[2019] NSWCA 280
Visual Building Construction Pty Ltd v Armitstead (No 2)
Appeal dismissed with costs
Catchwords
CONTRACTS – termination – whether building contract validly terminated – whether in the circumstances, 10 business days notice giving opportunity to remedy default needed to be given prior to termination – alternative bases for termination – Shepherd v Felt & Textiles of Australia Ltd
Cases cited
- Batson v De Carvalho (1948) 48 SR (NSW) 417
- Burger King Corporation v Hungry Jack’s Pty Limited[2001] NSWCA 187
- L.Schuler AG v Wickman Machine Tool Sales Ltd[1973] UKHL 2; [1974] AC 235
- Shepherd v Felt & Textiles of Australia Ltd (1931) 45 CLR 359;[1931] HCA 21
- Tricontinental Corporation Ltd v HJFI Ltd(1990) 21 NSWLR 689
Legislation cited
- Environmental Planning and Assessment Act 1979 (NSW) § 109F(1A), 121B, 149E(1)(a)
- Local Government Act 1993 (NSW)
Judgment
[This headnote is not to be read as part of the judgment]
- [1]
BELL ACJ: This is an appeal from the decision of Sorby ADCJ (the primary judge) of 21 August 2018. His Honour entered judgment in the sum of $651,536 for Mr David Armitstead and Ms Maria-Luisa Patisso, the plaintiffs in the court below and the respondents in these proceedings. The primary judge also held that the respondents had validly terminated a twice varied building contract (the Contract) with Visual Building Construction Pty Ltd (the appellant) for the construction of two duplex buildings on a block of land in Caddens, NSW.
- [2]
In the only ground of appeal pressed, the appellant contended that the primary judge erred in finding that the Contract had been validly terminated.
- [3]
By notice of contention, the respondents argued that there were grounds additional to those relied upon by the primary judge which supported the valid termination of the Contract.
- [4]
In my opinion, the appeal should be dismissed. As will be seen, there were a number of distinct grounds by reference to which the Contract was validly terminated, and no error has been demonstrated in the judgment of the District Court.
- [5]
More fundamentally, however, the respondents’ claim was one for damages for breach of contract. Even if the Contract had not been validly terminated, it remained the case, and was not put in issue by the appellant, that the Contract had been breached most obviously, as shall be seen, by the failure of the appellant to obtain a Construction Certificate prior to commencement of the works, or at all. There was no challenge ultimately pressed to the primary judge’s assessment of damages for breach of contract, although this had been a ground in the Notice of Appeal. The availability of those damages did not depend upon termination of the Contract.
The Contract
Development consent
- [10]
By letter dated 24 June 2014 addressed to the second respondent, Penrith City Council enclosed a copy of a Development Consent and stamped approved plans. The letter advised that construction could not commence until such time as a Construction Certificate had been issued.
- [11]
Clause 6 of the conditions of Development Consent provided that “[a] Construction Certificate shall be obtained prior to commencement of the remaining building works.”
- [12]
Section 109F(1A) of the Environmental Planning and Assessment Act 1979 (NSW) (the Act), as it then was, provided that a Construction Certificate has no effect if it is issued after the building work or subdivision work to which it relates is physically commenced on the land to which the relevant development consent applies.
- [13]
It was not in issue that the appellant never obtained a Construction Certificate in respect of the works the subject of the Contract.
Variations to the Contract
- [14]
During 2014, the respondents complained to the appellant about what they considered to be problems arising during the construction of the dwelling, with such concerns including the size of the ensuite bathroom and the wrong size steel beam being used in this construction. The respondents complained to the Department of Fair Trading (the Department) in November 2014 about the lack of progress on the building.
- [15]
The Department issued a rectification order on 27 January 2015 (the rectification order).
- [16]
On the following day, the respondents and the appellant through its director, Mr Youssef Shehata (Mr Shehata), entered into a variation of contract by which the appellant agreed to comply with the rectification order and to fix all building defects as contained in an independent building report to be provided by the respondents.
- [17]
A second variation of the Contract was entered into on 18 May 2015 (the Varied Contract). Clause 13 of the Varied Contract contained a lengthy list of outstanding, incomplete or defective work as at 6 May 2015.
- [18]
Clause 3 of the Varied Contract provided that:
Notice of Intention to serve Order 19
- [19]
On 5 June 2015, the respondents received a Notice of Intention to serve an Order 19 (Order 19 Notice) pursuant to s 121B of the Act. That Notice relevantly provided:
- [20]
The terms of the Proposed Order were as follows:
- [21]
The reasons for the Proposed Order were stated to be as follows:
- [22]
The Order 19 Notice and terms of the Proposed Order were provided immediately to the appellant by the respondents.
- [23]
Notwithstanding this, no steps were taken by or on behalf of the appellant to obtain a Building Certificate or a Construction Certificate. It may be noted at this point that a Building Certificate, if obtained, would operate to preclude the Council from making an order or taking proceedings for the making of an order or injunction under the Act or the Local Government Act 1993 (NSW) requiring the building to be repaired, demolished, altered, added to or rebuilt: s 149E(1)(a) of the Act.
Termination of the Contract
- [24]
On 13 July 2015, the respondents issued a formal Notice of Termination of the Contract. Clause I of this document recited that:
- [25]
On 23 March 2017, the respondents commenced proceedings in the District Court of New South Wales seeking damages. The appellant put in issue in its defence the validity of the termination of the Contract.
- [26]
It should also be noted that, in late February 2018, the Council refused the respondents’ application for a Building Certificate in respect of the works that had been carried out as at the date of the termination. The Council’s reasons for refusing to issue a Building Certificate were that:
- [27]
Further, on 1 March 2018, the Council issued a demolition order in respect of the work that had been unlawfully undertaken by the appellant.
Proceedings at first instance
- [28]
The essence of the appellant’s defence in the proceedings at first instance was that the termination of the Contract was defective because it was said that cl 15 of the Contract, extracted above at [9], required 10 business days to be provided to remedy defaults before the Contract could be terminated, and that the Notice of Termination had not allowed this period, or indeed any period of time, to remedy the alleged defaults.
- [29]
In rejecting this argument, the primary judge held at [23] that “[t]echnically it would not have been possible for the [appellant] to remedy faults as the completion date for the project on 2 July 2015 had passed.” He went on to hold at [24] of the judgment that:
Arguments on appeal and notice of contention
- [30]
The appellant in substance repeated its unsuccessful argument at first instance that the termination was not valid because 10 business days’ notice had not been given to remedy the defaults detailed in the Notice of Termination.
- [31]
To the extent that cl 15 of the Contract imposed any requirement to give 10 business days’ notice prior to termination, such a requirement only applied if the default was capable of being remedied within 10 business days. Clause 15 did not require termination of the Contract to be delayed by 10 business days where to do so would not have achieved a remedying of defaults. The primary judge’s finding, set out at [29] above, was a finding that a particular default relied upon in the Notice of Termination was incapable, as a matter of fact, of being remedied within that period. The appellant was critical of the primary judge’s reference to the events of 2018 to support his factual conclusion in relation to the validity of the termination in 2015, as set out at [29] above.
- [32]
In my opinion, it was quite legitimate for the primary judge to draw on the Council’s 2018 refusal to grant a Building Certificate to fortify his factual conclusion that at least one of the defaults of the appellant relied upon to justify the termination of the Contract on 13 July 2015 was incapable of being remedied. It is perfectly plain from the terms of the Council’s 2018 refusal to issue a Building Certificate, noted in [26] above, that that refusal related to the state of the building work that had been done at the time of termination of the Contract, as opposed to some subsequent deterioration in the intervening period between termination and the 2018 refusal to grant the Building Certificate.
- [33]
Moreover, the fact that the appellant took no steps from 5 June 2015 to 13 July 2015 to seek to address the Proposed Order and the requirement to obtain a Construction Certificate for the balance of the works supported the conclusion that it would not have been possible to obtain a Construction Certificate within a 10 business day period. Given that, under the Varied Contract, the appellant only had 4 weeks from 8 June 2015, ie. until 6 July 2015 to complete the works, and as it was unlawful to continue construction until such time as a Construction Certificate had been obtained, one would have expected the appellant to obtain a certificate as quickly as possible after the Order 19 Notice had been issued, in order to give itself the best opportunity to complete the works by the revised completion date. That the appellant did not do so strongly suggests that it did not think that it could be done (or that it could be done and the outstanding works completed within the necessary time frame).
- [34]
In addition to this, it was never possible to remedy the fact that a Construction Certificate was required prior to commencement of construction: see s 109F(1A) of the Act and [12] above.
- [35]
That having been said, however, it may well have been the case that the issue of a Building Certificate in respect of the unauthorised works (which would have the effect under s 149E(1)(a) of the Act, identified in [23] above) together with the obtaining of a Construction Certificate in relation to the balance of the work under the Contract would have amounted to a remedying in substance (so long as it could be achieved within 10 business days). This is despite the fact that, technically, the failure to obtain a Construction Certificate prior to commencement was a “once and for all” breach which was never capable of being remedied: cf. Burger King Corporation v Hungry Jack’s Pty Limited [2001] NSWCA 187 at [113]-[124] where, in a passage of the joint judgment that is not reported at (2001) 69 NSWLR 558 and which was strictly obiter, the Court of Appeal, citing Batson v De Carvalho (1948) 48 SR (NSW) 417; L.Schuler AG v Wickman Machine Tool Sales Ltd [1973] UKHL 2; [1974] AC 235; and Tricontinental Corporation Ltd v HJFI Ltd (1990) 21 NSWLR 689, endorsed the view that a “once and for all breach”, such as the failure to comply with a time provision, was nevertheless capable of being cured.
- [36]
It is not necessary to provide a definitive answer to that issue in this case (which did not involve non-compliance with a time provision) as the primary judge found, as I have pointed out, that the particular default was incapable of being cured within a 10 business day period as a matter of fact, and that finding has not been assailed.
- [37]
More fundamentally, as I have pointed out at [5] above, it is not necessary to answer this question given the existence of undoubted breaches of the Contract and the absence of any challenge to the award of damages. That award, and the availability of damages, did not depend upon the termination of the Contract.
- [38]
Even if, contrary to this point, termination was in truth relevant, it is plain, in my opinion, that by not taking any step to obtain either a Building or a Construction Certificate following the Order 19 Notice on 5 June 2019, the appellant repudiated the Contract. That repudiation was accepted by the respondents’ conduct in terminating the contract on 13 July 2015 and, if not by that date, certainly by the commencement of proceedings in the District Court on 23 March 2017. In this context, the termination of a Contract on an available ground, even if not expressly relied upon, will still be valid: Shepherd v Felt & Textiles of Australia Ltd (1931) 45 CLR 359 at 377; [1931] HCA 21.
- [39]
In my opinion, the appeal should be dismissed with costs.
- [40]
MACFARLAN JA: I agree with Bell ACJ.
- [41]
WHITE JA: I agree with Bell ACJ.