[2022] NSWSC 624
Goodwin Street Developments Pty Ltd atf Jesmond Unit Trust v DSD Builders Pty Ltd (in liq)
Second defendant liable to pay damages to plaintiff
Catchwords
BUILDING AND CONSTRUCTION – malicious damage to property – action for trespass – standing of plaintiff to bring action for trespass – whether plaintiff had exclusive possession of the property – whether plaintiff entitled to recover loss for damage to the reversion – measure of damages for damage to the reversion – whether second defendant caused the malicious damage – whether second defendant carried out construction work for the purpose of the Design and Building Practitioners Act 2020 (NSW) – whether second defendant acted in breach of his statutory duty of care under that Act in relation to that construction work
Cases cited
- Beaudesert Shire Council v Smith (1966) 120 CLR 145;[1966] HCA 49
- Birtchnell v Fred Walker & Co Pty Ltd (1930) Argus LR 176
- Bowen Investments Pty Ltd v Tabcorp Holdings Ltd (2008) 166 FCR 494;[2008] FCAFC 38
- Briginshaw v Briginshaw (1938) 60 CLR 336;[1938] HCA 34
- Concrete Constructions (NSW) Pty Ltd v Australian Building Construction Employees’ and Builders’ Labourers’ Federation (1988) 83 ALR 385;[1988] HCA 485
- De Gruchy v The Owners – Units Plan No 3989[2020] ACTSC 65
- Gagner Pty Ltd t/as Indochine Cafe v Canturi Corporation Pty Ltd[2009] NSWCA 413
- Georgeski v Owners Corporation – Strata Plan 49833 (2004) 62 NSWLR 534;[2004] NSWSC 1096
- Goodrich Aerospace Pty Ltd v Arsic (2006) 66 NSWLR 186;[2006] NSWCA 187
- Jones v Dunkel (1959) 101 CLR 298;[1959] HCA 8
- Jones v Llanrwst Urban District Council (1911) 1 Ch 393
- Joyner v Weeks [1891] 2 QB 31
- Livingstone v Rawyards Coal Co (1880) 5 App Cas 25
- Pollack v Volpato [1973] 1 NSWLR 653
- Shelfer v City of London Electric Lighting Company [1895] 1 Ch 287
- Shell Company of Australia Ltd v Bailey & Drysdale[1980] WAR 233
- Smiley v Townshend [1950] 2 KB 311
- Société d'Avances Commerciales (Société Anonyme Egyptienne) v Merchants' Marine Insurance Co [1924] 20 Ll L Rep 140
- Uren v John Fairfax & Sons Pty Ltd (1966) 117 CLR 118;[1966] HCA 40
Legislation cited
- Building Products (Safety) Act 2017 (NSW)
- Community Land Management Act 2021 (NSW)
- Corporations Act 2001 (Cth)
- Design and Building Practitioners Act 2020 (NSW)
- Design and Building Practitioners Regulation 2021 (NSW)
- Environmental Planning and Assessment Act 1979 (NSW)
- Evidence Act 1995 (NSW)
- Home Building Act 1989 (NSW)
- Local Government Act 1993 (NSW)
- Strata Schemes Management Act 2015 (NSW)
Judgment
- [1]
The plaintiff, Goodwin Street Developments Pty Ltd is the owner of land in Jesmond, New South Wales, located close to the campus of the University of Newcastle.
- [2]
On 10 July 2017, Goodwin entered into a building contract with the first defendant, DSD Builders Pty Ltd, to construct three residential boarding houses, intended for university student accommodation, on the site.
- [3]
DSD, now in liquation, was a company whose sole director, Ms Angela Sendjirdjian, was the fiancée (and later wife) of the second defendant, Mr Daniel Roberts.
- [4]
Goodwin alleges that Mr Roberts was the representative of DSD who negotiated the building contract with Goodwin, that Mr Roberts administered the building contract on behalf of DSD and controlled the carrying out of the construction work on the site on behalf of DSD.
- [5]
At the time the works commenced in July 2017, DSD employed a licensed supervisor at the site, Mr Stuart Johnstone. However, when Mr Johnstone left the employment of DSD in late August 2017, he was not replaced and, Goodwin contends, the work was thereafter supervised only by Mr Roberts.
- [6]
In early 2018, disputes arose between Goodwin and DSD relating to defective building works and the progress of the works (among other matters).
- [7]
On 2 March 2018, there was a “site meeting” between Mr Roberts, directors of Goodwin, including Mr Jeffrey Stokes, and persons claiming to represent creditors of Mr Roberts. At this meeting, the creditors’ representatives made demands and threats concerning money allegedly owing to their clients by Mr Roberts. I return to this below.
- [8]
Later on 2 March 2018, Goodwin served a Notice to Remedy Defaults on DSD pursuant to the building contract.
- [9]
DSD did no further work at the site after 2 March 2018.
- [10]
On 19 March 2018, Mr Stokes attended the site and observed substantial damage to the buildings on the site and that doors, windows, stairs and other items that had previously been installed in the buildings were missing. Mr Stokes reported the matter to the police.
- [11]
Also on 19 March 2018, Goodwin served a notice on DSD terminating the building contract with immediate effect.
- [12]
Goodwin commenced these proceedings against DSD in August 2018. Mr Roberts was added as a second defendant on 11 April 2019.
- [13]
In early 2021, DSD was ordered to be wound up in insolvency and a liquidator was appointed. The proceedings against DSD have been stayed since that time by operation of s 471B of the Corporations Act 2001 (Cth).
- [14]
What remains to be determined are the claims made by Goodwin against Mr Roberts.
- [15]
Goodwin claims that Mr Roberts:
- [16]
Goodwin claims some $586,000 from Mr Roberts on account of the first claim, being the cost of making good the damage caused to the site in March 2018; and some $300,000 from Mr Roberts being the cost to rectify the building defects. There is no dispute about these figures.
- [17]
Mr Roberts did not serve an affidavit and did not give evidence in response to Goodwin’s claims.
Decision
- [18]
I find that Mr Roberts did cause the damage and did remove the material the subject of Mr Stokes’s observations.
- [19]
I find that Mr Roberts did carry out “construction work” for the purposes of s 36 of the DBP Act and acted in breach of his duty of care under s 37 of that Act.
- [20]
Accordingly, Mr Roberts is liable to pay Goodwin the cost of making good the damage and the cost to rectify the defects.
The damage caused at the site in March 2018
- [21]
There is no dispute that between 2 and 19 March 2018 someone maliciously damaged the development works at the site, and removed materials, fixtures and fittings.
- [22]
The damage and the removed items are described in an Excel spreadsheet prepared by Mr Todd Corbett, a quantity surveyor who was also the contract administrator of the project.
- [23]
The damage included:
- [24]
The items missing included:
- [25]
As I have said, there is no dispute that the cost to repair the damage and replace the missing items is in the order of $586,000.
Goodwin’s standing to sue for trespass
- [26]
It is Goodwin’s case that this damage was caused by Mr Roberts.
- [27]
Goodwin alleges that Mr Roberts is, relevantly, “liable to Goodwin in trespass to land”.
- [28]
Goodwin claims that Mr Roberts “is liable to pay damages to Goodwin for the cost of rectifying the damage done” to the works and “for the cost of replacing the converted materials, fixtures and fittings”.
Was Goodwin entitled to exclusive possession of the Land at the time the damage was done and items removed?
- [29]
Mr Kidd SC, who appeared for Goodwin, submitted that Goodwin had, at the relevant time, a right to exclusive possession of the site and was thereby entitled to bring proceedings for trespass. [1]
- [30]
Consideration of whether, at the relevant time, Goodwin was entitled to exclusive possession of the site requires consideration of the terms of the building contract between Goodwin and DSD.
- [31]
In Item 3 of Schedule 1 of the contract, under the heading “Contract Information”, it was stated that Goodwin would not “remain in occupation” of the site.
- [32]
The contract also provided that:
- [33]
The contract provided that if, contrary to the situation here, Goodwin did “remain in occupation” then the reference in these provisions to “possession” would be replaced with the words “access to”. [10]
- [34]
The contract thus made reference both to the concepts of “occupation” and to “possession”. Goodwin was not to be in “occupation”; and was to give DSD “possession”.
- [35]
Morling J considered a contract containing similar provisions in Concrete Constructions (NSW) Pty Ltd v Australian Building Construction Employees’ and Builders’ Labourers’ Federation [11] and concluded:
- [36]
Nonetheless, Mr Kidd submitted that “what was granted under the Building Contract was a contractual right for DSD to occupy the Site during the Building Contract for the purpose of carrying out the works” [13] but that this was “not a right to exclusive possession”; and that Goodwin “remained entitled to exclusive possession”.
- [37]
Mr Kidd pointed out that whereas the contract in this case obliged Goodwin to give DSD “possession” of the site, the corresponding provision in Concrete Constructions provided that “the builder shall, upon the proprietor making the site available to him, have legal possession of the site for the purpose of carrying out his obligations under this agreement ...” (emphasis added). [14]
- [38]
I see that as being a distinction without a difference.
- [39]
Mr Kidd did not otherwise explain how his submission could be reconciled with the terms of the contract to which I have referred.
- [40]
DSD remained contractually entitled to possession of the site until Goodwin terminated the contract on 19 March 2018 and thereby became entitled to retake possession of the site pursuant to the provision to which I have referred at [32(e)] above.
- [41]
In those circumstances, I think Ms Chan, who appeared with Dr Lim for Mr Roberts, was correct to submit that, at the time the damage was done to the property, Goodwin was not entitled to exclusive possession of the site.
Goodwin’s rights as a reversioner
- [42]
In those circumstances, Ms Chan submitted:
- [43]
The implication of Ms Chan’s submission is that as DSD took no action in relation to the trespass while it did have exclusive possession, Goodwin, as the owner of the site, is without a remedy.
- [44]
That would be a strange result.
- [45]
It does not, in my opinion, reflect the correct legal position.
- [46]
Although Goodwin did not have exclusive possession of the site at the time the damage was done to its property in March 2018, it was a reversioner by reason of the fact it would, in due course (whether because the works were completed or because it exercised entitlement to retake possession) become entitled to exclusive possession of its property.
- [47]
In the circumstances that existed when the damage was done, Goodwin was in a position very shortly to obtain exclusive possession of the site and thus fall into possession of the reversion. It did so a number of days later, on 19 March 2018, when it terminated the building contract, and re-took possession.
- [48]
A reversioner, including a lessor who has leased its property to a lessee, or an owner who has temporarily given another (such as a builder) exclusive possession of its property, is entitled to bring “an action on the case for trespass” or an action “of trespass on the case”, [15] if during that other person’s possession of the property, a trespass occurs resulting in “permanent injury to the reversion”, [16] or that will “necessarily affect the reversioner’s interest when the property falls into possession”. [17]
- [49]
Permanent injury to the reversion in this context means “such as will continue indefinitely unless something is done to remove it”. [18]
- [50]
The “injury” done on the site in this case was thus “permanent” in this sense.
- [51]
Ms Chan submitted that the measure of damages to permanent injury to the reversion is the diminution in the value of the reversionary interest [19] and that she was not in a position to meet such a case. In any event, Goodwin had not adduced evidence of any diminution in value to its property. Rather, its evidence was directed to the cost of repair.
- [52]
However, the fundamental objective of an award for damages in tort is to provide “that sum of money which will put the party who has been injured … in the same position as he would have been in had he not sustained the wrong for which he is now getting his compensation or reparation”. [20]
- [53]
If, as here, the injured party is entitled to regain possession of the reversion shortly after the damage was done, the cost of repairs will better represent that “sum of money” than may be the case where the injured party is not able to retake possession for a lengthy period following the infliction of the damage. [21]
- [54]
I am satisfied that the appropriate measure of Goodwin’s loss for the damage done to the property is the reasonable cost of repairing the damage.
- [55]
As I have said, there is no controversy about what that reasonable cost is.
Did Mr Roberts cause the damage?
- [56]
To prove that it was Mr Roberts who caused the damage to and removed items from the site, Goodwin relies on the evidence of Mr Stevo Konjarski.
- [57]
Mr Konjarski is a scaffolder and leading hand employed by Star and Sons Group Pty Ltd, a company that provided scaffolding services to the project.
- [58]
Mr Konjarski’s affidavit was short and in the following terms:
- [59]
Ms Chan submitted that Mr Konjarski’s evidence was “unreliable, highly improbable and ought not to be accepted”.
- [60]
I am conscious of the restraint I should exercise in forming a view about the credibility of a witness based on the witness’s demeanour when giving evidence. Giving evidence is a stressful, alien experience for most people. I have in mind Atkin LJ’s familiar aphorism that “an ounce of intrinsic merit or demerit in the evidence, that is to say, the value of the comparison of the evidence with known facts, is worth pounds of demeanour”. [22]
- [61]
I must weigh my impressions as to demeanour “carefully against the probabilities” and “examine whether the disputed evidence is consistent with the incontrovertible facts”. [23]
- [62]
Here, Mr Konjarski’s evidence is “consistent with the incontrovertible acts” in as far as there is no dispute that someone caused the damage to the site of which Goodwin complains. But otherwise, there are no “known facts” by reference to which Mr Konjarski’s recollection may be tested.
- [63]
Mr Konjarski said the reason he was at the site on the day in question was that he was removing scaffolding from the rear of the three buildings on the site and that he needed to speak to Mr Roberts from time to time to obtain instructions about that process. Ms Chan drew attention to photographs taken on 13 March 2018 which showed no scaffolding on the site and compared those with photographs taken on 19 February 2018 “where there is still scaffolding” on the building nearest the road and submitted that “the Court may draw the inference that all of the scaffolding was removed in the period between 19 February and 13 March 2018”. However, the photographs taken on 13 March 2018 were taken by Mr Corbett’s staff after the works had been damaged. They were tendered by Goodwin to show that damage. There was thus no evidence as to the state of the scaffolding that contradicts Mr Konjarski’s evidence.
- [64]
In cross-examination, Mr Konjarski both qualified and added to the account he gave in his affidavit.
- [65]
The most significant addition Mr Konjarski gave to his affidavit account was to state that Mr Roberts did not act alone. Mr Konjarski said “he had other people with him” who Mr Konjarski identified as “his partner, and also his accountant”. Mr Konjarski said that all three of these people were involved in the removal of items from the site, and the loading of them into a vehicle parked on the street adjacent to the site.
- [66]
Ms Chan criticised the reliability of this evidence from Mr Konjarski. However, he gave this evidence in response to Ms Chan’s question as to whether Mr Roberts was present “alone”.
- [67]
That evidence unfolded this way:
- [68]
In the course of cross-examination, Mr Konjarski qualified and confined his account of what he observed Mr Roberts to do.
- [69]
Ultimately, Mr Konjarski’s account was that he saw Mr Roberts, in the company of his business partner and accountant:
- [70]
Mr Konjarski said he saw the “accountant” drive the laden one tonne ute away from the site.
- [71]
The same type of damage (cement poured in pipes and holes in the walls) and removal of items (stairs, doors and windows) that Mr Konjarski alleged he had seen Mr Roberts engage in was also observed by Mr Stokes and Mr Corbett when they attended the site on 19 March 2018, and had been observed by members of Mr Stokes’s staff earlier, on 13 March 2018.
- [72]
Thus, Mr Konjarski’s evidence as to what he saw is consistent with that other unchallenged evidence.
- [73]
As I have said, Ms Chan criticised Mr Konjarski’s evidence and submitted that he was an unreliable witness whose evidence should not be accepted.
- [74]
Ms Chan pointed to the fact that Mr Konjarski could not be certain as to precisely on what date he attended the site, and that there were the discrepancies between his affidavit account and his evidence in cross-examination that I have described, particularly as to the presence of Mr Roberts’s “business partner” and “accountant”, the “accountant’s” role in driving the one tonne ute away from the site and the more limited account given by Mr Konjarski as to what he allegedly saw Mr Roberts do.
- [75]
Ms Chan also pointed out that there was bad blood between Mr Konjarski and Mr Roberts. Mr Konjarski readily agreed that it was his position that Mr Roberts owed him some $66,000 and that in July 2021 he had entered a plea of guilty to a charge of assaulting Mr Roberts.
- [76]
But Mr Konjarski gave this evidence without hesitation, and appeared to me to be very confident as to the accuracy of his recollection. The evidence he gave was about matters in respect of which he could not be mistaken. He was either telling the truth or giving evidence he knew to be false.
- [77]
The conduct of Mr Roberts, as described by Mr Konjarski, was serious indeed. To accept it, I must have an “actual persuasion” of the mind that it is probably correct, bearing in mind the gravity of the matters alleged. [24]
- [78]
As I have mentioned, Mr Roberts did not give evidence. Accordingly, I may infer that Mr Roberts’s evidence will not have assisted his case. [25]
- [79]
It does not necessarily follow that I should accept Mr Konjarski’s evidence. However, as Mr Roberts has not given evidence, and as no explanation has been offered for his absence from the witness box, I may more comfortably draw such inferences, adverse to his interest, as are otherwise available.
- [80]
As I have mentioned, on 2 March 2018, Goodwin served on DSD a notice pursuant to the building contract alleging that DSD had failed to meet identified “substantial obligations” under the contract and requiring that those matters be remedied.
- [81]
Within an hour of the delivery of that notice, Mr Roberts wrote to Mr Stokes:
- [82]
Mr Roberts was clearly unhappy with Goodwin’s decision to serve the 2 March 2018 notice. That provides some, although I accept slender, evidence of a matter that may have motivated Mr Roberts to behave in the manner described by Mr Konjarski.
- [83]
Ms Chan submitted that it was more likely that the damage done to the site was caused by one or other of the persons who attended the 2 March 2018 “site meeting” to which I have referred.
- [84]
On 3 March 2018, Mr Stokes wrote to Senior Constable Michael Rowe about what had occurred at the “site meeting”. There is also in evidence what purports to be a transcript of a recording of a 30 minute conversation involving, among others, Mr Stokes, two other representatives of Goodwin, Mr Dale Dawson and Mr Nigel Archer, and three men each unidentified but described as a “money lender”.
- [85]
Mr Stokes emailed a transcript of the “site meeting”, and some “still shots of the guys” to Senior Constable Rowe:
- [86]
Evidently, the Police were unable to take any action in relation to the matters the subject of Mr Stokes’s report to Senior Constable Rowe.
- [87]
I cannot see upon what basis I could infer that one or more of the three “money lenders” who attended the 2 March 2018 “site meeting”, or their agents or associates, caused the damage to the site of which Goodwin complains.
- [88]
For one thing, according to the transcript of the “site meeting” the threat that was made during the meeting was that if Mr Roberts did not pay the “money lenders” the amount said to be due, they would “just get a 30 tonne dozer and … just doze the [expletive deleted] lot”. That is not what happened.
- [89]
Having observed Mr Konjarski in the witness box, and having regard to all the other circumstances I have set out above, I do have an actual persuasion of the mind that Mr Konjarski was telling me the truth as to what he observed on the day in question.
- [90]
I feel more readily able to come to that conclusion, in circumstances where Mr Roberts did not give evidence to dispute Mr Konjarski’s account.
- [91]
Accordingly, I find that the damage to Goodwin’s property was done by Mr Roberts, in company with the other persons who Mr Konjarski identified, and that he is liable to pay Goodwin the cost of repairing the damage.
Exemplary damages?
- [92]
Mr Kidd submitted, although ultimately with not great enthusiasm, that I should also order that Mr Roberts pay exemplary damages to Goodwin on the basis of the “reprehensible” or “high-handed” or “outrageous” nature of Mr Roberts’s conduct. [26]
- [93]
Mr Kidd pointed out that exemplary damages had been awarded in cases involving the tort of trespass to land. [27]
- [94]
Mr Kidd did not make a submission as to the amount of exemplary damages that should be made.
- [95]
I am not persuaded that I should make an order for exemplary damages. The Court’s mark of its disapproval of Mr Roberts’s conduct will be adequately made by an order that Mr Roberts pay the cost of the repairs and interest on that amount.
Mr Roberts’s alleged breach of statutory duty of care
- [96]
Goodwin claims that Mr Roberts was a person who carried out “construction work” within the meaning of s 37 of the DBP Act and that Mr Roberts acted in breach of his duty to exercise reasonable care to avoid economic loss caused by defects in the building of the site arising from the construction work.
- [97]
Section 37(1) of the DBP Act is in the following terms:
Does the statutory duty of care arise in relation to a boarding house?
- [98]
The building constructed on the site was a boarding house.
- [99]
Ms Chan submitted that the statutory duty of care under s 37(1) of the DBP Act does not extend to “construction work” carried out on a boarding house.
- [100]
For the reasons that follow, I do not agree.
- [101]
Resolution of the question involves consideration of the labyrinthine provision of s 36 of the DBP Act. The section appears to have been drafted so as to make comprehension of it as difficult as possible.
- [102]
Section 36 provides, relevantly:
- [103]
As can be seen, the definitions in s 36(1) incorporate by reference definitions from five other Acts: the Community Land Management Act 2021 (NSW), the Environmental Planning and Assessment Act 1979 (NSW), the Building Products (Safety) Act 2017 (NSW), the Home Building Act 1989 (NSW) and the Strata Schemes Management Act 2015 (NSW).
- [104]
Such a drafting technique, evidently used to achieve some kind of uniformity between the various statutes, renders construction of the section fiendishly difficult.
- [105]
Two of the Acts whose definition has been incorporated by reference, the Environmental Planning and Assessment Act 1979 (NSW) (the “EPAA”) and the Home Building Act 1989 (NSW) (the “HBA”) are relevant here.
- [106]
When introducing the amendments which gave effect to the current definitions of “building” and “building work” contained in the DBP Act, Mr David Shoebridge, moving “The Greens amendments”, stated:
- [107]
The duty under s 37 is in respect of “construction work”. In order that work be “construction work” it must, relevantly here, be “building work”.
- [108]
Thus, s 36(1) defines “construction work” to mean, relevantly, either:
- [109]
“Building work” is defined, generally, in s 4 of the DBP Act to mean, relevantly, “… the construction of a building of a class prescribed by the regulations for the purposes of this definition”.
- [110]
Regulations have been promulgated under s 4 of the DBP Act: Design and Building Practitioners Regulation 2021 (NSW). Mr Kidd and Ms Chan agreed, albeit for different reasons, that this regulation does not affect the meaning of “building work” for present purposes.
- [111]
Mr Kidd submitted that, on the proper construction of the DBP Act, the definition of “building work” in s 4 has no application to Pt 4 of the DBP Act.
- [112]
I agree.
- [113]
Part 4 of the DBP Act commenced on 10 June 2020, when the DBP Act was assented to. It is given retrospective operation by cl 5 of Sch 1 of the DBP Act. On the other hand, Pts 2, 3 and 5 to 9 of the DBP Act did not commence until 1 July 2021, [29] which was the same date on which the Design and Building Practitioners Regulation commenced. As Mr Kidd submitted, the statutory regime can only be seen to operate coherently if the s 4 definition of “building work” is interpreted as applying to the parts of the DPB Act that commenced on 1 July 2021, but not applying to Pt 4, which commenced on 10 June 2020 with retrospective operation.
- [114]
That interpretation is confirmed by the fact that, as I have set out, s 36(1) contains its own definition of “building work” expressed to be that applicable “in this Part”: that is, in Pt 4 of the DBP Act. This definition is qualified by s 36(2) of the DBP Act.
- [115]
Thus, s 36(2) provides that:
- [116]
The underlined reference to “building” must be a reference to the definition of “building” in s 36(1) which states that “building” “has the same meaning as it has” in the EPAA.
- [117]
“Building” is defined in s 1.4 of the EPAA as including:
- [118]
A boarding house is a “building” within that definition.
- [119]
Thus, by reason of the operation of s 36(2) and the definition of “building” in s 36(1), Pt 4, including s 37, applies to “building work”, and thus “construction work”, in relation to a boarding house.
- [120]
Despite s 36(2) stating that “building work” is “only” such work “relating to a building within the meaning of this Part”, s 36(1) defines “building work” as also including “residential building work” for the purposes of the HBA.
- [121]
Thus, as I have set out above, s 36(1) provides that:
- [122]
It is hard to see what this adds to the effect of Pt 4. As I have said, s 36(2) provides that in Pt 4 a reference to “building work” applies “only” to “building work” relating to a “building” within the meaning of this Part: that is, as defined in the EPAA.
- [123]
The effect of the definition of “building work” in s 36(1) is to include in “building work” so defined, “residential building work” within the meaning of the HBA.
- [124]
The effect appears to be that to the extent that “residential building work” under the HBA is also work relating to a “building” as defined in the EPAA, it comes within the ambit of Pt 4 of the DBP Act. Whether any practical consequence flows from this is hard to fathom.
- [125]
For present purposes, Ms Chan’s point was that under the HBA “residential building work” means, relevantly, work involved in “the construction of a dwelling”, [31] but that under the HBA a “dwelling” does not include “a boarding house”. [32]
- [126]
But it does not follow from this that work in relation to a “boarding house” is not “building work” for the purpose of Pt 4 of the DBP Act.
- [127]
That is because the definition of “building work” in s 36 of the DBP Act is an inclusive, not an exclusive, definition. The fact that a “boarding house” is not a “dwelling” within the meaning of the HBA and thus that construction of a boarding house is not “residential building work” for the purposes of the HBA merely means that work in relation a boarding house is not for the purposes of the DBP Act “building work” by reason of any provision in the HBA, insofar as those provisions are incorporated by reference into Pt 4 of the DBP Act.
- [128]
Ms Chan developed an elaborate argument that she described as a “write back” argument.
- [129]
As best I understood it, the argument was to the effect that, by reason of the imperative terms of s 36(2) of the DBP Act, there is a tension between:
- (1)
the provision in s 36(1) that for the purposes of the DBP Act “building” has the same meaning as it has in the EPAA (and therefore does not include a manufactured home or a moveable dwelling) on the one hand; and
- (2)
the provision in s 36(1) that “building work” includes “residential building work” for the purposes of the HBA (which would, in very limited circumstances, include or “write back” work in relation to a manufactured home or moveable dwelling) on the other.
- (1)
- [130]
Assuming such a tension exists, and that the combined effect of s 36(2) and the definitions incorporated by reference by s 36(1) is to “write back” some work as “building work” that would otherwise be excluded, I cannot see how this has any bearing on the question of whether or not Pt 4 of the DPB Act applies to a boarding house.
Was Mr Roberts engaged in “construction work”?
- [131]
Ms Chan accepted that the evidence showed that Mr Roberts had engaged in the “project management” of the construction on Goodwin’s site and thus engaged in “construction work” for the purposes of s 36(1) of the DBP Act to that extent.
- [132]
However, the evidence shows that Mr Roberts did not only engage in “project managing” but that he also supervised DSD’s construction of the relevant project.
- [133]
Mr Stokes gave unchallenged evidence that, at the outset of the works, Mr Roberts introduced himself as “the builder” of the project.
- [134]
Mr Stokes gave this further evidence:
- [135]
Further, Mr Corbett gave unchallenged evidence that:
- [136]
Mr Stokes and Mr Corbett gave evidence of numerous occasions on which they enquired of Mr Roberts about defects in the construction works and were given responses from Mr Roberts to the effect of “don’t worry about it’ll all be fixed”, “yeah we’ll get to it. Don’t panic about it all defects will be fixed” and “don’t worry about, it’ll get fixed”.
- [137]
From these responses alone, in the absence of any evidence from Mr Roberts about this matter, I am comfortably able to draw an inference consistent with the other evidence to which I have referred that Mr Roberts was not only engaging in project management of the site but also in supervision of the construction.
- [138]
He was therefore engaging in “construction work” for the purposes of Pt 4 of the DBP Act.
Were the defects caused by a want of care by Mr Roberts?
- [139]
There is evidence that the following defects exist:
- (1)
missing stormwater pipe;
- (2)
exposed unsupported pier footing;
- (3)
termite protection system not installed;
- (4)
no recess for vanity;
- (5)
external steel not hot dip galvanised;
- (6)
internal steel not painted;
- (7)
laundry window missing and incorrectly sized doors installed;
- (8)
windows in bathrooms in incorrect places;
- (9)
windows in kitchenette in incorrect places;
- (10)
frame built on sewer pipe;
- (11)
no step down from concrete slab;
- (12)
black mould on timber frames;
- (13)
loose bracing;
- (14)
floor sheeting moves up and down;
- (15)
wet area wall lining not fixed as required;
- (16)
waterproofing to showers;
- (17)
wrong board used on fascia;
- (18)
brick retaining wall not waterproofed;
- (19)
sliding door tracks not flush with floor;
- (20)
beams not supported by piers;
- (21)
damaged foil sarking;
- (22)
air conditioning drains drip outside the building;
- (23)
downpipe not fitted correctly – no sump and overflow;
- (24)
inadequate flashings around windows and sliding doors;
- (25)
wrong size reveals on window;
- (26)
incorrect painting of window architraves;
- (27)
downpipes from top roof drain into lower roof;
- (28)
penetrations not sealed;
- (29)
loose external wall linings;
- (30)
missing insulation;
- (31)
manholes sealed;
- (32)
hallway too narrow;
- (33)
loose tie down straps;
- (34)
temporary formwork not removed;
- (35)
inadequate clearances over doors and windows;
- (36)
no sill framing support;
- (37)
defective framing bolt;
- (38)
private certifier inspection approvals.
- (1)
- [140]
There is no dispute that this work was defective.
- [141]
Nor is there any dispute that the cost of rectifying the defects is the figure of some $300,000 to which I have referred at [16] above.
- [142]
Mr Goodwin drew each of these defects to Mr Roberts’s attention in writing.
- [143]
Mr Corbett said in cross-examination that Mr Roberts:
- [144]
Mr Corbett also gave evidence, in relation to some particular defects, of Mr Roberts giving him an assurance that the defect would be “all fixed”.
- [145]
As it was Mr Roberts that was project managing the construction on the site, and as the construction works were undertaken under Mr Roberts’s supervision, the fact that the defects were not corrected despite Mr Roberts’s assurances that “I’ll fix it” bespeaks his want of care in project managing and supervising the construction work.
- [146]
It is true that there is no evidence pointing to a particular act that Mr Roberts engaged in in relation to these defects.
- [147]
However, as I have mentioned, Mr Roberts did not give evidence in answer to Goodwin’s claim, which enables me to more readily draw an inference that the defects that he constantly assured Goodwin he would “fix” were brought about by a want of care on his part in his project management and supervision of the work and thus his engagement in “construction work” for the purposes of s 36(1) of the DPB Act.
- [148]
I therefore find that Mr Roberts is liable to pay damages to Goodwin for the cost of rectifying the defects.
Conclusion
- [149]
The parties should confer and agree on the orders necessary to give effect to these reasons, including as to costs.