled to a progress payment serving a claim on a person who “under the construction contract concerned, is or may be liable to make the payment”. No doubt the meaning of the phrases “under the construction contract” and “for construction work” will often coincide, but the former phrase is used in s 13(1), and the latter phrase is not. Each phrase is a label and, as Hodgson JA noted in JM Hargreaves, labels cannot be determinative of the nature of the claim. Reference to a claim “for” construction work merely invokes a different label. Section 13(2)(a) refers to construction work “to which the progress payment relates”; s 13(3)(b) provides for payment of an amount held by the respondent which is claimed to be “due for release”. No different language need be invoked, nor should it be.
- [69]
The scheme of the Security of Payment Act, as recognised in Southern Han and other cases, is to focus upon the construction contract, overlaid by a statutory entitlement to progress payments.
- [70]
Further, pursuant to s 9, the amount of a progress payment to which a person is entitled “in respect of a construction contract” (not “for construction work”) is, in the first instance, to be calculated “in accordance with the terms of the contract”. Again, the emphasis is on the contract. However, if the contract makes no such express provision, a valuation exercise must be undertaken pursuant to s 10(1)(b). One of the matters to which regard may be had is, “if any of the work is defective, the estimated cost of rectifying the defect”: s 10(1)(b)(iv). Thus, whether or not the exercise is fully covered by the terms of the contract, a progress claim will involve a range of evaluative assessments, such as the degree to which the work has been completed, whether it complies with the terms of the contract and whether it is defective. All of these are matters which, if a dispute is raised in a payment schedule, will need to be determined by an adjudicator.
- [71]
Consistently with this reasoning, in BSA this Court rejected a submission that an implication could be drawn from the statutory use of the term “reference date” in the singular, so that a payment claim could only be made with respect to one construction contract:
- [72]
Consistently with that approach, a payment schedule must identify why, if not the full amount, some part of the claim is being withheld “for any reason” and indicate “the respondent’s reasons for withholding payment”: s 14(3). Beyond those matters, and the requirement that the payment schedule be served within the permitted period, s 14 imposes no conditions on the validity of a payment schedule; if it is not served within time, it is ineffective.
- [73]
The respondents sought to derive some assistance from the requirements for a valid payment schedule addressed in Witron Australia Pty Ltd v Turnkey Innovative Engineering Pty Ltd. [25] However, there is nothing in the reasoning in Witron which suggests an intention to depart from the approach adopted to the construction of the Security of Payment Act discussed in earlier cases. [26] As the identification of the three relevant criteria at [21] of Witron demonstrates, the definition of a payment schedule is quite different from that of a payment claim. Further, the Court construed the relevant statutory provisions having regard to the purpose and function served by a payment schedule, which may be contrasted with that of a payment claim.
- [74]
Understanding the objects of the Security of Payment Act, its structure and its spare language, there is little scope for implying unstated conditions as essential to the validity of a payment claim or a payment schedule. The “important limitation that is implicit in the overall design of the Act” identified in Southern Han is not engaged with respect to the proposed criterion of the validity of a payment claim.
- [75]
Finally, alternative characterisations of a claim provide an uncertain basis for identifying an implied condition of validity, even if it were thought there might be greater room for implying limitations on the operation of the statutory scheme than that described above. In its simplest form, the claim and the payment schedule might be characterised as follows: “the claimant states ‘I am owed $x for construction work undertaken under the construction contract’; the respondent replies, ‘I have paid $x in full and no further amount is owing’”. In such a circumstance, the correctness of the claim and the response would be matters for determination by an adjudicator: however, that characterisation is equally apt to cover the present circumstances and the alternative characterisation provided by the respondents.
- [76]
The finding that the claim was invalid, and that the adjudication must be set aside for that reason, should be rejected.
Other issues
- [77]
The second way in which the appellant put its case was that, if there were such a “rule”, compliance was a matter for the adjudicator and not a matter of jurisdictional fact for determination by the Court. In the absence of such a “rule” that question does not directly arise. However, the underlying premise is that all questions arising from the construction of the contract and the provisions of the Security of Payment Act itself, as applied to the factual circumstances raised by the claim and the payment schedule, are matters for the adjudicator to determine. With few exceptions, it should be accepted that that is the object of the Security of Payment Act and the way it is expected to operate. That may be inferred from the terms of s 22, which provides in part:
- [78]
Further, the Act provides for an adjudication certificate to be filed as a judgment for a debt and to be enforceable accordingly: s 25(1). While a respondent can seek to have the judgment set aside, s 25(4) provides that the respondent:
- [79]
The effect of s 25(4)(a)(ii) is to confirm that the adjudicator’s understanding of the construction contract, even if legally erroneous, cannot be challenged on a claim to enforce an adjudication certificate; nor, without more, as held in Probuild Constructions, can it be so challenged on judicial review. These provisions, which are mirrored by restrictions on the respondents’ defences in relation to claims where no payment schedule has been served, or where there has been a failure to pay the excess above the scheduled amount, underlay the conclusion that an adjudication certificate cannot be challenged for error of law on the face of the record. The same statutory scheme is resistant to the implication of unexpressed conditions going to the validity of the claim.
- [80]
By way of observation, the reasoning of the adjudicator in upholding the payment claim was based on her understanding of the operation of the construction contract. Whether that understanding was correct or otherwise could not have been raised by the respondents in challenging the filing of the adjudication certificate. The Court should be cautious in implying an essential condition of validity of a payment claim in circumstances where the effect is to subvert the express preclusion on the power to resist the effect of an adjudication. The underlying basis for that observation is the function of the construction contract in determining whether a claim should succeed or not.
- [81]
It follows that, whatever conditions on the entitlement of the claimant arose from the correct reading of the subcontract and the Security of Payment Act, as relied on in the payment schedule, they were properly matters for the adjudicator. To that extent, ground 1(b)(ii) should be upheld.
- [82]
Ground 2 alleged error on the part of the primary judge in holding that PC 29 “was not, or did not comprise, a claim for construction work”. That ground was premised on acceptance of the propositions that (i) a payment claim could only be made for payment for construction work, and (ii) whether the payment claim was so made was a matter to be determined by the Court. For the reasons given above, that exercise was not a matter for the Court and it would be inappropriate for this Court to review that assessment. It is correct, however, as ground 2(b)(iii) asserted, that PC 29 was not invalid in the sense relied on by the respondents.
Orders
- [83]
The orders in the Equity Division entered on 15 December 2023 quashed the adjudication determination (order 1); superfluously, restrained the appellant from acting on the determination (order 2), and ordered that the present appellant pay the respondents’ costs, including the costs of the appellant’s cross-claim. The appellant sought to have each of these orders set aside. It did not seek to set aside the order dismissing its cross-summons (order 3), nor seek an order that the moneys paid into Court by the respondents be paid out to it (order 4). The reason for not challenging order 4 was presumably that it had already been given effect; however, there was an issue as to what order should be made in its place.
- [84]
The absence of challenge to order 3 (dismissing the cross-claim) has consequences for the appropriate order in relation to the costs in the Equity Division, namely whether the appellant should nevertheless pay the respondents’ costs of its failed cross-claim.
- [85]
With respect to the payment out, the appellant sought an order that the respondents pay it an amount of $10,180,582.60 less $20,472.83. (The balance is $10,160,109.77.) The appellant also sought interest from 7 July 2023 to the date of payment at the rate of 9.1% per annum. The adjudication determination identified the adjudicated amount as $10,180,582.60, indicating that the amount became payable on 7 July 2023; the accepted deduction was an amount which had been paid before the date of the adjudication determination, but after the date of the payment claim.
- [86]
Section 25(4) of the Security of Payment Act requires the respondent to an adjudication determination seeking to have the resulting judgment set aside to pay the unpaid portion of the adjudicated amount into Court pending final determination of the proceedings. It is conventional to make such a payment into Court as a condition of judicial review proceedings which seek to prevent the adjudication certificate being issued or filed.
- [87]
The respondents agreed that if the decision of the primary judge were to be set aside the appellant would be entitled to act on the adjudication certificate and obtain the payment made into Court plus interest. Counsel for the respondents further agreed that the procedure might be satisfied by an order of the Court requiring the respondents to make the payment directly to the appellant. That course should be taken.
- [88]
As to the costs of the proceedings in the Equity Division, the appellant’s costs of the respondents’ summons should be paid by those respondents. The cross-claim raised a separate matter as to whether cll 5.5(a)(iii) and 42.11 of the subcontract were invalid, because inconsistent with the terms of the Security of Payment Act and thus void pursuant to s 34 of the Act. Although it has been said that a respondent is entitled to raise such defences as it considers viable without being at risk of paying costs in respect of part of the proceedings if entirely successful on its first defence, where severable defences are raised by way of cross-claim that principle may not apply. Further, arguably it was only because the respondents sought to intervene to prevent the creation of a judgment debt that they were the plaintiffs in the Court below, whereas they might have sought to set aside a judgment debt once obtained by the appellant. In those circumstances, costs should follow the event and the appellant should pay the costs of its unsuccessful cross-claim. Otherwise, it should have its costs of the respondents’ summons and in this Court.
- [89]
Accordingly, the Court should make the following orders:
- (1)
Allow the appeal from the judgment in the Equity Division given on 14 December 2023.
- (2)
Set aside orders 1, 2 and 5 entered on 15 December 2023 and in their place order that:
- (3)
Order that the first to third respondents pay the appellant an amount of $10,160,109.77, together with interest at 9.1% per annum from 7 July 2023 to the date of payment.
- (4)
Order that the first to third respondents pay the appellant’s costs in this Court.
- (1)
- [90]
GRIFFITHS AJA: I agree with Basten AJA.