[2017] NSWCA 89

LDF Enterprise Pty Ltd v State of New South Wales

1. Grant leave to appeal. 2. Direct LDF Enterprise to file a notice of appeal in the form contained in the white folder within 7 days, and otherwise dispense with the rules as to service. 3. Appeal dismissed. 4. Dismiss the statement of claim in proceeding 2017/100386. 5. LDF Enterprise to pay the State’s costs in this Court, including the reserved costs of the hearing before Emmett AJA. 6. LDF Enterprise to pay the defendants’ costs at first instance.

Catchwords

ADMINISTRATIVE LAW – procedural fairness – existence of obligation to accord procedural fairness – whether power of entry in the course of investigations attracted obligation to accord procedural fairness to landowner – whether statute clearly displaced obligation – Protection of the Environment Operations Act 1997 (NSW) s 166 JURISDICTION – first duty of court to determine jurisdiction – whether claim for declaratory and injunctive relief concerning threatened entry on land in purported exercise of powers under Protection of the Environment Operations Act 1997 (NSW) within exclusive jurisdiction of Land and Environment Court – Land and Environment Court Act 1979 (NSW) s 71

Cases cited

  • Ashby v White (1703) 2 Ld Raym 938; 92 ER 126
  • Berowra Holdings Pty Ltd v Gordon (2006) 225 CLR 364;[2006] HCA 32
  • Bradlaugh v Gossett(1884) 12 QBD 271
  • Coco v The Queen(1994) 179 CLR 427
  • Commissioner of Australian Federal Police v Propend Finance Pty Ltd(1997) 188 CLR 501
  • CPCF v Minister for Immigration and Border Protection (2015) 255 CLR 514;[2015] HCA 1
  • D’Anastasi v Environment, Climate Change & Water (NSW) (2011) 81 NSWLR 82;[2011] NSWCA 374
  • Federated Engine-Drivers and Firemen’s Association of Australasia v Broken Hill Pty Co Ltd(1911) 12 CLR 398
  • Khatri v Price(1999) 95 FCR 287
  • Minister for Immigration and Border Protection v SZSSJ[2016] HCA 29; 90 ALJR 901
  • Musgrove v Chun Teeong Toy[1891] AC 272
  • Obeid v R (2015) 91 NSWLR 226;[2015] NSWCCA 309
  • Owners of “Shin Kobe Maru” v Empire Shipping Co Inc(1994) 181 CLR 404
  • Plenty v Dillon(1991) 171 CLR 635
  • Proust v Blake(1989) 17 NSWLR 267
  • Re Macks; ex parte Saint (2000) 204 CLR 158;[2000] HCA 62

Legislation cited

  • Civil Procedure Act 2005 (NSW), § 149B
  • Interpretation Act 1987 (NSW), § 33
  • Land and Environment Court Act 1979 (NSW), § 20, 71, 72
  • Law Enforcement (Powers and Responsibilities) Act 2002 (NSW), § 65
  • National Parks and Wildlife Act 1974 (NSW), § 86, 156B
  • Protection of the Environment Operations Act 1997 (NSW), § 184, 189, 196, 197, 199, 211

Judgment

  1. [1]

    LEEMING JA: This is an application for leave to appeal from the refusal of interlocutory injunctive relief sought by the owner of land to prevent officers within the Office of Environment and Heritage (OEH) from entering upon that land: LDF Enterprise Pty Ltd v State of New South Wales [2017] NSWSC 350.

Factual background

  1. [2]

    The salient facts may be summarised succinctly. The applicant, LDF Enterprise Pty Ltd, owns land at Bundabah in New South Wales, north of Newcastle. The OEH is conducting an investigation to determine whether any person has contravened s 86 of the National Parks and Wildlife Act 1974 (NSW). That section creates various offences involving the harming or desecration of Aboriginal objects and Aboriginal places.

  2. [3]

    Officers from the OEH have previously visited the site. There was evidence that on 9 June 2016, they accompanied an Office of Water investigation and a note records that they “observed potential breach of Native Vegetation Act which was brought to the attention of the owner”. A further visit was conducted on 10 August 2016, and a note records that “OEH officers observed potential breach of NPW Act”. A further visit occurred on 21 September 2016, and again on 23 March 2017.

  3. [4]

    There was correspondence between OEH and LDF Enterprise’s solicitor throughout this time, culminating in a letter dated 3 April 2017, which is reproduced in its entirety at [28] of the reasons of the primary judge. That letter referred to previous correspondence and stated that OEH intended to attend the premises from about 9.30am on 4 April 2017 to conduct an inspection. The letter named the officers proposed to attend and stated that “the power of entry to land for authorised officers is set out under s 196 of the Protection of the Environment Operations Act 1997”. Speaking generally, s 156B of the National Parks and Wildlife Act picks up and applies most of the provisions of Chapter 7 of the Protection of the Environment Operations Act to authorised persons and permits such persons to exercise those functions, relevantly for present purposes, “for determining whether there has been compliance with or a contravention of national parks legislation”: s 156B(2)(a). The letter gave particulars of the scope of the investigation and the intended inspection, confirmed that OEH was investigating potential offences under s 86(1), 86(2) and 86(4) of the National Parks and Wildlife Act 1974 but declined to specify the person or persons who were suspected of committing such offences or the date on which the offences were committed, those being matters “under active investigation”. The letter concluded:

  4. [5]

    Shortly before receiving that letter, and notwithstanding the extensive communications between the parties, LDF Enterprise filed a statement of claim and moved ex parte before the duty judge on 3 April 2017 seeking injunctive relief. That application was – unsurprisingly – refused, and instead short service was ordered and the matter stood over to 2pm on 4 April 2017. There was a short hearing that afternoon, following which the primary judge refused to grant the injunction sought. Her Honour gave reasons at 10am the following day.

  5. [6]

    In the meantime, by orders made on 6 April 2017 in this Court, an interim injunction up to and including 3 May 2017 (which is today) has been granted, and a concurrent hearing of the application for leave and the appeal has been directed.

Jurisdiction

  1. [7]

    The first question is whether the primary judge had jurisdiction to make the orders sought (and whether this court had power to grant an interim injunction). The “first duty” of a court is to determine whether it has jurisdiction: see Federated Engine-Drivers and Firemen’s Association of Australasia v Broken Hill Pty Co Ltd (1911) 12 CLR 398 at 415; Obeid v R (2015) 91 NSWLR 226; [2015] NSWCCA 309 at [9].

  2. [8]

    There is no issue as to the title of LDF Enterprise, nor its right to exclude a trespasser. There is no issue that officers of the OEH claim an entitlement to enter the land deriving from s 196 of the Protection of the Environment Operations Act 1997 (NSW). The issue arising before the primary judge, and sought to be reagitated in this Court, is whether the lawful authority relied upon by the OEH was vitiated by reason of an alleged failure to afford procedural fairness. The primary judge addressed jurisdiction at [49] in her reasons as follows:

  3. [9]

    Without intending to convey any criticism, given the urgency with which proceedings had been commenced, with which the defendant was required to respond, and in respect of which a decision was required of her Honour, it appears that her Honour was not as well assisted on this threshold question as she might have been.

  4. [10]

    Section 71 of the Land and Environment Court Act 1979 provides as follows:

  5. [11]

    Section 58 of the Land and Environment Court Act deals with appeals and is not relevant. Section 20(1)(e) identifies the general class of matters falling within “Class 4” of the jurisdiction of the Land and Environment Court, by reference to the proceedings referred to in subsection (2). That subsection provides as follows:

  6. [12]

    The “planning or environmental law” referred to is defined in subsection (3), by reference to a series of statutes, including the National Parks and Wildlife Act 1974 and the Protection of the Environment Operations Act 1997.

  7. [13]

    The consequence is that in respect of matters involving what may broadly be described as judicial review of the enforcement of rights, obligations or duties, or the exercise of functions, conferred or imposed by a wide range of planning or environmental laws, including the National Parks and Wildlife Act and the Protection of the Environment Operations Act, not only is jurisdiction invested in the Land and Environment Court, but that jurisdiction is exclusive of that of the Supreme Court. Proceedings answering that description may neither be commenced nor maintained in the Supreme Court.

  8. [14]

    Section 72 of the Land and Environment Court Act authorises the Supreme Court to transfer “proceedings commenced or purporting to have been commenced in the Supreme Court” which “could or should have been commenced” in the Land and Environment Court to that Court. That section does not apply to proceedings in, inter alia, Class 4 of the jurisdiction of the Land and Environment Court. However, s 149B of the Civil Procedure Act 2005 (NSW) confers power to do so, including on the Court’s own motion.

  9. [15]

    LDF Enterprise’s statement of claim seeks declarations that various entries onto its land would constitute trespasses and injunctions preventing officers of the OEH from entering onto the land without its consent. True it is that on the face of the statement of claim there is no reference to the statutory authority and the alleged obligation to accord procedural fairness on which LDF Enterprise’s case rests, which had been debated in the extensive correspondence between the parties. But the real issue between the parties, which was argued before the primary judge and in this Court, was whether there was an obligation to afford procedural fairness to LDF Enterprise before exercising the statutory function of entering onto the land, and, if so, whether that obligation was breached.

  10. [16]

    There are at least two ways in which the prohibitions in s 71(1) read with s 20(2) are attracted. The first is that the declaratory relief sought by LDF Enterprise, to the effect that various proposed entries onto its land and activities on the land “would, if carried out, constitute a trespass to the Land”, answers the description of a declaration of right in relation to a right, obligation or duty or the exercise of a function conferred by a planning or environmental law, within the meaning of s 20(2)(c).

  11. [17]

    The second is that the injunctive relief sought by LDF Enterprise all turns upon its claim that it was not accorded procedural fairness when the power under s 196 of the Protection of the Environment Operations Act was or was to be exercised. LDF Enterprise contended that the power under s 196 may only be exercised after first according procedural fairness to the landowner, and seeks injunctive relief to enforce the obligation or duty it claims is owed to it. Even if the obligation or duty to accord procedural fairness is better regarded as an incident of the common law rather than statute, it still falls naturally within the ordinary meaning of s 20(2)(a). That is because the issue in dispute concerns the limits of the statutory power.

  12. [18]

    It is no answer to either of the ways in which s 71(1) read with s 20(2) is engaged to say, as did Mr Larkin who appeared with Ms Byrne for LDF Enterprise, that the proceeding is “tortious” or alleges a cause of action in tort. The legislation does not speak in terms of causes of action, but instead refers to the concepts of enforcing, reviewing and commanding certain rights, obligations, duties or functions, and making declarations of right in relation thereto.

  13. [19]

    In Commissioner of Australian Federal Police v Propend Finance Pty Ltd (1997) 188 CLR 501 at 558, Gummow J observed that:

  14. [20]

    The same reasoning applies to the construction of s 20(2) of the Land and Environment Court Act, and the evident purpose of that provision, which is to entrust matters of that nature to the exclusive jurisdiction of that specialist court. The proceedings commenced by LDF Enterprise answer the description of the proceedings specified in s 20(2) of the Land and Environment Court Act. The only issue was the scope and nature of the power conferred upon OEH officers by s 196 of the Protection of the Environment Operations Act.

  15. [21]

    In reaching that conclusion, no question arises as to the principle of construction stated in Owners of “Shin Kobe Maru” v Empire Shipping Co Inc (1994) 181 CLR 404 at 421 as to the inappropriateness of reading provisions conferring jurisdiction upon courts by making implications or imposing limitations which are not found in the express words. Section 20(2) read with s 71 delineates an area of exclusive jurisdiction, conferring jurisdiction on one superior court of record and denying that same jurisdiction to another superior court of record. The principle has no operation.

  16. [22]

    It is not necessary to consider the position where part of a proceeding attracts the prohibition in s 71, but another part does not. This is a clear case. The whole of the case raised by LDF Enterprise falls within the section.

  17. [23]

    That is a threshold reason why it was inappropriate to grant any interlocutory relief.

Procedural fairness

  1. [24]

    If the primary judge lacked jurisdiction to deal with the matter, arguably this Court should do no more than record that conclusion. On the other hand, the way the parties presented the case to the primary judge and the correctness of the reasoning may affect orders as to costs, both below and in this Court. Further, if there were any doubt about the correctness of the conclusion as to jurisdiction, the need for an expeditious resolution of the dispute warrants this Court dealing with the substantive issues, if it is in a position to take that step. It is in that position because the parties have made written and oral submissions on a further question of law, which is whether there was an obligation to accord procedural fairness to the landowner before exercising the power of entry under s 196 of the Protection of the Environment Operations Act, in its operation as picked up by s 156B(2)(a) of the National Parks and Wildlife Act.

  2. [25]

    The primary judge said that she had “considerable reservations” about an obligation to accord procedural fairness. Her reasoning on this point at [42]-[43] was as follows:

  3. [26]

    Her Honour found, on the assumption that procedural fairness was required, that it had been given, and indeed that the contrary was “scarcely arguable”: at [46]. Her Honour also considered that the balance of convenience favoured declining relief.

  4. [27]

    Section 196 is the first section contained in Part 7.4 of the Act, which is headed “Powers of entry and search of premises”. The section provides:

  5. [28]

    LDF Enterprise pointed to the importance of a landowner’s right of exclusive possession: Plenty v Dillon (1991) 171 CLR 635, and to the requirement that “Statutory authority to engage in what otherwise would be tortious conduct must be clearly expressed in unmistakable and unambiguous language”: Coco v The Queen (1994) 179 CLR 427 at 436.

  6. [29]

    LDF Enterprise acknowledged that the obligation to accord procedural fairness could be excluded, but maintained that the Act did not sufficiently clearly do so. In Minister for Immigration and Border Protection v SZSSJ (2016) 259 CLR 180; [2016] HCA 29 at [75], the High Court framed the principle as follows:

  7. [30]

    For the reasons which follow, the statutory scheme clearly displaces the presumption that the power conferred by s 196 is conditioned by an obligation to accord procedural fairness.

  8. [31]

    Before identifying those reasons, however, it should be noted that there is, arguably, an antecedent question, namely whether any common law duty to accord procedural fairness is engaged. Generally, the obligation to accord procedural fairness is engaged only where there is a decision-making process which precedes the exercise of a power. For example, the powers of police officers to conduct investigations, arrest persons and obtain search warrants are not subject to any obligation to give the object of the proposed action an opportunity to be “heard” before the action is taken. An example may be found in the powers conferred on maritime officers to detain persons at sea and remove them to another place: CPCF v Minister for Immigration and Border Protection (2015) 255 CLR 514; [2015] HCA 1 at [51]-[53] (French CJ); [358]-[361] and [366]-[368] (Gageler J, Crennan J at [227] agreeing) and [500]-[503] (Keane J). The fact that there may be communications between an officer and another person prior to the exercise of the power, or that the person is given notice of the time and place at which a power may be exercised, are not circumstances which necessarily demonstrate an obligation to hear the person as to why the power should not be exercised. On that approach, the valid exercise of the powers of entry and inspection involved in this case were not conditioned upon any common law obligation to accord the owner of the property an opportunity to be heard as to why the power should not be exercised.

  9. [32]

    The alternative approach is that which underlay the submissions by LDF Enterprise, namely a consideration of whether, by implication if not expressly, the statutory provisions excluded the obligation to accord procedural fairness. It is convenient to turn to the reasons why, on that approach also, the applicant’s case fails.

  10. [33]

    First, s 196(1) is to be read as a whole. The subsection distinguishes between the power of entry “at any time” in paragraphs (a) and (b), where an authorised officer reasonably suspects any industrial, agricultural or commercial activities are being carried out or pollution occurring, and “at any reasonable time” in paragraph (c), which applies to all cases falling outside paragraphs (a) and (b). There is no scope for holding that the obligation to accord procedural fairness applies only to paragraph (c) and not paragraphs (a) or (b), and, to be fair, LDF Enterprise did not submit that it did. It is difficult to construe words of generality (“at any time”) as meaning “at any time, subject first to the landowner having been notified and given an opportunity to be heard”.

  11. [34]

    Secondly, s 196(3) in terms authorises the use of “reasonable force”. That is to say, it authorises entry where the occupier has not consented. The most likely circumstance for the need for reasonable force is that the occupier has not been notified in advance of the entry being effected. This accordingly tells against LDF Enterprise’s construction.

  12. [35]

    Thirdly, s 211(3), which is also in Chapter 7, provides:

  13. [36]

    For the same reasons, the presence of s 211(3) tells against LDF Enterprise’s construction. A likely occasion for wilful delay or obstruction is when a landowner has not received notice of entry.

  14. [37]

    Fourthly, Chapter 7 is entitled “Investigation”. The chapter commences with s 184, which is in the following terms:

  15. [38]

    The purpose of investigating compliance and contravention in legislation to protect the environment would not be furthered by qualifying the generally worded power of authorised officers to enter premises, so that it may only be exercised after notice has been given. It is easy to see how many investigations could be frustrated if notice were given (consider pollutants being discharged on occasion into waterways rather than in a more expensive lawful fashion). This Court is required to prefer a construction which promotes the purpose of the Act: Interpretation Act 1987 (NSW), s 33.

  16. [39]

    Fifthly, s 197 provides that the Part does not empower entry into residential premises without the permission of an occupier or the authority of a search warrant under s 199. Section 199 authorises search warrants to be issued generally in accordance with the Law Enforcement (Powers and Responsibilities) Act 2002 (NSW) where an authorised officer believes on reasonable grounds that the Act is being or has been contravened or that there is a matter or thing on the premises connected with an offence under the Act. Those provisions do not require notice to be given of the possible issuing of a warrant. Rather, s 65 of the latter statute gives the person the right to receive notice of a warrant at the time of entry or as soon as possible thereafter.

  17. [40]

    Although LDF Enterprise submitted that the regime required a warrant in all cases of nonconsensual entry onto residential premises and involving “independent judicial oversight”, there is some force in the submission advanced by Mr Hutley, who appeared with Mr Emmett for the State, that it would be incongruous if, in the case of entry into residential premises, there was no right to be heard in advance, but in the case of entry into non-residential premises, there was by implication sourced in s 196 a right to a greater level of notice. That incongruity tells against the construction for which LDF Enterprise contends.

  18. [41]

    Sixthly, s 189(2) qualifies the rights conferred upon authorised officers, including the right of entry. That subsection provides:

  19. [42]

    Once again, the terms of that provision tend to sit ill with the right only being exercisable after notice has first been given to the landowner. Further, this obligation, together with those in s 196(3) and s 211(3) referred to above, is suggestive of an analogy with the powers conferred on police officers. So too does the power of seizure conferred by s 198(2)(h) and (3) of things connected with offences. More generally, that analogy is strengthened by the law enforcement function of Chapter 7, at least in its application by s 156B(2)(a) of the National Parks and Wildlife Act.

  20. [43]

    In its written submissions, LDF Enterprise relied on this Court’s decision in D’Anastasi v Environment, Climate Change & Water (NSW) (2011) 81 NSWLR 82; [2011] NSWCA 374. That decision imposed minimal requirements upon the contents of a notice issued under s 193 requiring the production of information or records. The decision does not relevantly bear on the issue in the present case. A decision on the scope of the obligation to notify under a different section, in which notification is expressly required, does not assist the construction of s 196 which is silent as to notice.

  21. [44]

    For those reasons, the duty on which LDF Enterprise’s claim for interlocutory relief depends, does not exist. The requirement of unmistakable and unambiguous language is made out. The abrogation of the right to procedural fairness does not, contrary to the tenor of some of LDF Enterprise’s written submissions in reply, require express language. The question being one of law, and in light of the full submissions received from both sides in advance of the hearing, there is no utility in merely addressing this issue at the level of a serious question to be tried.

  22. [45]

    For that further reason, there was no error in the primary judge refusing interlocutory relief.

Other matters and orders

  1. [46]

    It is not necessary to address the balance of convenience, although it should be noted that an essential aspect of LDF Enterprise’s claim for equitable relief was that damages would not be adequate. LDF Enterprise repeatedly submitted in writing that if an injunction were not granted, its rights would be rendered nugatory. That submission tends to elide the obligation upon LDF Enterprise to demonstrate the inadequacy of its remedies at law.

  2. [47]

    In my view, although there should be a grant of leave to appeal, the appeal should be dismissed, with costs.

  3. [48]

    In accordance with s 71, the underlying proceeding should not have been commenced, and may not be maintained in the Supreme Court. However, the proceeding is not a nullity, and this Court had, at the very least, jurisdiction to determine whether its jurisdiction had been properly invoked: Re Macks; ex parte Saint (2000) 204 CLR 158; [2000] HCA 62; Berowra Holdings Pty Ltd v Gordon (2006) 225 CLR 364; [2006] HCA 32. It also had power to order costs: Proust v Blake (1989) 17 NSWLR 267 at 272; Khatri v Price (1999) 95 FCR 287.

  4. [49]

    It was conceded that if this Court reached the view that there was no obligation to accord procedural fairness, then there was nothing left in the case. Accordingly, the statement of claim should be dismissed, with costs. No order is necessary, but it follows also that the notice of motion which may have been filed seeking further interlocutory relief is dismissed.

  5. [50]

    The orders proposed are:

  6. [51]

    BASTEN JA: I agree with the orders proposed by Leeming JA and with his reasons.

  7. [52]

    MACFARLAN JA: I agree with the orders proposed by Leeming JA and, subject to one qualification, with his Honour’s reasons. The qualification is that I would base my conclusion concerning jurisdiction only on s 20(2)(c) of the Land and Environment Court Act and not express a view concerning the applicability of s 20(2)(a) to this case.