← All cases

[2015] NSWCA 275

Australian Vintage Limited v Belvino Investments No 2 Pty Ltd

Appeal allowed. Orders 1-3 made by the primary judge on 11 March 2015 be set aside. Order that the matter be remitted to the second respondent for determination in accordance with these reasons. Order the first respondent to pay the appellant’s costs of the appeal and, subject to Order 4 made by the primary judge, the costs of the proceedings below. The first respondent to have a certificate under the Suitors’ Fund Act 1951 (NSW) if eligible.

Catchwords

CONTRACT – construction – construction of clause stating formula to be applied by expert in dispute resolution under commercial lease of vineyard APPEAL – civil – expert determination under dispute resolution clause – whether expert’s determination open to review by Court on the basis that the expert misconstrued the formula to be applied by him in making the determination

Cases cited

  • AGL Victoria Pty Ltd v SPI Networks (Gas) Pty Ltd[2006] VSCA 173
  • Australian Broadcasting Commission v Australasian Performing Right Association Ltd[1973] HCA 36; 129 CLR 99
  • Belvino Investments (No 2) Pty Ltd v Australian Vintage Ltd[2014] NSWSC 978
  • Downer Engineering Power Pty Ltd v P & H Minepro Australasia Pty Ltd[2007] NSWCA 318
  • Electricity Generation Corporation v Woodside Energy Ltd[2014] HCA 7; 251 CLR 640
  • Holt v Cox(1997) 23 ACSR 590
  • Jones v Sherwood Computer Services plc(1992) 1 WLR 277
  • Legal & General Life of Australia Ltd v A Hudson Pty Ltd(1985) 1 NSWLR 314
  • Mercury Communications Ltd v Director General of Telecommunications[1994] CLC 1125
  • Mercury Communications Ltd v Director-General of Telecommunications(1996) 1 WLR 48
  • Onesteel Manufacturing Pty Ltd v BlueScope Steel (AIS) Pty Ltd[2013] NSWCA 27; 85 NSWLR 1
  • Shoalhaven City Council v Firedam Civil Engineering Pty Ltd[2011] HCA 38; 244 CLR 305
  • WMC Resources Ltd v Leighton Contractors Pty Ltd[1999] WASCA 10; 20 WAR 489

Legislation cited

  • Suitors’ Fund Act 1951 (NSW)

Judgment

[This headnote is not to be read as part of the judgment]

  1. [1]

    BATHURST CJ: This is an appeal from orders made by a judge of the Equity Division, dismissing a summons brought by the appellant (the lessee) challenging an expert determination by the second respondent (the expert), as agent for the third respondent. The expert determination was made pursuant to cl 4.26 of a lease between the first respondent (the lessor) as lessor and lessee, in respect of a vineyard known as Del Rios Vineyard in Victoria (the premises). Although nothing turns on this, it should be noted that each of the lessor and the lessee are successors in title to the original lessor and lessee.

The lease

  1. [2]

    The lease in question was dated 27 June 2003 and was for an initial term of 13 years with an option to renew for three further terms of 5 years (cl 4.13). The Court was informed at the hearing that the term of the lease had been extended to 2023. However, nothing turned on this for the purpose of these proceedings.

  2. [3]

    The permitted use of the premises was the development and operation of a vineyard. Clause 2.3(a) of the lease provided that the lessee could not use the premises for any purpose other than the permitted use.

  3. [4]

    Clause 2.3(b) imposed various covenants in relation to the maintenance of the premises. In particular, cl 2.3(b)(xi) imposed the following obligation on the lessee:

  4. [5]

    Clause 4.26, the subject of the proceedings in the present case, made provision for circumstances where the productivity of the premises was affected by a natural disaster. So far as relevant, it provided as follows:

  5. [6]

    It should be noted that cl 4.26(b) had two limbs. The first involved consideration of whether production had been reduced by more than 50% of average production capacity, as defined in the lease (average production capacity). The second involved a consideration of whether production capacity had been so reduced.

  6. [7]

    It is not necessary to set out the provisions in detail, but the facility, charge and mortgage referred to in cl 4.26(j) related to the facility granted to the lessor to enable it to purchase the premises and the mortgage and charge granted to secure that facility.

Background

  1. [8]

    In October 2013, a severe frost occurred in the area in which the premises was situated, causing a substantial diminution in the production of grapes for the 2014 vintage year. As a consequence, the lessee invoked cl 4.26 of the lease. By email to the lessor dated 8 January 2013, the lessee asserted that the volume of grapes capable of being produced in the vineyard had been reduced by more than 50% of average production capacity. It asserted that the difference between the current estimated actual yield for the 2014 vintage (16,194 tonnes) and the prefrost production capacity for the 2014 vintage (31,865 tonnes) was 15,671 tonnes, more than 50% of the average production capacity of 21,236 tonnes.

  2. [9]

    Following a request from the lessor for formal notice under cl 4.26, the lessee, by letter of 30 January 2014, essentially repeated the claims it had made in the email, but expanded somewhat on the method of calculation of the tonnages referred to.

  3. [10]

    On 16 June 2014, the issue was referred to the expert under cl 4.26(d).

The expert determination

  1. [11]

    On 2 August 2014, the expert issued an interim determination. On 7 October 2014, he issued a final determination which incorporated the interim determination.

  2. [12]

    The expert determined that although a natural disaster had occurred, any resulting reduction of production or production capacity was less than 50% of average production capacity. His conclusion was expressed in the following terms:

  3. [13]

    In a table forming part of the report, the expert rejected the calculations proffered by the lessee. According to the report, the lessee had submitted that the benchmark for assessing the reduction in production capacity due to frost was 50% of average production capacity, namely, 10,617.75 tonnes, which had to be compared with the reduction in actual production from the prefrost production capacity. This reduction (being the difference between 31,864.6 tonnes and 15,260.11 tonnes) was in an amount of 16,604.49 tonnes, which was greater than 50% of average production capacity. It followed from these conclusions that cl 4.26(h) to (j) had no application.

  4. [14]

    It can be seen from the rejection of the lessee’s submission that the area of dispute between the parties, at least on this issue, was the equation to be used in determining whether or not cl 4.26(h) to (j) applied, as distinct from the particular integers which went into the equation. However, as noted below, the lessor contended on the appeal that no postfrost production capacity figure had been supplied to the expert to enable a comparison between pre and postfrost production capacity to be undertaken.

  5. [15]

    The expert determination appears to have been carried out on the following basis. In dealing with what he described as “2014 Production vs Average Production Capacity”, the expert compared 2014 production with average production capacity. As this comparison showed a reduction of 28.14%, the expert found that the first limb of cl 4.26(b) did not apply.

  6. [16]

    In relation to the second limb, the expert compared prefrost production capacity for 2014 with average production capacity. The comparison showed no reduction in production capacity, but rather an increase.

  7. [17]

    By contrast, the lessee’s approach to the second limb of cl 4.26(b) involved comparing prefrost capacity with actual production in that year. This showed a reduction of 16,609.49 tonnes, which was greater than 50% of average production capacity.

  8. [18]

    In these circumstances, the lessee brought proceedings in the Equity Division, seeking to have the expert determination set aside and declarations as to the correct construction of cl 4.26(b) and (f).

The reasoning of the primary judge

  1. [19]

    The primary judge dismissed the summons. First, he held that the expert determination was not reviewable. Second, he held that the determination was correct, although he reached his conclusion that the relevant threshold was not reached in a somewhat different fashion to the expert.

  2. [20]

    The primary judge noted that both parties had agreed that the correct approach to the question of whether the expert determination could be reviewed was whether the determination was made in accordance with the terms of the contract: Legal & General Life of Australia Ltd v A Hudson Pty Ltd (1985) 1 NSWLR 314 (Legal & General Life) at 336. The primary judge also placed reliance on the decision of this Court in Downer Engineering Power Pty Ltd v P & H Minepro Australasia Pty Ltd [2007] NSWCA 318 (Downer Engineering), in which Hoeben J, with whom Giles JA concurred, noted (at [79]) that there was “ample authority for … questions of mixed fact and law to be referred, to third party experts”. In that case, Basten JA also commented (at [17]) that it was “well-established that the effect of a determination by a valuer depends upon the construction of the contract pursuant to which the referral takes place” and (at [18]) that the dispute “was within the contemplation of the parties as one which could properly be referred to the valuer”. The primary judge stated that these remarks supported the conclusion that, in the present case, the determination was not subject to review.

  3. [21]

    The primary judge noted that before the expert was appointed, it was obvious to both the lessor and the lessee that they differed as to the interpretation of cl 4.26. He pointed to the fact that prior to their submission to the expert, the lessor had brought proceedings seeking declarations as to the true construction of the clause. These proceedings were stayed by White J. However, it should be noted that in those proceedings, White J pointed out that if the lessee’s construction was correct, it was at least arguable that the determination would not be binding, having not been made in accordance with the terms of the lease: Belvino Investments (No 2) Pty Ltd v Australian Vintage Ltd [2014] NSWSC 978 at [54].

  4. [22]

    The primary judge placed particular reliance on the decision of the English Court of Appeal in Jones v Sherwood Computer Services plc (1992) 1 WLR 277 and, in particular, on the following passage from the judgment of Dillon LJ (at 287):

  5. [23]

    The primary judge stated that that case was “authority for the proposition that any question of construction of the clause under which the expert is to operate is as much part of the task of the expert as the determination of facts and the calculation of figures and not open to review by a Court”

  6. [24]

    The primary judge also referred to the decision of the House of Lords in Mercury Communications Ltd v Director-General of Telecommunications (1996) 1 WLR 48 (Mercury Communications). In that case, the appellant instituted proceedings seeking declarations as to the construction of certain phrases in an agreement by which the respondent was entitled to impose certain terms in telecommunication interconnection agreements. A majority of the Court of Appeal held that the proceedings should be struck out as there was no justiciable issue. The House of Lords allowed an appeal from that decision.

  7. [25]

    The primary judge referred to the following passage from the speech of Lord Slynn in Mercury Communications, with whom the other Law Lords agreed (at 58-59):

  8. [26]

    The primary judge acknowledged that, read in isolation, that paragraph supported the lessee’s contention. However, he concluded that as the clause in Mercury did not have a final and binding quality and was not characterised as an expert determination, it did not in fact assist the lessee in the present case. He also noted that the House of Lords did not criticise Jones v Sherwood Computer Services plc, so the decision did not undermine the proposition he drew from that case. The primary judge emphasised that cl 4.26(g) of the lease provided, in unqualified terms, that the expert determination was final and binding. He expressed his conclusions in the following terms:

  9. [27]

    The primary judge also concluded that the expert did not fall into error. He expressed his conclusion in the following terms:

  10. [28]

    Like the expert, the primary judge construed the first limb of cl 4.26(b) as requiring a consideration of the difference between average production capacity and actual production for the vintage year in question. He concluded that the reduction derived as a result of that calculation was less than 50% of average production capacity, so the first limb did not trigger the operation of cll 4.26(h) to (j).

  11. [29]

    The primary judge adopted a somewhat different approach to the expert in respect of what he described as option 2. In par [67](7) of his judgment, cited above, he indicated that the clause called for a comparison of postfrost production capacity and average production capacity. Although he stated that no postfrost production capacity figure had been provided, he used the figure which was agreed upon as postfrost production, 15,260 tonnes, as a proxy for postfrost production capacity. He stated that the difference between average production capacity, 21,236 tonnes, and that amount, namely, 5,976 tonnes, was less than 10,618 tonnes, being 50% of average production capacity.

A preliminary issue

  1. [30]

    As can be seen from par [67](6), [67](7) and [67](15) of the judgment of the primary judge, the primary judge concluded that the lessee did not provide the expert with a post-natural disaster production capacity figure. The lessor submitted that no reliance was placed by the lessee on post-disaster production capacity before the expert. However, senior counsel for the lessor accepted that it was relied on by the lessee in the Court below using actual production as a proxy for production capacity. The lessee, by contrast, contended that post-natural disaster production capacity was relied on before the expert.

  2. [31]

    It is not necessary to determine which of these contentions is correct. If the primary judge was correct on either or both of the issues dealt with by him then the appeal will be unsuccessful. If, on the other hand, it is concluded that the decision of the expert is reviewable and the primary judge was in error in concluding that the expert’s determination was correct, then the matter can be remitted to the expert to be determined in accordance with the reasons of the Court. Ultimately, the parties seem to accept that this approach is appropriate.

The correct construction of cl 4.26(b) and (f)

  1. [32]

    The lessee submitted that what was required by those clauses was first, a calculation of the extent to which there had been a reduction in production or production capacity due to the natural disaster. It submitted that once that reduction was ascertained, it was necessary to compare the reduction to the figure of 50% of average production capacity. If the comparison demonstrated that the reduction was greater than 50% of average production capacity, the threshold for the operation of the subsequent provisions of cl 4.26 was satisfied.

  2. [33]

    The lessee accepted that, in the present case, the first limb of the formula could not operate on that construction, as the natural disaster had occurred before production. It submitted that it could apply, for example, when the crops had been damaged after harvest by fire or flood. It was implicit in this submission that, contrary to the opinion of the expert, “production” did not refer to “total production, harvest and delivery to a winery of all grapes from the vineyard in any one vintage”.

  3. [34]

    The lessee submitted that the construction for which it contended was to be preferred as it involved a direct measurement of the reduction in production or production capacity caused by the natural disaster. It submitted that the construction relied on by the primary judge as to the second limb of the clause ignored the necessary causal connection.

  4. [35]

    It also pointed out that average production capacity was a different concept to production or production capacity and thus not an appropriate starting point from which to measure the reduction.

  5. [36]

    The lessee also submitted that the construction placed on the provision by the primary judge did not take into account the requirement in the clause that what was to be considered was the reduction in respect of “any one vintage”. Senior counsel for the lessee submitted that unless a comparison was done in the manner he contended for, the expression “reduction for that vintage year” would be devoid of meaning.

  6. [37]

    Senior counsel for the lessee accepted that, in the circumstances of the present case, the application of the second limb of cl 4.26(b) in the way contended for would produce a reduction of greater than 50% of average production capacity, although production capacity itself would remain greater than that figure. He accepted that this result meant that cll 4.26(c)(iii), 4.26(f)(iii) and 4.26(h)(i) could have no application. He submitted that, notwithstanding, the lessee had the option in those circumstances to do nothing or elect to exercise the option to terminate contained in cl 4.26(h)(ii) and, as a consequence, to elect whether or not to purchase the property, as provided for in cl 4.26(j)(iii) of the lease.

  7. [38]

    Senior counsel for the lessee also submitted that cl 2(b)(xi) performed a different function from cl 4.26, submitting that the separate and ongoing function required by that subclause was not related to the occurrence of a natural disaster, the issue with which cl 4.26 was dealing.

  8. [39]

    The lessor submitted that the conclusion of the trial judge was consistent with the meaning of the words “has been reduced by more than 50% of average production capacity”. Senior counsel for the lessor submitted that the minuend was average production capacity and the application of the clause did not involve a separate exercise of determining the difference between postfrost production capacity and prefrost production capacity and then comparing the difference with 50% of average production capacity. Put in non-mathematical terms, the lessor contended that the clause simply required a consideration of whether postfrost production capacity was less than 50% of average production capacity.

  9. [40]

    Senior counsel for the lessor submitted that, in that context, cl 4.26(f)(i) required what he described as a “one-stage approach”, namely, to determine whether production capacity had been reduced by reference to average production capacity. He submitted, placing particular reliance on cl 4.26(f)(iii), that the fundamental concern of the clause was to measure the effect that the disaster had on production compared with previous years.

  10. [41]

    The lessor submitted that the construction for which it contended was more consistent with the balance of cl 4.26, which recognised a reduction of 50% of average production capacity as the threshold for the operation of subcll 4.26(c)(iii), (f)(iii), (h) and (i). The lessor submitted that those paragraphs presupposed that for the right to terminate to be enlivened, there must have been a reduction of more than 50% of average production capacity. Senior counsel for the lessor submitted that the election contemplated by cl 4.26(h) would always arise when the approach it contended for led to a reduction of greater than 50% of average production capacity. He pointed out that on the lessee’s construction, there would be no room for the election in circumstances such as those that existed in the present case.

  11. [42]

    The lessor submitted that cl 4.26(f)(i) should be construed to work equally for production and production capacity. Adopting the expert’s definition of production, namely, the actual yield as harvested and delivered to a winery, it submitted that there could never be a situation where, on the lessee’s construction, natural disaster could reduce production. It submitted that a fire post-harvest, an example given by the lessee as a circumstance where the first limb of the clause could operate, would not be a natural disaster as it would not affect the vines growing on the premises.

  12. [43]

    The lessor also sought to draw support from cl 2.3(b)(xi). It submitted that cl 4.26 should be construed consistently with that clause, the only difference being the circumstances required for cl 4.26 to operate. It submitted that the Court would not give the same formulation a different meaning in different parts of the lease unless required to do so by clear language.

  13. [44]

    The lessor also submitted that the lessee’s construction was contrary to the commercial purpose of the clause. It submitted that the clause was designed to deal with circumstances where, as a result of a natural disaster, production capacity fell below 50% of, what it described as, “the historical average”. It submitted that the lessee’s construction would effectively permit the lessee to terminate the lease where, notwithstanding the disaster, production capacity remained significantly above the historical average. It also submitted that the lessee’s construction led to what it described as an unusual result, namely, that the better the vineyard is performing, the easier it would be to terminate.

  14. [45]

    The lessor submitted that, by contrast, its construction meant that there was a direct relationship between productivity, relative to average production capacity, and the required impact of the natural disaster. It submitted that on its construction, “The greater the relative productivity, the greater the required impact of the Natural Disaster”. Senior counsel for the lessor pointed to the fact that cl 4.26 only operated after the first five years of the lease. He said that it could be inferred from that that by that time, the vineyard would have been developed to a certain stage and the ebb and flow of seasons would be known, such that 50% of average production capacity would be an appropriate benchmark against which to measure postfrost production capacity.

Consideration

  1. [46]

    In dealing with the question of construction, it is appropriate to focus first on the words used by the parties, having regard to the fact that they must be considered in the context of the lease as a whole and having regard to the purpose and object of cl 4.26 as it appeared from the lease. Neither party suggested that there were any surrounding circumstances known to them which would assist in the construction of this clause.

  2. [47]

    Clause 4.26(b) requires consideration of the reduction in production or production capacity in respect of one vintage due to a natural disaster. The relevant level of reduction for the balance of cl 4.26 to operate is 50% of average production capacity for that vintage year. That is defined by reference to production for the preceding two vintages, not production capacity.

  3. [48]

    Clause 4.26(c)(i) and cl 4.26(f)(i) do not refer to production or production capacity being in respect of any one vintage year. However, it was not suggested by either party that these subclauses operate in a different fashion to cl 4.26(b). It would be anomalous if they did so.

  4. [49]

    Clause 4.26(b), on its face, looks to the effect of a natural disaster on production or production capacity in the vintage year in question. Read literally, it is only once the amount of that reduction is ascertained that the comparison with 50% of average production capacity is to be carried out.

  5. [50]

    By contrast, the expert’s determination of the first limb of the clause involved a direct comparison between 2014 production and average production capacity (see par [12] above). The primary judge effectively adopted the same construction in respect of the first limb.

  6. [51]

    The expert’s interpretation of the clause simply involves comparing production in a given year with average production capacity and then applying the balance of the clause if production is less than 50% of average production capacity. The difficulty with this approach is that it does not calculate reductions in grapes produced in one vintage year prior to comparing the reduction with average production capacity. Rather, it simply compares grapes produced in that year with average production capacity.

  7. [52]

    In respect of the second limb of cl 4.26(b), the approach of the expert and the primary judge differed somewhat, but neither considered the question of whether there had been a reduction in production capacity in the vintage year in question. Rather, their approaches compared production capacity in the relevant vintage year with average production capacity. In the case of the expert, he compared prefrost production capacity with average production capacity, while the primary judge compared postfrost production capacity with average production capacity. Both approaches ignored the reduction in production capacity in the vintage year in question resulting from the natural disaster.

  8. [53]

    As I indicated, the lessor pointed to a number of contextual matters which it said supported the primary judge’s construction. The first was that, on the lessee’s construction, the first limb could not operate as there could never be a situation where the comparison required by that construction was capable of being made. As I indicated above, that submission relied on the expert’s definition of production, namely, that production would only be completed when the yield was harvested and delivered to a winery. It does not seem to me that actual delivery was part of production and, in the circumstances, that the example given by the lessee, namely, crops destroyed after harvest, was an example where the first limb could operate.

  9. [54]

    In this context, the lessor also relied on cl 4.26(m), which, for the purpose of the definition of average production capacity, describes a natural disaster as one “which destroyed or affected the vines growing on the Premises”. However, the quoted words do not form part of the definition of natural disaster and the relevant test for the operation of the formula was the amount of grapes produced.

  10. [55]

    In considering this aspect of the matter, it must also be borne in mind that the construction preferred by the primary judge left the second limb of the clause with very little work to do. This is because post-disaster production capacity, as a matter of logic, must be greater than or at least equal to actual production. Thus, if the difference between actual production and average production capacity does not exceed the 50% threshold, it is self-evident that the difference between production capacity and average production capacity would not do so. Thus, on either interpretation of the clause, one or other limb will have a very limited operation.

  11. [56]

    The lessor also pointed to what it described as the anomalous result produced by the lessee’s construction. It pointed out that, in the present case, the option to terminate would arise, although production in fact would remain above 50% of average production capacity. However, the so-called anomaly arose from the fact that what was required to be ascertained was a reduction in production capacity, which was to be compared to a number, which, although described as average production capacity, was in fact based on actual production for the two previous years. Such a comparison is always capable of producing a result, as in the present case, when production capacity, which may or may not be greater than actual production capacity for the previous years, is significantly greater than actual production for those years.

  12. [57]

    It may be that the parties did not consider that this anomaly would arise, on the basis there would be little difference between actual production and production capacity for any year. The expert stated that in fact, that had been the case in respect of the preceding three vintages. The expert made the following comments on this issue:

  13. [58]

    The fact that the clause was operating in circumstances where there was a significant increase in prefrost production capacity, compared to average production capacity, does not mean that the construction urged by the lessor should apply and any reduction in capacity for the vintage year be ignored. It of course remains for the expert to reach a view on postfrost production capacity.

  14. [59]

    It is also correct, as the lessor pointed out, that the effect of the lessee’s construction in the present case is to render cl 4.26(f)(iii) and (h)(i) inoperative, while leaving the option to terminate available. However, this was because of the significant increase in prefrost production capacity over average production capacity in the circumstances of the present case, rather than what might be described as a capricious operation of the clause.

  15. [60]

    Further, I do not think that the position is affected by cl 2(b)(xi). That clause, which forms one of a set of provisions dealing with the maintenance of the vineyard, deals with reduction in production or production capacity between vintages. By contrast, cl 4.26(b) refers to a reduction in any one vintage year due to a natural disaster.

  16. [61]

    It follows, in my opinion, that the construction contended for by the lessee is correct. It accords with the literal meaning of the clause, which looks to reductions in production or production capacity in a vintage year due to a natural disaster. Although the parties may not have anticipated the particular circumstances in which the clause was required to operate in the present case, it does not follow that the interpretation is inconsistent with the commercial object of the provision, namely, to protect the lessee from a fall in production or production capacity due to a natural disaster. The construction does not produce commercial nonsense and is not arbitrary or capricious: Electricity Generation Corporation v Woodside Energy Ltd [2014] HCA 7; 251 CLR 640 at [35]; Australian Broadcasting Commission v Australasian Performing Right Association Ltd [1973] HCA 36; 129 CLR 99 at 109.

Was the expert’s determination reviewable

  1. [62]

    The question remains as to whether the expert’s determination was capable of review.

  2. [63]

    Each party accepted that the relevant test was that the expert’s determination would only be set aside if it was not done in accordance with the terms of the contract: Legal & General Life at 336. The parties also seemed to accept that if, as a matter of construction, the expert’s mandate extended to determining the true construction of the contract, the decision would not be reviewable.

  3. [64]

    It was also common ground between the parties that the question was to be determined by ordinary principles concerning the construction of contracts, requiring consideration of the language used by the parties, the surrounding circumstances known to them and the commercial purpose or object to be secured by the contract, so as to avoid it making commercial nonsense or working commercial inconvenience: Electricity Generation Corporation v Woodside Energy Ltd at [35] and the cases there cited.

  4. [65]

    The lessee submitted that in considering the issue of what the parties agreed to entrust to an expert, a distinction is sometimes drawn between objective and subjective matters. It submitted, referring to AGL Victoria Pty Ltd v SPI Networks (Gas) Pty Ltd [2006] VSCA 173 (AGL Victoria) at [53], that it was “easier to suppose that parties to a contract contemplate that the expert’s determination on subjective matters is beyond the realm of review”, as distinct from a determination of objective matters. In that context, the lessee submitted that the parties agreed to a determination in accordance with the true meaning of the clause.

  5. [66]

    Senior counsel for the lessee submitted that the correct construction of a contractual provision was an objective matter. He submitted that the primary judge was in error when he stated that the construction of the clause was not an objective fact, submitting that it was not for the expert to determine the relevant contractual criteria without the possibility of correction.

  6. [67]

    Senior counsel for the lessee also submitted that the primary judge erred in his conclusion that Jones v Sherwood Computer Services plc was authority for the proposition that any question of construction of the clause under which the expert was to operate was as much part of the task of the expert as the determination of facts or calculations of figures. He submitted that, to the extent that that case was authority for that proposition, it was contrary to the dissenting opinion of Hoffmann LJ in Mercury Communications Ltd v Director General of Telecommunications [1994] CLC 1125 (Mercury Communications CoA Judgment) at 1140, whose conclusion was upheld on appeal: Mercury Communications.

  7. [68]

    The lessee, in its written submissions, and senior counsel for the lessee, criticised the reliance by the primary judge on the fact that cl 4.26(g) provided that the expert’s determination was final and binding. The lessee pointed to the statement by Nettle JA (as his Honour then was) in AGL Victoria at [76] that such a clause makes very little difference to the question of whether the determination is reviewable for error.

  8. [69]

    In this context, the lessee submitted that the clause, as a matter of construction, did not empower the expert to determine the meaning of the contractual terms in question, such that his decision on the question was not reviewable. It pointed to the fact that the expert was an expert in viticulture and it was unlikely that a reasonable business person would have intended such a person to determine a question of contractual construction without resort to the court.

  9. [70]

    The lessor submitted that understanding the structure and language of clause 4.26 was critical to answering the question. It pointed out that the mechanism of cl 4.26 was enlivened by the lessee forming the opinion in cl 4.26(b). It pointed out that cl 4.26(c) then required the lessor and the lessee to meet and negotiate and, if there was disagreement, to refer the dispute to the expert. Senior counsel for the lessor submitted that the role of the expert was to determine the dispute between the parties, which may involve a question of how the relevant contractual provisions would operate.

  10. [71]

    Senior counsel for the lessor submitted that although a provision that the expert’s decision was final and binding was not determinative of whether a decision was reviewable, it was a relevant factor to take into account, particularly in cases such as the present where the dispute could involve a question of construction of the contract.

  11. [72]

    Senior counsel for the lessor submitted that the primary judge was correct in his reliance on Jones v Sherwood Computer Services plc. He referred to the passage from the judgment of Dillon LJ, which I have set out above, and submitted that the primary judge correctly applied that approach. He noted that Jones v Sherwood Computer Services plc was cited by the House of Lords in Mercury Communications without disapproval.

  12. [73]

    The lessor also submitted there were good commercial reasons as to why the decision might have been entrusted to an expert viticulturist, including cost, expedition and finality.

Consideration

  1. [74]

    The parties accepted that the question depended upon whether the determination was made in accordance with the contract: Legal & General Life at 336. As Nettle JA pointed out in AGL Victoria at [44], in one sense, this test is conclusionary. The question of whether the determination is open to review rather depends on whether or not the expert has carried out the task which he or she was contractually required to undertake: AGL Victoria at [51]; Holt v Cox (1997) 23 ACSR 590 at 596-597; Shoalhaven City Council v Firedam Civil Engineering Pty Ltd [2011] HCA 38; 244 CLR 305 at [26]-[27]. If the expert in fact carried out that task, the fact that he made errors or took irrelevant matters into account would not render the determination challengeable.

  2. [75]

    On the other hand, if the expert had not performed the task contractually conferred on him or her, but rather performed some different task, or carried out his or her task in a way not within the contractual contemplation of the parties, objectively ascertained, then the determination will be liable to be set aside.

  3. [76]

    That is not to say that questions of mixed fact and law, or for that matter, pure questions of law, could not be left for the determination of the expert: Downer Engineering at [79]. Whilst it is a matter of contractual construction in each case, it has been stated in a number of cases that parties are more likely to have left to an expert matters involving discretion or opinion, rather than matters of objective fact: AGL Victoria at [53]; WMC Resources Ltd v Leighton Contractors Pty Ltd [1999] WASCA 10; 20 WAR 489 at 494-497.

  4. [77]

    There will be cases, such as the present case, where the expert, for the purpose of performing his or her task, will be required to consider objective matters, including the construction of a contract. As was pointed out by Allsop P (as his Honour then was) in Onesteel Manufacturing Pty Ltd v BlueScope Steel (AIS) Pty Ltd [2013] NSWCA 27; 85 NSWLR 1 at [61], the objective analysis required by the process of contractual construction can only produce one meaning.

  5. [78]

    It is correct, as Allsop P pointed out in the passage referred to above, that the fact that there is one true meaning does not detract from what his Honour described as “the pervasive reality that a contract will often have potentially more than one meaning … and that reasonable minds often differ about what is the true meaning”. That does not mean that the ascertainment of that meaning was necessarily left to the expert, such that the expert’s determination was immune from review by the Court. The position was explained by Hoffmann LJ in his dissenting judgment in the Court of Appeal in the Mercury Communications CoA Judgment in the following terms (at 1140):

  6. [79]

    In the present case, cl 4.26(b) required the lessee to form an opinion as to whether production or production capacity had been reduced by more than the threshold amount and whether it was due to a natural disaster. Clause 4.26(c) required the parties to meet to agree on these issues and the remedial work required to restore production capacity to the threshold. In the absence of an agreement, the matter could be referred to the expert, defined in cl 4.25 as a person who was a principal or consultant of the third respondent. Such an expert was mandated by cl 4.25 to give a report on the state of the property, including the health and condition of vines and the state of repair of trellises. Such a person, self-evidently, would be in a position to consider the effect of a natural disaster on production or production capacity.

  7. [80]

    Under cl 4.26(f), the expert was required to deal with three specific matters. The first required an assessment of pre and post-disaster production and production capacity and whether there had been a reduction by more than 50% of average production capacity. It involved a calculation of the integers to be put into the formula.

  8. [81]

    It is correct that the expert also needed to make a decision as to the manner in which the formula operated. However, that did not mean that the parties agreed to be bound by the expert’s determination of that issue. The question is whether the parties agreed to be bound by the expert’s determination, both on the construction of the formula provided for in cl 4.26(b), as well as the quantification of lost production or production capacity and the determination of whether it was caused by a natural disaster, or whether the parties only intended to be bound in respect of the determination of the latter two matters.

  9. [82]

    It is correct, as the lessor pointed out, that the reference to the expert came as a result of the parties being unable to resolve a dispute, which included a dispute as to the interpretation of the formula. However, notwithstanding that fact, in my opinion, the decision-making authority of the expert (to adopt the words of Hoffmann LJ) would not extend to determining the construction in the formula such as to leave his or her decision on this issue unreviewable.

  10. [83]

    Although it is correct that the dispute between the parties could include matters of contractual construction, the contract provided that the expert’s determination was to relate to the three matters in cl 4.26(f). These matters seem to me to involve, first, a calculation of production, production capacity and average production capacity and the calculation of any reduction. Although the expert had to apply the formula, it does not seem to me that the contract revealed an intention that the parties would be bound if he or she misapplied it.

  11. [84]

    The three matters for determination, namely, calculation of production or production capacity, whether the reduction was due to a natural disaster and the remedial work required to restore production capacity, were all matters of judgment and were peculiarly within the qualification of the expert, particularly having regard to his or her functions under cl 4.25. By contrast, the construction of the formula was an objective matter outside of the expertise of such a person. It seems to me that, in these circumstances, it would be unlikely that the parties intended to bind themselves to the expert’s determination on that issue. It does not seem to me that questions of costs, finality and expedition compel a contrary conclusion.

  12. [85]

    Nor do I think that the fact that the decision is said to be final and binding compels a contrary conclusion. I respectfully agree with the statement by Nettle JA in AGL Victoria at [76] that such a clause makes very little difference to the question. To the extent that the decision was made in accordance with the terms of the contract, it will be final and binding. To the extent that it is not, it will be subject to review.

  13. [86]

    As I indicated, the primary judge considered that Jones v Sherwood Computer Services plc was authority for the proposition that any question of construction of the clause was as much the task of the expert as the determination of facts and calculation of figures. With respect to his Honour, I cannot agree that that case is authority for such a wide proposition. Immediately before the passage cited by the primary judge, Dillon LJ stated that “on principle, the first step must be to see what the parties have agreed to remit to the expert” and that the decision would not be binding if the expert had not done what he or she was appointed to do: Jones v Sherwood Computer Services plc at 287.

  14. [87]

    In these circumstances, in my opinion, the primary judge erred in concluding that the expert’s determination on the construction of the formula was incapable of review.

Conclusion

  1. [88]

    The expert and the primary judge were in error in their construction of cl 4.26. When reduction of production capacity is in issue, the clause requires a comparison of pre-disaster production capacity for the vintage year in question and post-disaster production capacity for that year. If the difference exceeds 50% of average production capacity, then cl 4.26(h) to (j) apply.

  2. [89]

    Further, the expert’s determination was not made in accordance with the contract and is reviewable.

  3. [90]

    As I indicated, the expert has not calculated post-disaster production capacity. In these circumstances, the matter should be remitted to the expert to make a determination in accordance with these reasons.

  4. [91]

    I would make the following orders:

    1. (1)

      Appeal allowed.

    2. (2)

      Orders 1-3 made by the primary judge on 11 March 2015 be set aside.

    3. (3)

      Order that the matter be remitted to the second respondent for determination in accordance with these reasons.

    4. (4)

      Order the first respondent to pay the appellant’s costs of the appeal and, subject to Order 4 made by the primary judge, the costs of the proceedings below.

    5. (5)

      The first respondent to have a certificate under the Suitors’ Fund Act 1951 (NSW) if eligible.

  5. [92]

    BEAZLEY P: I have had the advantage of reading in draft the reasons of the Chief Justice. I agree with his Honour's reasons and with the orders he proposes.

  6. [93]

    McCOLL JA: I agree with Bathurst CJ's reasons and the orders his Honour proposes.

Unofficial copy. Source: NSW Caselaw. Refer to the official version for authoritative text.